ESI Research · Living Index · Updated 2026-09-22

AI Power Readiness Index

Which markets can support the next generation of 100 MW–2 GW AI infrastructure? ESI separates published market facts from modeled readiness scores, with evidence tiers, source links and transparent weights.

22 markets7 scoring dimensionsPrimary + institutional sourcesNo grid-MW inference from colocation vacancyLiving URL - no year in slug
Markets22North America, Europe, APAC, Middle East
Evidence model7Weighted readiness dimensions
Highest evidence tierTier APublic ≥1-GW-class execution evidence
Last review22 Sep 2026Designed for future updates at the same URLs
Methodological guardrail: commercial colocation availability is shown only as a market fact. It is never treated as spare transmission or grid capacity. A market score is an ESI model output, while each published MW figure retains its original meaning and source.

Build your own power-readiness scenario

Change project size and weights. The default model prioritizes deliverability (30%) and firm power (20%) because current industry research consistently identifies speed-to-power as the primary site-selection constraint.

Scenario controls

Size penalties affect deliverability and scalability only. Tier A/B evidence partially offsets the penalty where public evidence supports large-scale execution.

#MarketScenario score1-GW evidenceConfidenceDelivery posture

All 22 market dossiers

Each market page contains published facts, evidence notes for every score dimension, source provenance and the same integrated scenario tool.

Johor

81

Cushman & Wakefield reported 1,110 MW operational, 602 MW under construction and…

MalaysiaTier ARank #1

Dallas–Fort Worth

78

DFW had 1,432.8 MW of inventory and 39.6 MW of available commercial capacity in …

United StatesTier BRank #2

Alberta

77

Alberta reports ~19,565 MW of requested new data-centre load versus 1,200 MW all…

CanadaTier BRank #3

Helsinki

75

Cushman & Wakefield H1 2026 report indicates Helsinki has crossed the 1.1 GW thr…

FinlandTier ARank #4

Atlanta

74

Atlanta led North America with about 2,882 MW under construction in H1 2026.

United StatesTier BRank #5

Oxagon / NEOM

74

HUMAIN and DataVolt announced 100 MW under development within a 360 MW first pha…

Saudi ArabiaTier BRank #6

Madrid

74

Cushman & Wakefield reports Madrid's operational capacity at 538 MW.

SpainTier ARank #7

Chicago

73

Chicago had 910.6 MW of inventory and 20.0 MW of commercial availability in H1 2…

United StatesTier BRank #8

Québec

73

Hydro-Québec expects data-centre peak demand to exceed 1,000 MW by 2035; project…

CanadaTier CRank #9

Paris

72

Paris had 666.8 MW of inventory and 44.8 MW of availability in Q1 2026.

FranceTier BRank #10

Sydney

72

Cushman & Wakefield reported 917 MW operational and a 2,134 MW development pipel…

AustraliaTier BRank #11

Toronto

72

IESO forecasts data center demand growing from 2.5 TWh to 14 TWh by 2050.

CanadaTier ARank #12

Stockholm

72

Svenska Kraftnät's 10-year plan cites 1,500 km of needed lines.

SwedenTier ARank #13

Melbourne

72

AEMO's 2026 ISP specifically targets data center load.

AustraliaTier BRank #14

Zaragoza

72

Identified in multiple 2025/2026 reports as a key growth location in Southern Eu…

SpainTier BRank #15

Reykjavik

72

Featured in EMEA H2 2025 snapshot reports for extreme high-density AI deployment…

IcelandTier BRank #16

Marseille

71

Consistently ranked as a top-tier secondary connectivity hub in EMEA reports.

FranceTier BRank #17

Santiago

71

CBRE Q1 2025 reports Santiago inventory at 148 MW.

ChileTier BRank #18

Salt Lake City

70

Categorized alongside Reno and Phoenix as primary beneficiaries of secondary hyp…

United StatesTier BRank #19

Oslo

70

Mordor Intelligence reports 430 MW installed (2025), while Statnett lists 11,000…

NorwayTier ARank #20

Las Vegas/Reno

69

Identified by CBRE and JLL as a top-tier emerging market absorbing West Coast hy…

United StatesTier BRank #21

Sao Paulo

69

Maintains position as the largest LATAM market with 493 MW inventory (CBRE Q1 20…

BrazilTier ARank #22

Hillsboro

68

Hillsboro had 491.4 MW of inventory and only 1.1 MW of commercial availability i…

United StatesTier CRank #23

Lisbon

68

Noted by Cushman & Wakefield H1 2026 as a rapidly expanding secondary market.

PortugalTier BRank #24

Riyadh

68

Noted as a key growth spot in the EMEA H2 2025 report.

Saudi ArabiaTier BRank #25

Osaka

68

Ranked #16 globally in the 2026 Data Centre Market Tiering.

JapanTier BRank #26

Milan

67

Identified by JLL and C&W as a primary beneficiary of FLAP-D grid saturation.

ItalyTier BRank #27

Vienna

67

C&W H1 2026 highlights Vienna's continued expansion benefiting from faster power…

AustriaTier BRank #28

Bogota

67

Identified as one of the four largest LATAM markets by CBRE.

ColombiaTier BRank #29

Phoenix

66

Phoenix reached 1,069.2 MW of inventory with 12.1 MW commercially available in H…

United StatesTier CRank #30

Columbus

66

AEP Ohio reported signed binding contracts for 5,642 MW as of early 2026, alongs…

United StatesTier ARank #31

Cardiff-Newport

66

Highlighted in EMEA H2 2025 as a secondary growth market capturing UK demand.

United KingdomTier CRank #32

Dubai

66

Continues expansion as noted in C&W H1 2026, alongside Abu Dhabi.

United Arab EmiratesTier BRank #33

Austin/San Antonio

65

CBRE H1 2025 reported 193 MW operational and 463 MW under construction.

United StatesTier ARank #34

Copenhagen

65

EUDCA reports note Denmark is facing a reckoning over grid strain.

DenmarkTier BRank #35

Chennai

65

Reported at 243 MW capacity as of 2025.

IndiaTier BRank #36

Zurich

65

Maintains steady growth in C&W snapshots but focused on high-value, data-soverei…

SwitzerlandTier BRank #37

Northern Virginia

64

4,496.5 MW of inventory, 10.8 MW of commercial availability and 2,420.2 MW under…

United StatesTier CRank #38

Mumbai

64

CBRE and Cushman & Wakefield place inventory at 667-800 MW.

IndiaTier ARank #39

Abu Dhabi

63

The UAE–US AI Campus was announced at 5 GW; following regional security incident…

United Arab EmiratesTier BRank #40

Kuala Lumpur

63

Listed in the 2025 Global Data Center Market Comparison as a key APAC growth nod…

MalaysiaTier CRank #41

Tokyo

62

Tokyo had 1,086.0 MW of inventory and 6.0% vacancy in Q1 2026.

JapanTier CRank #42

Berlin

62

Highlighted in EMEA MarketBeat 2025 as a key secondary hub attracting diverted F…

GermanyTier BRank #43

Hong Kong

61

Hong Kong had 687 MW of inventory and 18.0% vacancy in Q1 2026.

Hong Kong SARTier CRank #44

Dublin

60

Ireland’s CRU states that data centres grew from 5% of national electricity dema…

IrelandTier DRank #45

Athens

60

Marked as an emerging Southern European market in EMEA overviews.

GreeceTier CRank #46

Queretaro

60

Counted among the top four LATAM markets experiencing rapid investment influx.

MexicoTier BRank #47

Beijing

59

Regulations mandate that data centers in Beijing increase renewable share by 10%…

ChinaTier BRank #48

London

58

CBRE reported 1,338.4 MW of inventory in Q1 2026; 2026 demand is expected to exc…

United KingdomTier CRank #49

Frankfurt

58

Frankfurt had 1,222.5 MW of inventory and 10.3 MW of availability in Q1 2026.

GermanyTier CRank #50

Singapore

58

Singapore had 821 MW of inventory in Q1 2026; the government’s second data-centr…

SingaporeTier DRank #51

Bangkok

58

Recorded 147 MW capacity in early 2022, with continuous pipeline additions track…

ThailandTier BRank #52

Shanghai

58

Listed alongside Tokyo and Mumbai as a powerhouse, with planned developments act…

ChinaTier BRank #53

New York / Tri-State

56

CBRE reported 190.0 MW of inventory and 13.7 MW commercially available in H1 202…

United StatesTier CRank #54

Jakarta

56

Achieved ~370 MW capacity by 2025.

IndonesiaTier BRank #55

Silicon Valley

55

CBRE describes Silicon Valley as one of North America’s most supply-constrained …

United StatesTier CRank #56

Warsaw

54

Reported 157 MW operational capacity dwarfed by a 150 GW grid queue.

PolandTier ARank #57

Amsterdam

52

Amsterdam had 634.0 MW of inventory and 3.9 MW of availability in Q1 2026.

NetherlandsTier DRank #58

Seoul

51

CBRE reports KEPCO restricted power supply to new DC projects in Seoul.

South KoreaTier ARank #59

Taipei

50

Categorized as emerging hyperscale region, limited by geographic isolation.

TaiwanTier CRank #60

Tel Aviv

50

Identified as a secondary market in EMEA reports, though regional conflict has s…

IsraelTier CRank #61

Johannesburg

41

Eskom's systemic load shedding mandates extreme behind-the-meter reliance.

South AfricaTier BRank #62

What the score means - and what it does not

The score is a decision-support model, not a forecast of a guaranteed connection date. It combines public evidence across seven dimensions. Where a source publishes a direct number, ESI displays that number with its original definition. Where no directly comparable number exists, ESI uses a normalized analytical score and labels it as modeled.

Do not read “available MW” as grid headroom. For CBRE markets, available MW refers to commercially available data-centre capacity. Utility/grid headroom is a different variable and is not inferred from it.

Press-ready finding

The AI infrastructure race is increasingly a race for deliverable power, not simply cheap electricity. ESI’s index distinguishes markets with named gigawatt-scale execution evidence from mature markets where demand is high but grid delivery is constrained.

Read the full methodology Download CSV

FAQ

Is this a ranking of spare grid capacity?

No. Public, comparable spare-grid-capacity data does not exist across all 22 markets. The index combines published evidence and a transparent normalized model.

Why no year in the URL?

This is a living research product. The URL stays stable while the evidence date, dataset version and market facts are updated.

Can a 100 MW project rank markets differently from a 1 GW project?

Yes. The interactive model applies a larger scale penalty to deliverability and scalability as requested IT load increases, while markets with direct large-scale execution evidence receive limited relief.