| Mechanism | Status | Authority | Effective Window | Key Threshold |
|---|---|---|---|---|
| CfD Core Offshore Wind Contract (Pot 3 & Pot 4) Energy Act 2013 Two-Way Revenue Settlement |
Active (AR7 Awarded; AR8 Open) | DESNZ / NESO / LCCC | AR7 awards Jan 2026; 20-year CPI-indexed term | AR7 clearing: £91.20/MWh E&W fixed, £89.49/MWh Scotland fixed, £216.49/MWh floating (2024 prices) |
| Clean Industry Bonus (CIB / Sustainable Industry Rewards) S.I. 2024 & S.I. 2025/903 Supply-Chain Gate |
Mandatory Pre-Gate (AR7–AR8) | DESNZ / LCCC | AR7 (£544m) through AR8 (£515m); AR9 onshore review | £100m/GW minimum standard (fixed-bottom); ~£27m/GW indicative extra ceiling (£20.1m/GW AR7 baseline) |
| AR8 Contract Budget Notice & ASP Schedule Sealed-Bid Cross-Pot Budget Screening |
Notional Initial Pass | DESNZ / HM Treasury | Notice published 19 Nov 2026; budget decision early 2027 | £1 notional initial budget for Pots 1–4 (£0 final Pot 5); ASPs held at £113/MWh fixed, £271/MWh floating |
| REMA Reformed National Pricing (RNP) Wholesale Market & Grid Charging Framework |
Confirmed National Market | DESNZ / Ofgem / NESO | Decision 10 Jul 2025; delivery plan ongoing | Zonal wholesale split rejected; single GB IMRP retained with TNUoS & constraint reform |
Under Part 2 of the Energy Act 2013, a UK offshore wind CfD is a private-law contract between a project Special Purpose Vehicle (SPV) and the Low Carbon Contracts Company (LCCC), awarded via NESO sealed-bid auctions.
For each metered megawatt-hour exported, LCCC compares the CPI-indexed Strike Price against the Intermittent Market Reference Price (IMRP), derived from day-ahead hourly GB wholesale auctions. LCCC pays the positive delta when IMRP sits below Strike; the SPV remits the surplus when IMRP clears above Strike.
LCCC funds net payouts through the statutory Supplier Obligation levied on licensed GB electricity suppliers under S.I. 2014/2014. Quarterly Interim Levy Rates (ILR) and Total Reserve Amounts (TRA) were amended by S.I. 2025/903 to include Clean Industry Bonus costs.
Through AR6, DESNZ published strike prices in 2012 real terms, forcing analysts to compound a decade of CPI inflation. From AR7 into AR8, DESNZ re-based published ASPs and clearing prices to 2024 real terms while keeping annual CPI indexation across the contract.
Auction outcomes from 2022 through late 2026 illustrate how inflation and supply bottlenecks forced a structural reset of UK offshore wind procurement.
In Allocation Round 4 (July 2022), intense bidding cleared roughly 6,994 MW (7 GW) of fixed-bottom wind at £37.35/MWh (2012 prices). Within twelve months, steel plate, subsea HVDC cable, turbine, and installation vessel rates surged globally. When DESNZ capped AR5 (September 2023) at £44/MWh (2012 prices), every offshore wind developer withheld bids, leaving AR5 with 0 MW awarded.
DESNZ corrected course in two phases. AR6 (September 2024) lifted the fixed-bottom ASP to £73/MWh and floating ASP to £176/MWh (2012 prices), awarding 3,363 MW of new fixed capacity at £58.87/MWh, 1,578 MW of AR4 Permitted Reduction re-bids at £54.23/MWh, and 400 MW of floating wind (Green Volt) at £139.93/MWh. AR7 (14 January 2026) then re-based ASPs to 2024 prices (£113/MWh fixed, £271/MWh floating), extended contract length to 20 years, and awarded 8,437.5 MW at 19.3% to 20.1% below ASP caps. In AR8 (19 November 2026), DESNZ held those ASPs flat but set £1 notional initial budgets across Pots 1 to 4 so ministers and HM Treasury can inspect anonymised bid stacks before releasing final budgets in early 2027.
| Allocation Round | Price Base | Fixed-Bottom ASP | Fixed-Bottom Clearing & MW | Floating ASP / Clearing & MW | Key Structural Rule |
|---|---|---|---|---|---|
| AR4 Results 7 Jul 2022 |
2012 CPI | £46.00/MWh | £37.35/MWh · 6,994 MW (5 projects) | £116.00/MWh ASP · 32 MW (TwinHub) | First offshore round with zero-hour negative pricing rule; 15-year contract term |
| AR5 Results 8 Sep 2023 |
2012 CPI | £44.00/MWh | 0 MW (zero offshore bids submitted) | £116.00/MWh ASP · 0 MW | ASP cap failed to absorb 2022–2023 turbine, steel, and marine CAPEX inflation |
| AR6 Results 3 Sep 2024 |
2012 CPI | £73.00/MWh | £58.87/MWh new (3,363 MW) £54.23/MWh PR (1,578 MW) |
£176.00/MWh ASP £139.93/MWh · 400 MW (Green Volt) |
Permitted Reduction (PR) allowed up to 25% of AR4 capacity to re-bid; 15-year term |
| AR7 Results 14 Jan 2026 |
2024 CPI | £113.00/MWh (£81 in 2012 base) |
£91.20/MWh E&W (6,865 MW) £89.49/MWh Scot (1,380 MW) |
£271.00/MWh ASP £216.49/MWh · 192.5 MW |
20-year tenor introduced; Clean Industry Bonus (£544m final pool) mandatory pre-gate |
| AR8 Notice 19 Nov 2026 |
2024 CPI | £113.00/MWh | Pending 2027 award (£1 notional Pot 3 initial budget) |
£271.00/MWh ASP (£1 notional Pot 4 initial budget) |
Cross-pot anonymised bid inspection before HM Treasury budget unlock; £515m CIB; Pot 5 £0 |
AR7 was the largest single offshore wind procurement in UK history, contracting 8,245 MW of fixed-bottom generation in Pot 3 and 192.5 MW of floating capacity in Pot 4. Notably, England and Wales projects cleared at £91.20/MWh while Scotland's Berwick Bank Phase B cleared at £89.49/MWh (2024 prices), reflecting competitive bid dynamics and locational cost trade-offs.
| Project / CfD Unit | Sponsor Group & Nation | Technology Pot | Awarded Capacity | Strike Price (2024 Base) | 2012 Base Equivalent |
|---|---|---|---|---|---|
| Norfolk Vanguard East Units A (1,380 MW), B (90 MW), C (75 MW) |
RWE / KKR · England | Pot 3 (Fixed-Bottom) | 1,545.0 MW | £91.20 / MWh | £65.45 / MWh |
| Norfolk Vanguard West Units A (1,380 MW), B (90 MW), C (75 MW) |
RWE / KKR · England | Pot 3 (Fixed-Bottom) | 1,545.0 MW | £91.20 / MWh | £65.45 / MWh |
| Dogger Bank South East CfD Unit A |
RWE / Masdar · England | Pot 3 (Fixed-Bottom) | 1,500.0 MW | £91.20 / MWh | £65.45 / MWh |
| Dogger Bank South West CfD Unit A |
RWE / Masdar · England | Pot 3 (Fixed-Bottom) | 1,500.0 MW | £91.20 / MWh | £65.45 / MWh |
| Berwick Bank Phase B Single Scottish Pot 3 Award |
SSE Renewables · Scotland | Pot 3 (Fixed-Bottom) | 1,380.0 MW | £89.49 / MWh | £64.23 / MWh |
| Awel y Môr Offshore Wind Farm A Irish Sea Development |
RWE / Partners · Wales | Pot 3 (Fixed-Bottom) | 775.0 MW | £91.20 / MWh | £65.45 / MWh |
| Erebus Floating Offshore Wind Celtic Sea (2029/30 delivery) |
Blue Gem Wind · Wales | Pot 4 (Floating) | 100.0 MW | £216.49 / MWh | £155.37 / MWh |
| Pentland Floating Offshore Wind Dounreay Coast (2029/30 delivery) |
CIP / GB Energy / NWF · Scotland | Pot 4 (Floating) | 92.5 MW | £216.49 / MWh | £155.37 / MWh |
Notice how multi-unit phasing shaped Norfolk Vanguard East and West: splitting each 1,545 MW site into Units A, B, and C gives sponsors commercial flexibility to align Target Commissioning Dates with staged onshore HVDC substation energisation and submarine export cable factory slots. Meanwhile, the £90.91/MWh capacity-weighted fixed offshore wind average in 2024 terms masks the spread between North Sea / Irish Sea Transmission Network Use of System (TNUoS) tariffs and Scottish transmission charges, which remain a primary driver of bid dispersion even under a unified national wholesale price.
Replaced the legacy Supply Chain Plan as a hard financial gate, the Clean Industry Bonus (Sustainable Industry Rewards) links CfD eligibility directly to UK manufacturing, coastal port capacity, and verified supplier decarbonisation.
Under the Sustainable Industry Rewards Regulations 2024, offshore wind applicants must clear DESNZ's CIB Minimum Standard before entering the main CfD auction (around £100m/GW baseline investment into deprived-area supply chains or Science-Based Target suppliers in AR7). Developers may then submit competitive "CIB extra" bids for bonus revenue around an indicative £27m/GW ceiling (£20.1m/GW final AR7 notice baseline).
Oversubscribed AR7 proposals prompted DESNZ to lift the CIB pool from ~£204m to £544m, embedded into LCCC levy rules via S.I. 2025/903. For AR8, DESNZ set a £515m CIB budget and shifted to payment-on-delivery milestones, interim Fair Work Charter labour terms, and mandatory skills-fund contributions, while deferring onshore wind CIB entry (£25m/GW proposed) to AR9.
For sponsors, CIB obligations create binding pre-FID procurement risk. Commitments to UK monopile yards or offshore wind marshalling ports must be backed by enforceable OEM contracts before bidding, as S.I. 2026 regulations expose unsubstantiated industrial pledges to forfeiture. Tight HVDC converter station supplier concentration further narrows post-award vendor substitution.
Two structural risk variables govern realised cash flow per generated MWh for AR7 and AR8 offshore wind assets: hourly negative-price payment suspension and Great Britain's settled decision to reject zonal wholesale pricing.
AR2 and AR3 CfDs only suspended difference payments after six consecutive hours of negative IMRP. Since AR4, and continuing across AR6, AR7, and AR8, standard CfD terms enforce zero tolerance: any single settlement hour where the IMRP clears below £0/MWh receives zero LCCC top-up. During high-wind overnight periods, offshore wind SPVs face an immediate economic stop-signal to curtail output or route power into co-located electrolysers or storage.
In its 10 July 2025 REMA Summer Update, DESNZ formally ruled out splitting Great Britain into locational wholesale pricing zones. Had zonal pricing passed, Scottish projects like Berwick Bank Phase B and Pentland would have faced deep wholesale price discounts relative to southern demand centres, complicating CfD reference pricing. Confirming Reformed National Pricing (RNP) keeps a single GB IMRP across all offshore CfDs.
Retaining a national wholesale price under RNP shifts locational discipline onto Transmission Network Use of System (TNUoS) charges, connection queue reform, and NESO balancing-market curtailment mechanics. Because CfDs settle on metered export (with separate Balancing Mechanism rules), Scottish and North Sea assets must still model rising TNUoS tariff volatility and grid-reinforcement timing delays when bidding into AR8.
Evaluating an AR7 or AR8 offshore wind SPV requires separating headline strike prices from actual net cash yield, construction inflation exposure, and contract forfeiture triggers.
Extending the CfD term from 15 to 20 years reshapes infrastructure equity returns by amortising offshore export and foundation CAPEX over five additional CPI-linked revenue years, trimming required bid strike prices in ESI LCOE Calculator and Project Finance Model runs while compressing late-life merchant cannibalisation. For direct equity sponsors and asset-backed sukuk tranches alongside sovereign co-investors such as Great British Energy and the National Wealth Fund (as on Pentland), the 20-year CPI stream delivers transparent inflation protection.
Three underwriting hazards remain critical: (1) real EPC and vessel inflation outpacing UK CPI between auction clearing and FID; (2) Milestone Requirement compliance within 18 months of CfD signature and Target Commissioning Window erosion before Longstop termination; and (3) rising hourly negative-price curtailment exposure unless assets pair flexible dispatch or DESNZ Hydrogen Allocation Round industrial offtake.
In AR8, the £1 notional budget mechanism heightens auction-clearing uncertainty ahead of HM Treasury's early-2027 pot unlock, prompting multi-unit sponsors to evaluate splitting consented capacity between CfD bids and long-dated physical corporate PPAs. Compare generation economics in our 2026 Offshore Wind Economics Benchmark and UK Capacity Market Auctions Dossier.
Every statutory citation, clearing price, capacity figure, and rule change in this dossier is verified directly against primary UK government, Parliamentary legislation, and LCCC counterparty publications as of November 2026.
Every statutory parameter, clearing strike price, and contract condition in this dossier is anchored directly to primary UK legislation, DESNZ ministerial notices, NESO auction outputs, and LCCC counterparty rules. ESI separates enacted legal obligations from project-level commercial projections.
| Mechanism | Status | Authority | Effective Window | Key Threshold |
|---|---|---|---|---|
| Energy Act 2013 & S.I. 2014/2014 CfD & Supplier Obligation Core Statute |
Enacted & Active | UK Parliament / LCCC | 2013–Present (20-yr AR7+ term) | Zero-hour negative IMRP suspension; quarterly ILR levy |
| S.I. 2025/903 & SIR Regs 2024/2026 Clean Industry Bonus Legal Basis |
Enacted & Active | DESNZ / LCCC | AR7 (£544m) through AR8 (£515m) | Mandatory minimum standard gate; payment-on-delivery (AR8) |
| AR8 Budget Notice & REMA RNP 2026–2027 Allocation & Market Rules |
Active Notice (Nov 2026) | DESNZ / HM Treasury / NESO | AR8 bids 2026–2027; RNP ongoing | £1 initial Pots 1–4; £113 fixed / £271 floating ASP (2024 base) |
Connect UK offshore CfD rules directly to port marshalling constraints, HVDC converter backlogs, and levelised generation models.