Türkiye YEKA Zones: 2024–2026 Auction Rules & Economics

Türkiye's Renewable Energy Resource Zones (YEKA) framework under Law No. 5346 allocates utility-scale solar (GES) and wind (RES) grid capacity through two-stage auctions managed by MENR. Following the USD-denominated 2024 rounds (2,000 MW), MENR pivoted to Euro floors in 2025–2026: 3.25 EUR cents/kWh for solar and 3.50 EUR cents/kWh for wind, paired with ascending upfront Katkı Payı bids (€/MW), a 60-month (GES) or 72-month (RES) merchant sales window, 20-year state off-take, and accelerated land permitting under Law No. 7554.
Law No. 5346 & Law No. 7554 2025–2026 Floors: 3.25€c / 3.50€c 2,285 MW Awarded Nov 2026
2026 YEKA Tenders
2,285 MW
1,500 MW RES + 785 MW GES (Nov 2026)
2025–2026 Floor Rates
3.25€c / 3.50€c
EUR/kWh floor (5.50€c ceiling) · 20-yr PPA
Merchant Sales Window
60 / 72 Mos
From contract signing (GES / RES)
Peak 2025 Katkı Payı
€312k / MW
R25-Balıkesir-3 RES (€285k/MW GES)

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
Türkiye YEKA Renewable Energy Resource Zones
Law No. 5346 · YEKA Regulation (Amended Dec 2025)
Active Annual Cadence Ministry of Energy & Natural Resources (MENR) / EPDK / TEİAŞ 2024–2035 Roadmap (2+ GW/yr toward 120 GW solar+wind) 5.50€c ceiling; 3.25€c (GES) & 3.50€c (RES) floors; 60/72-mo merchant + 20-yr PPA; 75% PV / 55% wind local content

Three Distinct Waves of Türkiye's YEKA Model

Established under Law No. 5346 and the YEKA Regulation (Official Gazette No. 29852 of 9 October 2016, most recently amended via Official Gazette No. 33102 on 9 December 2025), YEKA functions very differently from Türkiye's standard YEKDEM feed-in tariff mechanism. Rather than granting uniform administrative collars to projects that obtain private land and grid rights independently, YEKA pre-designates transmission capacity and zone parcels through competitive auctions administered by the General Directorate of Energy Affairs (EİGM).

Wave 1 (2017–2019): Mega-Sites & Factory Mandates

The inaugural rounds anchored heavy industrial localization. YEKA GES-1 (2017, 1,000 MW at Konya-Karapınar) cleared at 6.99 USD cents/kWh and required the Kalyon-Hanwha consortium to build a domestic ingot-to-module manufacturing complex in Ankara. On the wind side, YEKA RES-1 (2017, 1,000 MW) cleared at 3.48 USD cents/kWh with a turbine plant obligation, but stalled and was terminated under Electricity Market Law provisions. MENR subsequently pivoted in YEKA RES-2 (2019, 1,000 MW across Aydın, Muğla, Balıkesir, and Çanakkale) to four 250 MW regional packages backed by 15-year USD off-take.

Wave 2 (2021–2022): Mini-YEKA & TRY Inflation Disruption

To accelerate distributed capacity, MENR launched smaller 10–30 MW competitions denominated in Turkish Lira (TRY). YEKA GES-3 (2021, 1,000 MW across 74 sub-tenders in 36 provinces) cleared between 18.2 and 32.0 kuruş/kWh. However, rapid domestic inflation and Lira depreciation eroded real revenues before construction. Although YEKA GES-4 (2022) and YEKA RES-3 (2022) introduced higher TRY ceilings (0.95 TRY/kWh) and partial FX escalation clauses, roughly 24% of RES-3 capacity experienced cancellations or delays, and the planned 10–30 MW YEKA GES-5 rollout (capped at 40 kuruş/kWh) was deferred in favor of a structural redesign.

Wave 3 (2024–2026): Hard-Currency Floors & Katkı Payı

Under Türkiye's National Energy Plan targeting 120 GW of combined solar and wind by 2035, MENR committed to tendering at least 2,000 MW annually via a reformed hard-currency floor model. Crucially for cross-border equity underwriting, the 2024 cycle (auctioned in January and February 2025) remained USD-denominated, whereas the 2025 and 2026 cycles (auctioned November–December 2025 and November 2026) shifted completely to Euros. Once bidders compress tariffs to the floor, price discovery moves to an upfront cash Contribution Fee (Katkı Payı) bid per MW of connection capacity.

YEKA Round Tender / Signing Date Capacity & Zones Currency & Tariff Mechanics Merchant + PPA Structure Commercial Outcome
YEKA GES-1 March 2017 1,000 MW (Karapınar, Konya) USD · Cleared at 6.99¢/kWh 15-yr direct PPA Fully operational; anchored Ankara PV manufacturing plant
YEKA RES-1 August 2017 1,000 MW (Multiple wind zones) USD · Cleared at 3.48¢/kWh 15-yr direct PPA Terminated due to implementation and financing delays
YEKA RES-2 May 2019 1,000 MW (4 × 250 MW zones) USD · 3.53¢ to 4.56¢/kWh 15-yr direct PPA Signed and executed (Aydın, Muğla, Balıkesir, Çanakkale)
YEKA GES-3 2021 1,000 MW (74 lots, 36 provinces) TRY · 18.2–32.0 kuruş/kWh Indexed cap framework Severe TRY FX mismatch delayed multi-lot construction
YEKA RES-3 & GES-4 2022 Up to 2,000 MW RES / 1,000 MW GES (Bor, Erzin, Viranşehir) TRY ceiling raised to 0.95 TRY/kWh + FX indexation Up to 15-yr indexed off-take Partial realization (Bor/Erzin built); ~24% RES-3 adjusted/cancelled
YEKA RES-2024 28 Jan 2025 1,200 MW (5 zones: Edirne, Kırklareli, Sivas) USD · 5.50¢ ceiling / 3.50¢ floor 72-mo merchant + 20-yr PPA All 5 lots hit 3.50¢/kWh; $119.6M Katkı Payı committed
YEKA GES-2024 4 Feb 2025 800 MW (6 zones: Karapınar, Karaman, Malatya, Van, Kütahya, Antalya) USD · 5.50¢ ceiling / 3.25¢ floor 60-mo merchant + 20-yr PPA All 6 lots hit 3.25¢/kWh; $100.75M Katkı Payı committed
YEKA GES-2025 25 Nov 2025 (Signed 6 Jan 2026) 650 MW across 8 zones (revised from 850 MW after 2 site pulls) EUR · 5.50€c ceiling / 3.25€c floor 60-mo merchant + 20-yr PPA All 8 lots hit 3.25€c/kWh; ~€102M Katkı Payı incl. 35 MW floating PV
YEKA RES-2025 9 Dec 2025 (Signed Jan 2026) 1,150 MW (6 zones: Balıkesir, Kütahya, Aydın-Denizli, Sivas) EUR · 5.50€c ceiling / 3.50€c floor 72-mo merchant + 20-yr PPA All 6 lots hit 3.50€c/kWh; >€208M VAT-incl. Katkı Payı
YEKA RES-2026 2 Nov 2026 (Call: 11 Jul 2026) 1,500 MWe (7 zones: Sivas, Balıkesir, Manisa, Kütahya) EUR · 5.50€c ceiling / 3.50€c floor 72-mo merchant + 20-yr PPA 12 firms / 29 bids; €75.5M VAT-incl. Katkı Payı
YEKA GES-2026 3 Nov 2026 (Call: 11 Jul 2026) 785 MW across 11 zones (revised from 900 MWe call) EUR · 5.50€c ceiling / 3.25€c floor 60-mo merchant + 20-yr PPA €31.585M excl. VAT (€37.9M VAT-incl.) Katkı Payı

How Floor Tariffs, Katkı Payı & Merchant Windows Shape Equity IRR

Unlike Western European two-way Contracts for Difference (CfDs) that claw back wholesale revenues above a strike price, Türkiye's 2024–2026 YEKA contracts split project life into two completely distinct commercial regimes: an uncapped early merchant window followed by a long-dated hard-currency floor PPA.

1. Descending Price to Ascending Katkı Payı

Every recent YEKA tender opens at a ceiling tariff of 5.50 USD cents/kWh (2024 rounds) or 5.50 EUR cents/kWh (2025–2026 rounds). Because domestic sponsors view the statutory floors (3.25 cents/kWh for solar and 3.50 cents/kWh for wind) as below standalone 25-year levelized equity hurdles, bidding rapidly compresses to the floor. Once two or more qualified consortia match the floor, the auction converts into an ascending cash fee contest (Katkı Payı) in increments starting at 10,000 USD/MW or 10,000 EUR/MW. Winning sponsors pay this lump-sum fee in cash to EPİAŞ/the state at contract execution, calculated at Central Bank (TCMB) FX selling rates, plus 20% Value Added Tax (KDV), creating an immediate Day-1 equity liquidity outflow.

2. The 60-Month / 72-Month Merchant Arbitrage Window

The economic justification for paying €200,000 to €312,000/MW upfront lies inside the initial free-market window. Starting from the contract signature date (not commercial operation date, making construction speed critical), solar plants hold 60 months and wind plants hold 72 months to sell output freely on EPİAŞ's day-ahead market (PTF) or through bilateral corporate PPAs. Wind developers capturing 72 months of winter-weighted wholesale prices avoid daytime solar cannibalization and can recover a large share of upfront equity before the 20-year 3.50 EUR-cent/kWh off-take commences. By contrast, solar sponsors with slower permitting lose valuable months of the 60-month merchant clock and face midday PTF compression as national PV capacity scales.

3. Curtailment Protections & Site-Specific Fee Compression

Following the March 2025 tender addenda (zeyilname) to the 2024 rounds, revenue losses caused by TEİAŞ dispatch curtailment instructions are compensated under YEKDEM settlement mechanisms, removing uncompensated grid-curtailment tail risk during PPA years. Meanwhile, comparing 2025 and 2026 clearing data reveals sharp fee normalization: as MENR expanded annual tender supply to 2,285 MW in November 2026, total VAT-inclusive Katkı Payı bids dropped from over €310 million across 1,800 MW in late 2025 to €113.4 million across 2,285 MW in November 2026, improving Day-1 capital efficiency for disciplined equity bidders.

Round & Zone Capacity (MWe) Winning Sponsor Cleared Floor Katkı Payı / MW Implied Upfront Fee (Excl. VAT)
RES-2025 · R25-Balıkesir-3 110 MW Eksim Enerji A.Ş. 3.50 EUR¢/kWh €312,000 / MW €34.32M (Peak wind bid)
RES-2025 · R25-Kütahya 120 MW İçdaş Elektrik A.Ş. 3.50 EUR¢/kWh €222,000 / MW €26.64M
RES-2025 · R25-Balıkesir-2 120 MW Balıkesir Elektrik A.Ş. 3.50 EUR¢/kWh €218,000 / MW €26.16M
RES-2025 · R25-Balıkesir-1 160 MW Soma Enerji A.Ş. 3.50 EUR¢/kWh €212,000 / MW €33.92M
RES-2025 · R25-Sivas 500 MW Kanat Rüzgar Enerji A.Ş. 3.50 EUR¢/kWh €56,000 / MW €28.00M (Scale discount)
GES-2025 · Kahramanmaraş 40 MW Güçlü GES Enerji A.Ş. 3.25 EUR¢/kWh €285,000 / MW €11.40M (Peak 2025 solar bid)
GES-2025 · Demirköprü Floating 35 MW (~50.25 MWp) Demirköprü Yüzer GES OGG 3.25 EUR¢/kWh €225,000 / MW €7.88M (1st floating YEKA PV)
GES-2025 · Eskişehir 260 MW Efor Holding 3.25 EUR¢/kWh €105,000 / MW €27.30M
GES-2025 · Bolu 50 MW Ecogreen Elektrik A.Ş. 3.25 EUR¢/kWh €44,000 / MW €2.20M
GES-2024 · G24-Van 60 MW Chen Güneş Enerjisi 3.25 USD¢/kWh $270,000 / MW $16.20M (Peak 2024 solar bid)
GES-2024 · G24-Karapınar 385 MW Kalyon YEKA GES 5 A.Ş. 3.25 USD¢/kWh $67,000 / MW $25.80M
RES-2024 · R24-Edirne 410 MW Enerjisa Üretim A.Ş. 3.50 USD¢/kWh $60,000 / MW $24.60M

Law No. 7554 Permitting Acceleration & Domestic-Content Mandates

Because the 60-month (GES) and 72-month (RES) merchant clock starts on contract signature rather than commissioning, development delays directly compress project cash flow. Two 2024–2025 legal shifts govern construction timelines and equipment BOM costs.

Law No. 7554 ("Super Permit" Reform, July 2025)

Enacted in Official Gazette No. 32965 on 24 July 2025, Law No. 7554 overhauled renewable land, forestry, and environmental bottlenecks. Under Provisional Article 33 added to the Electricity Market Law, EPDK gained authority to execute urgent expropriation of private land for pre-licensed and licensed renewable projects through 31 December 2030 (extendable five years by Presidential decree). The statute also allows forestry permit durations to match the full production license term and tightens Environmental Impact Assessment (EIA/ÇED) procedures under Environmental Law No. 2872 through centralized coordination, shrinking multi-agency delays on YEKA corridors.

YEKA Local Content & Upstream Cell Rules

Modern YEKA tenders do not require each winner to build a factory, but enforce strict component-level localization audited by EİGM under the Domestic Goods Communiqué (SGM 2014/35). Solar specifications require PV modules with a Yerli Malı Belgesi verifying at least 75% domestic content, fabricated with cells processed domestically from at least raw gray wafer stages, plus 51% domestic content on DC cables and mounting structures (with an optional +0.3 cent/kWh 5-year incentive for qualifying domestic inverters). Wind projects require a minimum 55% local-content score across towers, blades, generators, and nacelles. Note that floating projects such as the 35 MW Demirköprü reservoir array carry specialized marine anchoring and float BOM profiles.

Trade-Defense & Customs Cost Interaction

Supply-chain underwriting must account for Türkiye's interlocking trade-defense wall alongside YEKA localization. The Ministry of Trade raised the customs import surveillance reference price (gözetim kıymeti) on unassembled PV cells to $170/kg, applied $25/m² anti-dumping duties across Chinese and third-country transshipment hubs (Vietnam, Malaysia, Thailand, Croatia, Jordan), and imposed 38.23%–57.11% duties on Chinese solar junction boxes. Late-2024 investment incentive rules also bar imported modules from state tax certificates unless cells originate from domestic ingot-slicing onward. See ESI's local solar tariff, import surveillance, and anti-dumping dossiers for full HS-code exposure.

YEKA vs. YEKDEM, Storage-Paired EYÜT & Article 5.1.h Unlicensed

Infrastructure sponsors evaluating Turkish solar and wind deployments in 2026–2027 face four distinct regulatory pathways. Modeling each pathway inside ESI's LCOE Calculator, Solar Calculator, Wind Power Estimator, and Industrial BESS Simulator clarifies how upfront fee outlays compare against merchant curtailment and grid-access scarcity.

Deployment Route Grid & Site Access Tariff / Revenue Model Upfront Fee & Capex Burden Optimal Equity Mandate
YEKA Auctions (2025–2026) Pre-allocated TEİAŞ capacity & designated resource zone 60-mo (GES) / 72-mo (RES) merchant PTF + 20-yr EUR floor (3.25€c / 3.50€c) Competitive Katkı Payı (€44k–€312k/MW + 20% VAT); 75% PV / 55% wind local content Utility-scale IPPs seeking 20-yr EUR downside floor and designated grid bays
YEKDEM (Decree No. 7189) Standard TEİAŞ/distribution pre-license queue (or YEKA optional opt-in) 10-yr TRY monthly basket (30% USD, 30% EUR, 25% PPI, 15% CPI) bounded by 4.95–6.05 USD¢/kWh No auction Katkı Payı; optional local-content adders; private land acquisition Licensed projects with existing grid capacity seeking higher near-term USD collar
Storage-Paired IPP (EYÜT) Priority TEİAŞ capacity conditional on ≥1 MWh BESS per MW Merchant PTF peak arbitrage or elevated YEKDEM collar (5.85–7.15 USD¢/kWh for 10 yrs) Added BESS Capex + 80%–85% availability & dispatch compliance; zero auction fee Sponsors capturing evening PTF spreads and avoiding midday solar zero-pricing
Unlicensed Self-Consumption (Art. 5.1.h) Tied to industrial/commercial consumer meter (up to 2× contract power) Avoided retail industrial tariff; hourly netting since May 2026; surplus capped by PTF Minimal licensing friction; sensitive to domestic module duties unless rooftop local Corporates and CBAM-exposed exporters hedging industrial power bills behind-the-meter

Equity Underwriting Risks & Engineering Controls

Merchant Clock Erosion & Schedule Penalties

Because the 60-month solar and 72-month wind merchant period runs from contract signature rather than commissioning, every month spent on EIA clearance, transformer lead times, or civil works reduces uncapped wholesale cash flow. Equity sponsors should enforce binding EPC milestone buffers, secure early slots for high-voltage grid transformers and switchgear, and verify Law No. 7554 expropriation schedules before finalizing Katkı Payı ceiling bids.

Midday Solar PTF Cannibalization

Rapid utility-scale and unlicensed PV expansion regularly compresses midday day-ahead market clearing prices (PTF) toward zero during spring and summer solar peaks. For YEKA GES projects operating inside their 60-month merchant window, unhedged solar generation earns a discounted capture price relative to baseload PTF. Underwriting models should stress-test capture rates, pair co-located battery energy storage where permitted, or execute corporate bilateral PPAs with industrial off-takers facing EU CBAM carbon costs.

Domestic BOM Premiums & Working-Capital Outflows

Winning bidders must fund 100% of the awarded Katkı Payı plus 20% VAT upfront in equity or sponsor liquidity before generating a single kilowatt-hour. Simultaneously, the 75% solar module localization rule and $170/kg cell surveillance reference floor lift domestic EPC costs above imported Asian spot module benchmarks. Diligence teams should benchmark 30-year PV degradation rates and onshore wind LCOE assumptions against certified Turkish Tier-1 suppliers before locking bid economics.

Executive Regulatory Q&A

How does Türkiye's YEKA two-stage floor price and Katkı Payı auction format work in 2025–2026?
Under MENR's reformed YEKA architecture, bidders first compete downward from an opening ceiling of 5.50 EUR cents/kWh until hitting the statutory floor of 3.25 EUR cents/kWh for solar (GES) or 3.50 EUR cents/kWh for wind (RES). Once multiple bidders match the floor, competition flips to an ascending auction for the upfront Contribution Fee (Katkı Payı) payable per MW of allocated capacity, starting at increments of 10,000 EUR/MW.
What changed between the 2024 and 2025–2026 YEKA auction rounds?
The YEKA RES-2024 (1,200 MW, January 2025) and YEKA GES-2024 (800 MW, February 2025) rounds were denominated in US dollars, generating roughly $119.6 million and $100.75 million in Katkı Payı commitments. Starting with YEKA GES-2025 (650 MW) and YEKA RES-2025 (1,150 MW) in late 2025, and continuing through YEKA RES-2026 (1,500 MW) and YEKA GES-2026 (785 MW) in November 2026, MENR shifted both floor tariffs and Katkı Payı bids to Euros.
How long is the free-market merchant sales window before the 20-year YEKA off-take begins?
From the contract signature date, YEKA solar (GES) projects receive a 60-month (5-year) free-market window to sell power on the liberalized day-ahead wholesale market (PTF) or via bilateral corporate contracts, whereas YEKA wind (RES) projects receive a 72-month (6-year) free-market window. After this merchant period ends, the 20-year state-backed purchase guarantee activates at the cleared floor price.
How does Law No. 7554 (July 2025) affect YEKA permitting and land acquisition?
Published in Official Gazette No. 32965 on 24 July 2025, Law No. 7554 accelerates renewable project execution by empowering EMRA (EPDK) to execute urgent expropriation for licensed and pre-licensed renewable sites through 31 December 2030, aligning forestry permit durations with full generation license lifespans, and tightening and centralizing Environmental Impact Assessment (EIA/ÇED) workflows.
What domestic-content rules apply to YEKA solar and wind equipment in 2026?
Recent YEKA GES specifications require photovoltaic modules to carry a Domestic Goods Certificate (Yerli Malı Belgesi) with at least 75% domestic content, alongside domestic solar cell manufacturing starting from at least raw gray wafer processing and 51% domestic content for DC cables and mounting structures. YEKA RES tenders mandate a minimum 55% local-content score across wind turbine towers, blades, generators, and nacelles.
How does YEKA differ from YEKDEM (Decree 7189), EYÜT storage-paired IPPs, and Article 5.1.h unlicensed solar?
YEKA allocates pre-designated TEİAŞ grid capacity via competitive auctions with 20-year EUR-denominated off-take after a 60–72 month merchant window, requiring upfront Katkı Payı cash payments. By contrast, YEKDEM (Decree 7189) provides a 10-year TRY-basket collar (4.95–6.05 USD cents/kWh standalone; 5.85–7.15 USD cents/kWh with storage) to qualifying licensed plants; EYÜT pairs wind or solar with at least 1 MWh/MW of battery storage to capture grid priority and peak PTF spreads; and Article 5.1.h unlicensed solar targets behind-the-meter self-consumption under hourly netting rules.

Official Government, Regulatory & Gazette References

All statutory frameworks, tender dates, floor tariffs, and Katkı Payı outcomes are anchored to official Turkish ministry announcements, energy regulators, and the Official Gazette. Verified November 2026.

Regulatory Verification & Primary Basis

Every auction parameter, currency pivot, permitting reform, and local-content threshold in this dossier is verified directly against primary Turkish statutes, Official Gazette issues, and MENR/EİGM tender filings. ESI separates enacted statutory obligations from site-level merchant power forecasts.

Mechanism Status Authority Effective Window Key Threshold
YEKA Regulation & Law No. 5346 Amended Dec 2025 MENR / EİGM (Gazette No. 33102) 2016–2035 (Annual 2+ GW calls) 3.25€c/kWh GES & 3.50€c/kWh RES floors; 60/72-mo merchant + 20-yr PPA
Law No. 7554 ("Super Permit" Reform) Enacted Jul 2025 TBMM / EPDK (Gazette No. 32965) 24 Jul 2025 – 31 Dec 2030 EPDK urgent expropriation authority; license-matched forestry permits; EIA reform
Local Content & PV Surveillance Active Enforcement Ministry of Trade / MENR (SGM 2014/35) 2024–2026 Procurement Cycles 75% PV module / 55% wind turbine local score; $170/kg PV cell customs floor
Primary-Source AnchoringAll clearing prices, Katkı Payı €/MW commitments, and statutory deadlines reflect MENR tender records and Official Gazette publications through November 2026 rather than secondary projections.
Underwriting & Diligence ProtocolBefore submitting YEKA bids or executing equity commitments, sponsors should verify round-specific addenda (zeyilname), VAT cash-flow timing, TEİAŞ substation readiness, and domestic BOM certificates with Turkish energy counsel.