Tax Credits & Subsidies · United Kingdom · Verified Nov 2026

United Kingdom: CfD Allocation Round 6 (AR6) Results & Delivery Audit

Published by DESNZ on 3 September 2024 under a £1.555 billion revised budget, UK CfD Allocation Round 6 (AR6) awarded 131 contracts totaling 9,648.26 MW (~9.65 GW) across Solar PV (£50.07/MWh), Onshore Wind (£50.90/MWh), Tidal Stream (£172.00/MWh), Floating Wind (£139.93/MWh), and Fixed-Bottom Offshore Wind (£58.87/MWh new; £54.23/MWh Permitted Reduction, all 2012 base). Following Ørsted's 7 May 2025 exit from the 2,400 MW Hornsea 4 contract, ~7.25 GW remains active toward 2026–2029 delivery.
131 Contracts Awarded 9.65 GW Gross / 7.25 GW Active 2012 Base CPI Indexed
Primary sources: DESNZ AR6 Official Results · LCCC CfD Register. Verified Nov 2026.
AR6 Gross Cleared
9,648.26 MW
131 contracts under £1.555B revised budget
Pot 1 Solar PV
£50.07/MWh
2012 base (~£72.27/MWh in 2026); 3,288.31 MW
Pot 3 Offshore Wind
£58.87 / £54.23
New / Permitted Reduction (2012 base)
2025 Attrition Shock
-2,400 MW
Hornsea 4 discontinued 7 May 2025 (~25% of AR6)

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
CfD Allocation Round 6 (Pot 1: Solar & Onshore)
Established Renewables 15-Year CPI Contracts
Awarded (2026–2028 Delivery) DESNZ / LCCC Results 3 Sep 2024; Delivery Years 2026/27–2027/28 Solar PV: 3,288.31 MW @ £50.07/MWh; Onshore Wind: 990.37 MW @ £50.90/MWh (2012 base)
CfD AR6 Pot 2 (Floating Wind & Tidal Stream)
Emerging Marine Ringfence & FLOW
Awarded (Active Pre-FID / Build) DESNZ / LCCC Results 3 Sep 2024; 15-year CPI term Green Volt: 400.00 MW @ £139.93/MWh; Tidal: 28.00 MW (6 contracts) @ £172.00/MWh
CfD AR6 Pot 3 (Fixed Offshore & Permitted Reduction)
New Capacity & AR4 Re-Bid Window
Partially Active (Hornsea 4 Exited) DESNZ / LCCC Delivery Years 2027/28–2028/29; Hornsea 4 exit 7 May 2025 New: 3,363.07 MW @ £58.87/MWh (£84.97/MWh in 2026); PR: 1,578.51 MW @ £54.23/MWh
Non-Delivery Disincentive & Supplier Obligation
S.I. 2014/2014 & CfD Allocation Regulations
Enacted & Enforced LCCC / DESNZ Active 2024–2026 (ILR quarterly resets) Zero-hour negative IMRP suspension; site re-bid lockouts on failure; Q4 2026 ILR reset to £0.000/MWh

Multi-Pot Clearing Schedule: Pots 1, 2, and 3 Under the £1.555B Revised Budget

AR6 bridged the blank AR5 offshore outcome (2023) and AR7's 20-year, 2024-price-base reset. After expanding the budget by £530 million in July 2024 to £1.555 billion (2011/12 prices), DESNZ cleared 131 contracts totaling 9,648.26 MW on 3 September 2024.

While our AR7–AR8 Offshore Wind CfD Dossier examines 20-year contracts and Clean Industry Bonus gating, AR6 stands apart for its Pot 1 and Pot 2 breadth: 93 solar PV projects (>5 MW) secured 3,288.31 MW at £50.07/MWh, alongside 22 onshore wind contracts totaling 990.37 MW at £50.90/MWh (2012 base). Energy from Waste with CHP, remote island wind, wave, and geothermal recorded zero cleared MW.

Auction Pot & Technology Contracts Awarded MW 2012 ASP Cap Clearing Strike (2012 Base) 2024 Clearing / 2026 LCCC Indexed
Pot 1: Solar PV (>5 MW)
Delivery Years 2026/27 & 2027/28
93 3,288.31 MW £61.00/MWh £50.07/MWh ~£69.87/MWh (2024) / ~£72.27/MWh (2026)
Pot 1: Onshore Wind (>5 MW)
England, Scotland & Wales
22 990.37 MW £64.00/MWh £50.90/MWh ~£71.03/MWh (2024) / ~£73.47/MWh (2026)
Pot 2: Tidal Stream (Ringfenced)
5 sites across Wales & Scotland
6 28.00 MW £261.00/MWh £172.00/MWh ~£240.04/MWh (2024) / ~£248.25/MWh (2026)
Pot 2: Floating Offshore Wind
Green Volt (Scottish North Sea)
1 400.00 MW £176.00/MWh £139.93/MWh ~£195.29/MWh (2024) / ~£201.97/MWh (2026)
Pot 2: Geothermal / Wave / ACT / EfW
Eligible technologies with zero awards
0 0.00 MW £157–£257/MWh No award Unallocated in AR6
Pot 3: Offshore Wind (New Capacity)
Hornsea 4 (2,400 MW) & East Anglia Two (963.07 MW)
2 3,363.07 MW £73.00/MWh £58.87/MWh ~£82.16/MWh (2024) / £84.97/MWh (LCCC 2026)
Pot 3: Offshore Wind (Permitted Reduction)
AR4 25% trim re-bids across 4 wind farms
7 1,578.51 MW £73.00/MWh £54.23/MWh ~£75.68/MWh (2024) / ~£78.27/MWh (2026)
Total AR6 Auction Outcome
Gross cleared prior to May 2025 attrition
131 9,648.26 MW £1.555B Budget 15-Year CPI Term ~7,248.26 MW active post-Hornsea 4 exit

Pot 1: Solar & Onshore Spread

Solar PV cleared 17.9% below its £61/MWh cap across sub-50 MW arrays and NSIPs such as 60 MW Horton Wood. Onshore wind cleared 20.5% beneath its £64/MWh cap, led by Scottish projects.

Pot 2: Marine Compression

Tidal stream cleared 34% under the £261/MWh ASP at £172/MWh across HydroWing (10 MW), MeyGen (9 MW), Seastar (4 MW), Magallanes (3 MW), and Ocean Star Tidal (2 MW). Green Volt cleared 20.5% under its £176/MWh cap.

Pot 3: Permitted Reduction

AR4 offshore winners holding £37.35/MWh awards trimmed up to 25% of AR4 capacity and re-bid at £54.23/MWh, lifting blended SPV cashflow enough to unlock FID on Inch Cape, Hornsea 3, and East Anglia Three.

2012-to-2026 CPI Strike-Price Conversion and LCCC Supplier Obligation Impact

DESNZ published AR6 prices in 2012 real terms, whereas LCCC settles every MWh in current nominal pounds after compounding twelve-plus years of CPI inflation.

Each April at the contract Indexation Anniversary, LCCC recalculates Adjusted Strike Prices for cumulative UK CPI inflation alongside Balancing Services Use of System (BSUoS) and Transmission Loss Multiplier (TLM) adjustments. At the September 2024 auction, the CPI factor (~1.396x) placed £58.87/MWh offshore wind near £82.16/MWh and £50.07/MWh solar near £69.87/MWh. By 2026, LCCC's live Schemes Register listed East Anglia Two and Hornsea Project Four at £84.97/MWh (1.443x over 2012), placing Pot 1 solar near £72.27/MWh and onshore wind near £73.47/MWh. To remove this 2012-base distortion, DESNZ re-based AR7 and AR8 to 2024 real terms alongside a 20-year offshore tenor.

CPI vs. Offshore EPC Inflation

UK CPI tracks consumer goods rather than marine steel, HVDC converters, or installation vessels. Between September 2024 and May 2025, specialised offshore CAPEX and capital costs moved faster than CPI, compressing pre-FID equity margins on fixed-real contracts.

LCCC Interim Levy Rate (2025–2026)

LCCC funds net payouts via quarterly Interim Levy Rates (ILR) on GB suppliers under S.I. 2014/2014: Q1 2025 opened at £7.608/MWh, Q1 2026 rose to £10.576/MWh (TRA £332.5M), Q3 2026 was cut in-period to £2.068/MWh in August 2026, and Q4 2026 dropped to £0.000/MWh in November 2026.

Hornsea 4 Discontinuation, Non-Delivery Penalties, and Flagship Delivery Tracker

Between January 2025 and late 2026, AR6's flagship portfolio diverged sharply between projects reaching construction and a 2.4 GW exit that removed a quarter of the round.

On 7 May 2025, Ørsted discontinued the 2,400 MW Hornsea 4 project in its AR6 form and terminated supply contracts, with formal LCCC register termination logged in July 2025. Ørsted cited supply-chain CAPEX escalation, higher capital costs, and execution risk that eroded equity value creation even at ~£84.97/MWh indexed pricing, absorbing break-away write-downs while preserving seabed rights, grid agreements, and its Development Consent Order.

Project & Sponsor AR6 Pot & MW Strike Price (2012 / 2026) 2025–2026 Contractual & Build Status Commercial & Regulatory Driver
Hornsea 4
Ørsted (North Sea)
Pot 3 New
2,400.00 MW
£58.87 / £84.97 Discontinued / Terminated
Halted 7 May 2025; LCCC exit Jul 2025
Supply-chain CAPEX escalation & execution risk eroded equity returns; subject to NDD site re-bid lockouts
Hornsea 3
Ørsted (2.85+ GW total)
Pot 3 PR
1,080.00 MW
£54.23 / ~£78.27 Active Offshore Construction
Marine logistics & foundation build 2025–2026
Blended AR4 + AR6 PR revenue stabilised FID; dedicated vessels & aviation contracted into 2026
East Anglia Two
ScottishPower Renewables
Pot 3 New
963.07 MW
£58.87 / £84.97 Construction Underway
Substation civils 2025; HDD landfalls 2026
Sole surviving Pot 3 New build after Hornsea 4 exit; onshore cable corridor & crane orders progressing
Inch Cape
ESB / Red Rock Renewables (1,080 MW)
Pot 3 PR
266.00 MW
£54.23 / ~£78.27 Financial Close & Offshore Build
£3.5B financial close 27 Jan 2025
AR6 Permitted Reduction slice closed the funding gap across the 1,080 MW Firth of Forth array
East Anglia Three
ScottishPower / Iberdrola (1,400 MW)
Pot 3 PR
158.90 MW
£54.23 / ~£78.27 Heavy Offshore Construction
Commissioning ramp 2026
AR6 PR top-up complemented AR4 core CfD, keeping 1.4 GW East Anglian build on 2026 schedule
Moray West (String 9)
Ocean Winds (Moray Firth)
Pot 3 PR
73.50 MW
£54.23 / ~£78.27 Late-Stage / Operational Transition
Delivery Year 2027/28
Targeted PR allocation supplemented merchant PPA and AR4 capacity on String 9
Green Volt
Flotation Energy / Vårgrønn
Pot 2 FLOW
400.00 MW
£139.93 / ~£201.97 Pre-FID / Supply Chain Reservation
28x15 MW turbine & Aberdeen port deals 2026
World's largest commercial floating wind farm; backed by offshore oil-platform electrification demand
Pot 1 Solar PV Portfolio
93 Utility Solar SPVs (10–60 MW)
Pot 1 Solar
3,288.31 MW
£50.07 / ~£72.27 Active Pre-Build & Grid Queue
Delivery Years 2026/27 & 2027/28
Module price deflation improved equity IRR, though DNO/TNUoS connection dates govern energisation

Hornsea 4's withdrawal spotlighted DESNZ's Non-Delivery Disincentive (NDD) rules: terminating before the Milestone Delivery Date triggers statutory site-exclusion penalties barring immediate re-entry for roughly 13 to 24 months (one to two cycles). Ørsted confirmed no immediate AR7 or AR8 re-bid, while DESNZ tightened DCO maturity and surrendered-capacity rules ahead of AR7–AR8 and Offshore Wind Marshalling Ports expansion.

Pot 1 Solar vs. Corporate PPAs, Negative-Pricing Exposure, and Equity Structuring

Three commercial mechanics govern realised equity yield on AR6 portfolios relative to unsubsidised bilateral power contracts.

Solar PV: £50.07/MWh vs. PPAs

At ~£72/MWh in 2026 terms, Pot 1 solar CfDs rival 10-to-12-year corporate PPAs while avoiding buyer credit migration and post-year-10 merchant tail exposure. Model returns in the Solar Calculator and LCOE Calculator.

Zero-Hour Negative Pricing

AR6 enforces zero-hour negative-price tolerance: whenever the GB day-ahead IMRP falls below £0/MWh in any hour, LCCC suspends top-up payments, creating an immediate curtailment or co-located storage signal.

Market Stack Interactions

CfD assets cannot stack the UK Capacity Market, sub-5 MW solar uses the Smart Export Guarantee (SEG), and North Sea sponsors benchmark AR6 against Belgium's Princess Elisabeth Zone.

Before secondary SPV acquisitions, equity committees should confirm 18-month Milestone Requirement satisfaction on the LCCC register, check Target Commissioning Window erosion against Longstop termination, and benchmark yield against our Solar Degradation, Onshore Wind, and Offshore Wind Economics studies.

Executive Regulatory Q&A

How much capacity and how many projects cleared in UK CfD Allocation Round 6?
Published by DESNZ on 3 September 2024 under a revised £1.555 billion budget (2011/12 prices), AR6 awarded 131 contracts totaling 9,648.26 MW (~9.65 GW) across three pots. Pot 1 cleared 3,288.31 MW of solar PV (93 projects at £50.07/MWh) and 990.37 MW of onshore wind (22 projects at £50.90/MWh). Pot 2 cleared 28.00 MW of tidal stream (6 projects at £172.00/MWh) and 400.00 MW of floating wind (Green Volt at £139.93/MWh). Pot 3 cleared 3,363.07 MW of new fixed-bottom offshore wind (£58.87/MWh) plus 1,578.51 MW of AR4 Permitted Reduction re-bids (£54.23/MWh).
How do AR6 2012-base strike prices convert into 2024 and 2026 nominal LCCC rates?
AR6 clearing prices were denominated in 2012 real terms and are adjusted each April by the Low Carbon Contracts Company (LCCC) using Consumer Prices Index (CPI) inflation plus transmission loss and balancing charge adjustments. At auction clearing in 2024, the £58.87/MWh offshore wind strike price equated to roughly £82.16/MWh, while by 2026 the LCCC Schemes Register listed Hornsea 4 and East Anglia Two at a Current Strike Price of £84.97/MWh (roughly 1.443x the 2012 base). On the same basis, £50.07/MWh solar PV scales to roughly £69.87/MWh in 2024 terms and ~£72.27/MWh in 2026.
What happened to Ørsted's 2,400 MW Hornsea 4 AR6 CfD contract in May 2025?
On 7 May 2025, Ørsted announced it would discontinue the 2,400 MW Hornsea 4 offshore wind project in its existing AR6 form and terminate supply-chain contracts, citing supply-chain cost escalation, higher capital costs, and execution risk. Because Hornsea 4 represented roughly 25% of AR6's total contracted capacity, its withdrawal reduced the deliverable AR6 pipeline from 9.65 GW to ~7.25 GW, with formal contract termination recorded on the LCCC register in July 2025.
How do Non-Delivery Disincentive rules affect re-bidding after Hornsea 4 or missed milestones?
Under the Contracts for Difference (Allocation) Regulations, if a generator fails to sign an offered CfD within the statutory window or terminates before satisfying the Milestone Delivery Date, the Non-Delivery Disincentive (NDD) bars that site from re-entering subsequent allocation rounds for a statutory exclusion period spanning roughly 13 to 24 months (or the next one to two allocation cycles depending on the breach). Subsequent DESNZ reforms for AR7 and AR8 further tightened rules governing previously surrendered capacity.
What is Permitted Reduction and which AR6 offshore projects moved into construction in 2025-2026?
Permitted Reduction allowed AR4 offshore wind projects facing post-2022 cost inflation to relinquish up to 25% of their AR4 capacity without penalty and re-bid it in AR6 at £54.23/MWh (2012 prices). Four projects cleared 1,578.51 MW under this route: Hornsea 3 (1,080 MW), Inch Cape (266 MW), East Anglia Three (158.9 MW), and Moray West String 9 (73.5 MW). By 2025-2026, Inch Cape reached £3.5 billion financial close on 27 January 2025, Hornsea 3 and East Anglia Three progressed through active offshore construction, East Anglia Two (963.07 MW) advanced onshore cable landfalls, and Green Volt (400 MW) signed turbine and port agreements.
How do Pot 1 AR6 solar PV contracts at £50.07/MWh compare against corporate PPAs and negative pricing?
AR6 solar PV cleared 93 projects (3,288.31 MW) at £50.07/MWh (2012 base), indexing to roughly £72/MWh in 2026 nominal money over a 15-year CPI-linked term. While corporate physical PPAs offer shorter 10-to-12-year horizons and bilateral counterparty exposure, AR6 CfDs carry LCCC settlement backed by the statutory Supplier Obligation. However, AR6 solar and wind assets remain exposed to the zero-hour negative pricing rule, where LCCC pays zero difference top-up during any single settlement hour with a negative Intermittent Market Reference Price.

Official Statutory Registers & Primary Filings

All AR6 clearing prices, awarded megawatts, 2026 CPI-indexed strike prices, LCCC levy determinations, and Hornsea 4 contract-exit milestones are verified directly against official UK government, LCCC, and corporate regulatory filings as of November 2026.

Regulatory Verification & Primary Basis

Every clearing figure, CPI conversion factor, and post-award milestone in this dossier is anchored directly to primary DESNZ auction publications, LCCC counterparty registers, UK statutory instruments, and stock-exchange corporate disclosures. ESI strictly separates gross auction awards from active deliverable capacity.

Mechanism Status Authority Effective Window Key Threshold
Energy Act 2013 & CfD (Allocation) Regulations 2014
AR6 Auction Clearing & NDD Enforcement
Enacted & Active UK Parliament / DESNZ 3 Sep 2024 awards; 15-yr CfD tenor 131 contracts / 9,648.26 MW cleared; NDD site lockout on breach
LCCC Strike Price Indexation & S.I. 2014/2014
Annual CPI Escalation & Supplier Obligation
Active Settlement (2025–2026) LCCC Annual April indexation; quarterly ILR £58.87 (2012) indexed to £84.97/MWh (2026); Q4 2026 ILR £0.000/MWh
AR6 Post-Award Attrition & FID Ledger
Contract Delivery vs. Termination Tracking
7.25 GW Active / 2.4 GW Exited LCCC Register / Sponsors Jan 2025–Nov 2026 milestones Hornsea 4 (-2,400 MW) exited May/Jul 2025; Inch Cape FID Jan 2025
Primary-Source AnchoringAR6 pot totals, strike prices, Permitted Reduction shares, and 2026 rates are verified against DESNZ tables and the LCCC Schemes Register.
Underwriting & Diligence ProtocolBefore equity deployment, confirm Milestone Requirement status on the LCCC register, Target Commissioning Window buffers, and grid dates.
Authored & Verified by Khaled Shawky · Chief Energy Systems & Policy Editor, Energy Solutions Intelligence Verification Cycle: November 2026