United States: HALEU Availability Program & Export Controls

Policy & Export Summary: Created by Energy Act of 2020 § 2001 (42 U.S.C. § 16281) and funded via $700M (IRA § 50173) plus $2.72B (P.L. 118-42), the DOE HALEU Availability Program builds commercial supply of 5% to 20% U-235 fuel (19.75% wt% norm). Cross-border transfers face strict statutory barriers: physical HALEU fuel requires an NRC Specific License under 10 CFR Part 110 and a bilateral Section 123 Agreement, whereas enrichment hardware and cascade know-how require case-by-case Secretarial Specific Authorization under 10 CFR 810.7, even for allies.
$3.42B Statutory Stack $2.7B Jan 2026 Task Orders Russian Ban Sunset: Jan 1, 2028 10 CFR 810 / 110 Controlled
Statutory Appropriations
$3.42B
$700M IRA § 50173 + $2.72B P.L. 118-42.
Jan 2026 Task Orders
$2.70B
$900M each: Centrus, General Matter, Orano.
Russian Waiver Sunset
Dec 31, 2027
Zero waivers from Jan 1, 2028 (P.L. 118-62).
Enrichment Tech Export
Part 810.7
Case-by-case Secretarial authorization.

Statutory & Regulatory Architecture

Mechanism Status Authority Effective Window Key Threshold
Energy Act of 2020 § 2001
42 U.S.C. § 16281 (P.L. 116-260)
Active Statute DOE-NE Dec 2020 to Ongoing (Jan 1, 2026 target) 5% to 20% U-235 (19.75% wt% norm)
IRA § 50173 & OBBBA P.L. 119-21
P.L. 117-169 / P.L. 119-21 (July 4, 2025)
Obligation Window Closed DOE-NE / Treasury (§§ 45U, 45Y, 48E) IRA through Sept 30, 2026; FEOC rules active $700M HALEU fund; strict FEOC exclusion
Consolidated Appropriations Act, 2024
P.L. 118-42 Domestic Fuel Security
Awarded (Jan 2026) US DOE Mar 2024; 10-yr IDIQs; Jan 5, 2026 TO2 $2.72B appropriated; $2.7B awarded
Prohibiting Russian Uranium Imports Act
P.L. 118-62 (H.R. 1042)
Enforced (Tapering Quotas) DOE / Commerce / NRC Aug 11, 2024; waivers end Dec 31, 2027 476.5 MT (2024) to 459.1 MT (2027); 0 MT in 2028
ADVANCE Act & May 2025 EOs
P.L. 118-67; E.O. 14300, 14301, 14302
Active Implementation White House / DOE / NRC July 2024; May 23, 2025 EOs active 20 MT HALEU release (EO 14302); 18-mo NRC cap
HALEU & Enrichment Export Controls
10 CFR 110, 10 CFR 810, EAR, ITAR
Strictly Restricted NRC / DOE-NNSA / BIS / State Permanent Atomic Energy Act Regime 10 kg U-235 Cat II; Part 810.7 Specific Auth

How Congress Built the $3.42B US HALEU & LEU Fuel Stack

Between 2020 and 2026, federal legislation linked domestic enrichment appropriations to a phased Russian uranium ban, stockpile releases, and Foreign Entity of Concern (FEOC) tax-credit guardrails.

1. Energy Act of 2020 § 2001 and IRA § 50173

Section 2001 of the Energy Act of 2020 (Division Z of P.L. 116-260; 42 U.S.C. § 16281) created the DOE HALEU Availability Program for civilian uranium enriched above 5.0% and below 20.0% U-235, with commercial developers standardizing at 19.75% wt%. It established the HALEU Consortium and set a January 1, 2026 operational capability milestone. To seed initial supply, Section 50173 of the Inflation Reduction Act of 2022 (P.L. 117-169) appropriated $700 million through September 30, 2026: $500 million for commercial HALEU acquisition and consortium support, $100 million for transport and storage infrastructure, and $100 million for associated R&D.

2. P.L. 118-42 ($2.72B) Paired With the Russian Import Ban (P.L. 118-62)

In spring 2024, Congress paired a $2.72 billion enrichment appropriation in the Consolidated Appropriations Act, 2024 (P.L. 118-42) with the Prohibiting Russian Uranium Imports Act (P.L. 118-62, enacted May 13, 2024, effective August 11, 2024). P.L. 118-62 bans unirradiated Russian LEU and natural uranium imports, permitting temporary DOE national-interest waivers only when no viable alternative source exists and capping total annual waivers at 476,536 kg (2024), 470,376 kg (2025), 464,183 kg (2026), and 459,083 kg (2027). All waiver authority expires after December 31, 2027, locking in a complete ban from January 1, 2028.

3. OBBBA (P.L. 119-21), May 2025 Executive Orders, and GAO-26-107385

On May 23, 2025, three nuclear executive orders accelerated federal fuel mobilization: E.O. 14300 (ordering NRC structural reform and 18-month new-reactor licensing caps), E.O. 14301 (establishing the DOE Reactor Pilot Program), and E.O. 14302 (Reinvigorating the Nuclear Industrial Base). E.O. 14302 invoked Defense Production Act cooperative authorities and directed DOE to release at least 20 metric tons of HALEU from federal stockpiles, complementing FY 2024 NDAA § 3131(h), which mandated releasing 21 MT across three tranches (3 MT by Sept 30, 2024; 8 MT by Dec 31, 2025; 10 MT by June 30, 2026).

On July 4, 2025, the One Big Beautiful Bill Act (OBBBA, P.L. 119-21) clawed back unobligated balances across various IRA clean-energy accounts while preserving IRC § 45U, § 45Y, and § 48E nuclear tax credits and adding strict FEOC prohibitions barring Chinese, Russian, Iranian, and North Korean fuel supply chains. Yet in GAO-26-107385 (August 20, 2026), auditors warned that while NNSA holds sufficient defense uranium inventories into the early 2040s, near-term civilian HALEU supply risks trailing reactor demand and DOE lacked documented economic modeling confirming federal awards alone will establish self-sustaining commercial conversion, enrichment, and deconversion.

DOE Procurement IDIQs, $2.7B Task Orders & Allocations (2024–2026)

DOE deployed 10-year IDIQ pools across deconversion, HALEU enrichment, and LEU enrichment, followed by $2.7 billion in January 2026 implementation task orders and three rounds of conditional stockpile allocations.

Program Track Award Value Selected Contractors / Recipients Scope & 2025–2026 Delivery Status
Centrus Piketon Cascade
Phase I–III
Cost-share + Phase III to June 30, 2026 American Centrifuge Operating, LLC (Centrus, Piketon, OH) Delivered 900 kg HALEU UF6 milestone in June 2025 (Phase II); exceeded 1,900 kg cumulative output during Phase III scale-up transition.
HALEU Deconversion IDIQ
Oct 2024
$800M ceiling ($2M min. each) BWXT, Centrus (ACO), Framatome, GE Vernova (GNF-A), Orano Federal Services, Westinghouse Converts enriched HALEU UF6 gas into oxide, metal, or nitride feed for TRISO and metallic reactor fuels.
HALEU Enrichment IDIQ
Oct 2024
$2.7B pool ($2M TO1 each) Centrus (ACO), General Matter, Louisiana Energy Services (Urenco USA), Orano Federal Services Builds domestic commercial enrichment up to 19.75% U-235; all four remain eligible for future task orders.
LEU Enrichment IDIQ
Dec 2024
$3.4B ceiling ($2M TO1 each) Centrus (ACO), General Matter, Global Laser Enrichment, Urenco USA, LIS Technologies, Orano Replaces Russian LEU SWU ahead of Jan 1, 2028 ban using gas centrifuge and laser isotope separation.
Implementation Task Orders
Jan 5, 2026
$2.70B ($900M x 3) + $28M GLE Centrus/ACO ($900M HALEU), General Matter ($900M HALEU), Orano ($900M LEU), GLE ($28M) Centrus expanding Piketon (targeting up to 12 MT/yr in future buildout phases); General Matter at Paducah, KY; Orano Oak Ridge, TN.
Conditional HALEU Allocations
2025–2026
Stockpile allocations (NDAA / EO 14302) Apr 9, 2025: TRISO-X, Kairos, Radiant, Westinghouse, TerraPower.
Aug 26, 2025: Antares, Standard Nuclear, ACU/Natura.
Jul 23, 2026: NASA, Radiant (2nd award).
Conditional on binding contracts and licensing milestones. Oklo separately combined EBR-II fuel with Centrus commercial prepayments.

Logistics Bottleneck: Deconversion & DN30-X / 30B-20 Packaging

Enrichment capacity alone cannot deliver reactor fuel without upstream UF6 conversion capacity, downstream deconversion, and certified Type B transport. Standard 30B cylinders are licensed only up to 5.0% U-235. Commercial 19.75% HALEU requires criticality-controlled cylinders such as Orano/Urenco's 30B-X inside the DN30-X overpack (NRC-certified March 2023; 30B-20 holds roughly 1,271 kg of UF6), which is separate from NNSA's defense-complex DPP-2 container.

Are There Restrictions on Exporting HALEU Material or Enrichment Technology?

Yes. US federal export law separates physical nuclear fuel exports from intangible enrichment technology transfers across four distinct regulatory regimes.

Layer 1: Physical HALEU Fuel & Category II Thresholds (NRC 10 CFR Part 110)

The NRC regulates physical exports of Special Nuclear Material (SNM), source material, and Nuclear Suppliers Group (NSG) Part 1 Especially Designed or Prepared (EDP) equipment under 10 CFR Part 110. Commercial HALEU exports require a Specific NRC Export License, which cannot be issued unless the destination country maintains an active bilateral Section 123 Agreement for peaceful nuclear cooperation, full-scope IAEA safeguards, and non-retransfer guarantees.

Enrichment assay also triggers strict physical-protection tiers. Under 10 CFR 73.2, uranium enriched between 10% and less than 20% U-235 escalates from Category III (>1,000 g to <10,000 g U-235) to Category II (moderate strategic significance) at 10,000 grams (10 kg) or more of contained U-235. At 19.75% assay, 10 kg of contained U-235 equals just 50.6 kg of uranium metal (or ~74.8 kg of UF6), meaning virtually every SMR reload or 30B-20 cylinder requires Category II armed transit security and hardened site safeguards.

Layer 2: Enrichment, Reprocessing & TRISO Know-How (DOE 10 CFR Part 810)

DOE NNSA regulates intangible exports of unclassified nuclear technology, software, drawings, and engineering services to foreign persons (including "deemed exports" inside the US) under 10 CFR Part 810. Although Appendix A grants General Authorization for routine civilian LWR assistance to allied nations, 10 CFR 810.7 bars General Authorization for Sensitive Nuclear Technologies. Any foreign transfer involving uranium isotope separation (enrichment), irradiated fuel reprocessing, plutonium fuel fabrication, or heavy water production always requires case-by-case Secretarial Specific Authorization with interagency concurrence from State, Defense, Commerce, and the NRC, even for Appendix A allies. While the ADVANCE Act of 2024 (P.L. 118-67) directed DOE to modernize Part 810 review workflows and created the NRC International Nuclear Export and Innovation Branch, the statutory firewall around enrichment IP remains intact.

Layer 3: Dual-Use Hardware & Defense Carve-Outs (EAR & ITAR)

Dual-use NSG Part 2 items on the Commerce Control List (maraging steel, nuclear graphite, specialized vacuum pumps, frequency changers, and CVD coating furnaces) require BIS validated licenses under EAR 15 CFR Part 742.3, while defense, naval, or military space microreactor systems fall under State Department ITAR (22 CFR Part 121).

Export Item / Activity Statute & Agency Authorization Path Allied (Appendix A / 123) Treatment & Limits
Physical HALEU Fuel
(UF6, oxide/metal, TRISO compacts)
10 CFR Part 110 (NRC) Specific Export License Requires active Section 123 Agreement and IAEA safeguards; 10 kg+ U-235 (10% to <20%) triggers Category II security (10 CFR 73.2).
Enrichment Technology & Software
(Centrifuge/laser IP, cascade design)
10 CFR 810.7 (DOE / NNSA) Specific Secretarial Authorization No General Authorization, even for Appendix A allies. Mandatory DOE Secretary sign-off plus State, DoD, Commerce, and NRC review.
TRISO Fabrication Know-How
(Non-plutonium kernel/coating IP)
10 CFR Part 810 + EAR General (App. A) or Specific Auth Commercial HALEU fabrication assistance to Appendix A allies can use General Authorization if isolated from enrichment or reprocessing interfaces.
Dual-Use Fuel-Cycle Hardware
(Maraging steel, CVD furnaces, pumps)
EAR 15 CFR 742 (BIS) CCL / ECCN Validated License NSG Part 2 Nuclear Referral List controls; strict end-user vetting and FEOC / Entity List denials.
Defense & Naval Reactors ITAR 22 CFR 121 (State) DDTC License / TAA Excluded from civilian general authorizations; strict defense-article controls apply.

Underwriting SMR Fuel Costs, Tax Credits & Supply Risk

HALEU fuel-chain constraints directly shape SMR levelized cost, equity return timing, and federal tax-credit qualification.

SWU Parity & Feed Multiplier

Enriching 1 kg of 19.75% HALEU requires roughly 5 to 6 times the Separative Work Units (SWU) of 4.5% LEU. Because Western enrichment SWU capacity must simultaneously replace banned Russian LEU by January 1, 2028, tails-assay optimization (0.20% vs 0.30%) and DOE task-order CAPEX underwriting dictate delivered fuel $/kg parity.

Take-or-Pay Prepayments & Equity

With commercial HALEU cascades scaling through late-decade, industrial off-takers and data-center sponsors increasingly fund early capacity via long-term take-or-pay off-take prepayments and project-level equity rather than spot contracts, synchronizing fuel delivery with NRC licensing and DOE stockpile allocations.

OBBBA FEOC & Credit Preservation

Under P.L. 119-21, IRC §§ 45Y and 48E credits require strict Foreign Entity of Concern compliance. Sponsors must maintain auditable chain-of-custody records across mining, conversion, enrichment, and deconversion to ensure zero Russian or Chinese material enters blended cores.

Executive Regulatory & Export Q&A

Are there current restrictions on exporting HALEU fuel and enrichment technology from the United States?
Yes. Exporting physical HALEU fuel requires an NRC Specific License under 10 CFR Part 110, an active bilateral Section 123 Agreement, IAEA safeguards, and Category II security at 10 kg or more of contained U-235 (10% to under 20%). Exporting enrichment technology or cascade software is controlled under 10 CFR 810.7 as Sensitive Nuclear Technology and always requires case-by-case Secretarial Specific Authorization, even for Appendix A allies.
How much federal funding backs the US HALEU Availability Program and domestic enrichment buildout?
Congress paired $700 million under IRA Section 50173 (available through September 30, 2026) with $2.72 billion under P.L. 118-42. DOE executed an $800 million HALEU deconversion IDIQ in October 2024, a $3.4 billion LEU/HALEU IDIQ framework in late 2024, and $2.7 billion in January 2026 task orders split equally ($900 million each) among Centrus (American Centrifuge Operating), General Matter, and Orano Federal Services.
What does the Prohibiting Russian Uranium Imports Act (P.L. 118-62) require through 2027?
Enacted May 13, 2024 and effective August 11, 2024, P.L. 118-62 bans unirradiated Russian LEU imports. DOE national-interest waivers are capped at 476,536 kg in 2024, 470,376 kg in 2025, 464,183 kg in 2026, and 459,083 kg in 2027. All waiver authority expires after December 31, 2027, imposing a complete statutory prohibition starting January 1, 2028.
Which advanced reactor developers received DOE conditional HALEU allocations in 2025 and 2026?
DOE announced three allocation rounds: Round 1 on April 9, 2025 (TRISO-X, Kairos Power, Radiant Industries, Westinghouse Electric, TerraPower), Round 2 on August 26, 2025 (Antares Nuclear, Standard Nuclear, Abilene Christian University / Natura Resources), and Round 3 on July 23, 2026 (NASA for the SR-1 Mars mission and a second Radiant Industries allocation for Buckley Space Force Base).
How does the 2025 One Big Beautiful Bill Act (P.L. 119-21) affect nuclear fuel and tax credits?
Signed on July 4, 2025, OBBBA (P.L. 119-21) rescinded unobligated balances across several IRA clean-energy accounts while preserving nuclear tax credits under IRC Sections 45U, 45Y, and 48E. However, OBBBA tightened Foreign Entity of Concern (FEOC) rules, disqualifying projects whose nuclear fuel or critical components trace to Russian, Chinese, Iranian, or North Korean entities.
Why are DN30-X cylinders and deconversion bottlenecks critical for SMR equity diligence?
Standard 30B commercial UF6 cylinders are licensed only up to 5.0% U-235. Commercial 19.75% HALEU transport requires criticality-controlled packaging like the NRC-certified DN30-X overpack and 30B-20 cylinder (holding about 1,271 kg of UF6), plus deconversion plants to convert UF6 gas into oxide, metal, or TRISO kernels before reactor loading.

Official Statutes, Filings & Regulator Records

Citations verified directly against US Public Laws, DOE releases, eCFR titles, and GAO-26-107385 through November 2026.

Regulatory Verification & Primary Basis

Every statutory threshold, contract award, conditional allocation, and export restriction in this dossier is verified against enacted US statutes, eCFR texts, DOE procurement notices, and GAO-26-107385.

Mechanism Status Authority Effective Window Key Threshold
HALEU Program & Task Orders Active Execution DOE-NE (42 U.S.C. § 16281; P.L. 118-42) 2020 to 2034 (10-yr IDIQs) 5%–20% U-235; $2.7B Jan 2026 awards
Export Control Firewall Mandatory Compliance NRC (10 CFR 110) / DOE (10 CFR 810.7) / BIS Continuous Statutory Enforcement 10 kg U-235 Cat II; Specific Auth for enrichment IP
Primary-Source AnchoringFigures reflect enacted Public Laws (116-260, 117-169, 118-42, 118-62, 118-67, 119-21), E.O. 14300–14302, and GAO-26-107385 rather than developer projections.
Underwriting & Export DiligenceBefore committing equity or off-take prepayments, sponsors must secure 10 CFR 810/110 determinations, verify Section 123 treaty coverage, and audit FEOC chain-of-custody.