Québec AI Data Centre Power Readiness
Hydro-Québec expects data-centre peak demand to exceed 1,000 MW by 2035; projects above 5 MW remain subject to selection.
Tier C evidence
Not a utility rating or guaranteed connection outcome.
Why the model scores Québec this way
Every 0–100 input below is an ESI normalised analytical score. The text under each bar states the evidence basis; direct facts remain separately sourced above.
Selection process prevents treating Québec as an unconstrained 1-GW connection market.
Sector demand is expected to exceed 1 GW by 2035, while major new generation is planned.
Proposed large-data-centre rate averages about C$0.13/kWh; this is not a universal project all-in cost.
Hydro-heavy system supports the highest low-carbon score in the index.
Cool climate is highly favorable.
Rules are clear, but discretionary project selection limits certainty.
Sources and provenance
Where multiple sources use different definitions, ESI does not merge the numbers into a single synthetic figure.
Compare Québec against all markets
The exact same interactive model is embedded on every market page so readers can reproduce the default result or change their assumptions.
Scenario controls
Size penalties affect deliverability and scalability only. Tier A/B evidence partially offsets the penalty where public evidence supports large-scale execution.
| # | Market | Scenario score | 1-GW evidence | Confidence | Delivery posture |
|---|
Related markets
Compare Québec with other leading AI data centre markets by power readiness.