Methodology v2.0 · 2026-09-22

How the AI Power Readiness Index is scored

The methodology is designed to be auditable: facts remain facts, modeled scores remain labeled as model outputs, and uncertain grid headroom is never invented.

Default weights

Power deliverability - 30%

Evidence that large loads can actually be delivered: active construction, allocated power, explicit grid constraints and utility pathways.

Firm power depth - 20%

Depth and reliability of dispatchable or firm electricity supply supporting 24/7 compute.

Scalability / pipeline - 15%

Ability to scale beyond the current installed base, using published pipelines and large-campus evidence.

Power economics - 10%

Relative structural power-economics position. It is not a quoted retail tariff unless a market page explicitly cites one.

Low-carbon supply - 10%

Availability of low-carbon firm power or credible renewable procurement pathways.

Water & climate - 5%

Cooling climate and water stress relevant to high-density AI facilities.

Connection / permitting clarity - 10%

How explicit, predictable and navigable the large-load connection and permitting pathway is.

Evidence tiers

Tier A - direct gigawatt-class evidence

A named ≥1-GW cluster/campus, or evidence of a comparable large-load execution pathway, is publicly committed or under development.

Tier B - large-scale pathway

Strong evidence of hundreds of MW to multi-GW pipeline or dedicated-generation pathway, but no independently verified contiguous 1-GW grid block is assumed.

Tier C - established but constrained

Large market or strong power system, with material connection, policy, cost or siting constraints for a new 1-GW-scale project.

Tier D - allocation/policy constrained

New large loads are explicitly capped, selected, or require special generation/storage conditions.

Source hierarchy

  1. Grid operators, utilities, regulators and government agencies for connection policy and system facts.
  2. Project owners/sponsors for named project capacities and construction status.
  3. Institutional market research such as CBRE, JLL and Cushman & Wakefield for comparable inventory, availability and pipeline data.
  4. Secondary reporting only when primary or institutional evidence is unavailable.

Scoring guardrails

  • Commercial availability ≠ grid headroom. No conversion is made between the two.
  • Pipeline ≠ guaranteed delivery. Construction and planned capacity support scalability but do not prove spare grid capacity.
  • Cost score ≠ tariff quote. It reflects relative structural economics unless a page cites an explicit tariff.
  • No guaranteed delivery year. The final release uses evidence tiers and delivery posture instead of an unsupported point forecast.
  • Confidence is evidence quality. It is not a probability that a project will succeed.

Scenario-size adjustment

The interactive model reduces deliverability and scalability as the requested IT load increases from 100 MW to 2 GW. Tier A and B markets receive limited relief because public evidence demonstrates larger execution pathways. Other dimensions are not automatically changed by project size.

How to cite

Energy Solutions Intelligence (ESI). “AI Power Readiness Index.” Methodology v2.0. Evidence reviewed 2026-09-22. https://energy-solutions.co/reports/ai-power-readiness-index/

Use the model

Scenario controls

Size penalties affect deliverability and scalability only. Tier A/B evidence partially offsets the penalty where public evidence supports large-scale execution.

#MarketScenario score1-GW evidenceConfidenceDelivery posture