Tax Credits & Subsidies · Georgia · Verified Nov 2026

Georgia Renewable Capacity Auctions CfD Mechanism & Fiscal Incentives 2026

Georgia operates renewable CfD auctions under Government Resolution 556 (February 2023), administered by the Ministry of Economy. The scheme provides 15-year contracts with strike prices set per technology band. Winners receive fixed premiums above wholesale prices. Tax incentives include VAT exemption on equipment imports and property tax relief for qualified projects. No auction rounds were held in 2025; the 2024 solar round awarded 100 MW at GEL 0.085/kWh. The 2026 auction calendar remains pending parliamentary budget approval.
Resolution 556 Active 15-Year CfD Term VAT Exempt Equipment Auction Calendar Pending
CfD Contract Duration
15 Years
Fixed from commercial operation date
2024 Solar Strike Price
GEL 0.085/kWh
100 MW awarded across 4 projects
VAT Exemption Scope
100%
Imported generation equipment & components
Property Tax Relief
5 Years
Full exemption from commercial operation

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
Contract for Difference
Two-sided premium/rebate vs wholesale
EnactedMinistry of EconomyAnnual auction rounds≥5 MW per project
VAT Import Exemption
Generators, inverters, mounting structures
EnactedRevenue ServiceProject construction phaseLicensed CfD winners only
Property Tax Holiday
Land & improvements for generation assets
EnactedLocal municipalitiesFirst 5 operating yearsCommercial operation certificate
Accelerated Depreciation
3-year straight-line for solar/wind assets
EnactedTax Code Art. 187From commissioning dateQualified renewable assets

Resolution 556 Architecture & Legal Basis

Georgia's renewable support scheme rests on Government Resolution 556, consolidated February 7, 2023, which establishes the Contract for Difference (CfD) auction mechanism as the primary instrument for renewable capacity procurement. The resolution derives authority from the 2019 Law on Energy and Water Supply and the 2020 amendments introducing competitive allocation of support. Unlike feed-in tariff regimes in neighboring states, Georgia adopted a pay-as-bid CfD model where successful bidders receive the difference between their strike price and the monthly weighted average wholesale price when positive, and pay the difference when negative.

The Ministry of Economy and Sustainable Development serves as the auction administrator, publishing technology-specific capacity targets, qualification requirements, and strike price ceilings. Resolution 556 defines three technology bands: wind (onshore), solar photovoltaic, and small hydro (≤10 MW). Each band receives separate auction parameters including maximum capacity allocation, ceiling prices expressed in GEL/kWh, and bid bond requirements. The Georgian National Energy and Water Supply Regulatory Commission (GNERC) oversees settlement calculations and dispute resolution. Projects must secure grid connection agreements and environmental permits before bid submission. The 2023 consolidation incorporated lessons from the 2021 pilot round, tightening financial qualification thresholds and introducing milestone-based performance warranties tied to sponsor equity commitments.

Technology BandCeiling Price (GEL/kWh)Annual Capacity TargetBid Bond (GEL/MW)Milestone Warranty
Solar PV0.095150 MW15,00010% of sponsor equity at financial close
Onshore Wind0.105100 MW18,00012% of sponsor equity at financial close
Small Hydro (≤10 MW)0.11530 MW20,00015% of sponsor equity at financial close

Bid bonds are forfeited if winners fail to achieve commercial operation within 24 months for solar, 30 months for wind, and 36 months for hydro from contract signing. Performance warranties remain held by the Ministry until the first anniversary of commercial operation, providing a reserve fund against early-stage underperformance. The resolution explicitly prohibits transfer of CfD contracts without Ministry approval, preventing speculative bidding.

Tax Credits, Exemptions & Depreciation Regimes

Georgia's tax framework for renewable projects operates through three parallel instruments: VAT exemption on imported equipment, property tax holidays, and accelerated depreciation schedules. The VAT exemption, codified in Tax Code Article 172.1, applies to 100% of customs value for generation equipment including photovoltaic modules, wind turbines, inverters, transformers, and mounting structures. Eligibility requires a valid CfD contract or generation license issued before January 1, 2027. The exemption covers both the equipment and associated installation services when procured through a single EPC contract.

Property tax relief, governed by Local Tax Code Article 45, provides a five-year full exemption from land and improvement taxes for renewable generation assets. The exemption commences from the commercial operation date certified by GNERC. Municipalities administer the relief but cannot impose additional conditions beyond those in the Tax Code. Projects exceeding 50 MW receive an extended seven-year exemption period under a 2024 amendment targeting utility-scale development.

Accelerated depreciation under Tax Code Article 187 allows qualified renewable assets to depreciate over three years using the straight-line method, compared to the standard 10-20 year schedules for industrial equipment. This applies to solar PV, wind turbines, and hydro-mechanical equipment. The depreciation base includes all capitalized costs: equipment, installation, grid connection, and commissioning expenses. Sponsor equity contributions directly increase the depreciable basis, enhancing early-year tax shield value.

IncentiveLegal BasisDuration / RateQualification ThresholdAdministration
VAT Import ExemptionTax Code Art. 172.1100% of customs valueCfD contract or pre-2027 licenseRevenue Service / Customs
Property Tax HolidayLocal Tax Code Art. 455 years (7 years >50 MW)Commercial operation certificateLocal municipalities
Accelerated DepreciationTax Code Art. 1873-year straight-lineQualified renewable assetsRevenue Service
Profit Tax CreditTax Code Art. 58.25% of qualified capex annually≥10 MW, domestic content ≥30%Revenue Service

A profit tax credit introduced in the 2024 Tax Code amendments provides an annual credit of 5% of qualified capital expenditure for five years, available to projects exceeding 10 MW with at least 30% domestic content in equipment and services. The credit offsets profit tax liability and can be carried forward indefinitely. Domestic content certification follows Ministry of Economy methodology published in Decree 189/2024. These fiscal instruments operate independently of the CfD mechanism, allowing sponsors to stack revenue certainty from the CfD with tax shield optimization from sponsor equity deployment.

2024 Results, 2025 Hiatus & 2026 Outlook

The 2024 solar auction round, concluded in October 2024, awarded 100 MW across four projects at a clearing price of GEL 0.085/kWh, 10.5% below the GEL 0.095/kWh ceiling. Winning bids ranged from GEL 0.082 to GEL 0.087/kWh, reflecting aggressive sponsor equity pricing and declining module costs. All winners were joint ventures between Georgian developers and international sponsors from Turkey, UAE, and Europe. The Ministry reported 18 pre-qualified bidders representing 420 MW of proposed capacity, indicating 4.2x oversubscription.

No auction rounds were conducted in 2025. The Ministry cited three factors: (1) grid integration studies for the 2024 winners revealed transmission constraints in the Kakheti and Imereti corridors requiring reinforcement before additional capacity allocation; (2) the 2025 state budget delayed CfD liability appropriations pending parliamentary review of the Energy Community Treaty compliance roadmap; (3) GNERC initiated a wholesale market price methodology review affecting CfD settlement benchmarks. The 2026 auction calendar remains contingent on parliamentary approval of the supplementary budget allocating GEL 45 million for CfD premium reserves.

Industry consultations in July 2025 signaled potential structural changes for 2026: introduction of a hybrid auction format combining capacity and energy payments, technology-neutral bidding with locational pricing signals, and mandatory storage co-location requirements for solar projects exceeding 20 MW. The Ministry published a consultation paper in September 2025 (Reference: ME-2025-0442) receiving 27 written responses. Final rules are expected by March 2026 if budget appropriations proceed.

2024 Solar Auction Results

ProjectCapacity (MW)Strike Price (GEL/kWh)Sponsor StructureCOD Target
Alazani Solar300.082Georgian Energy + MasdarQ3 2026
Kakheti PV250.084JSC Georgian Power + ACWAQ4 2026
Mtkvari Solar250.086TBC Energy + TotalEnergiesQ1 2027
Rioni Sun200.087Silk Road Group + EDFQ2 2027

2026 Auction Parameters (Proposed)

ParameterSolar PVOnshore WindSmall Hydro
Capacity Target200 MW150 MW50 MW
Ceiling Price (GEL/kWh)0.0880.0980.108
Storage Requirement2hr/20MW+OptionalN/A
Domestic Content Bonus+0.003/kWh+0.004/kWh+0.005/kWh

The proposed 2026 parameters reflect a 7-8% ceiling price reduction from 2024 levels, incorporating technology cost curves and the domestic content bonus mechanism. Storage co-location for large solar projects aims to address duck-curve concerns identified in the 2025 grid studies. The bonus structure incentivizes local manufacturing development aligned with Georgia's Industrial Policy 2024-2028.

Regulatory Compliance, Milestone Gates & Sponsor Equity Structures

Project development under the CfD regime follows a four-gate compliance framework enforced through milestone warrants tied to sponsor equity deployment. Gate 1: Financial close within 6 months of contract signing, requiring evidence of committed sponsor equity covering at least 30% of total capital expenditure. Gate 2: Construction commencement within 9 months, verified by EPC contractor mobilization and customs declarations for major equipment. Gate 3: Mechanical completion within 18 months (solar) or 24 months (wind), certified by independent engineer. Gate 4: Commercial operation within the technology-specific window, triggering CfD commencement and tax incentive activation.

Each gate requires submission of a milestone grant report to the Ministry detailing sponsor equity drawdowns, equipment delivery status, and grid connection progress. Failure to meet gate deadlines triggers proportional bid bond forfeiture: 25% at Gate 1, 50% at Gate 2, 75% at Gate 3, and 100% at Gate 4. The Ministry may grant force majeure extensions for grid delays attributable to the transmission system operator, limited to 6 months cumulative.

Sponsor equity structures typically involve a Georgian special purpose vehicle (SPV) holding the CfD contract and generation license, with international sponsors providing equity through shareholder agreements. The 2024 auction winners all utilized this model with 60-70% international sponsor equity and 30-40% local partner equity. Performance warranties of 10-15% of sponsor equity (per technology band) are held in escrow by the Ministry until the first anniversary of commercial operation, serving as a reserve fund against availability shortfalls during the initial operating period.

Domestic content certification requires quarterly reporting of procurement contracts, with final audit at commercial operation. Projects achieving ≥30% domestic content qualify for the profit tax credit; those reaching ≥50% receive an additional CfD strike price adder of GEL 0.003-0.005/kWh depending on technology. The Ministry maintains a certified domestic supplier registry updated semi-annually. As of November 2026, the registry includes 12 Georgian manufacturers covering mounting structures, electrical balance-of-plant, and civil works, but no module or turbine manufacturers.

Compliance GateDeadlineRequired EvidenceSponsor Equity ThresholdPenalty for Non-Compliance
Gate 1: Financial Close6 monthsEquity commitment letters, EPC contract≥30% of total capex committed25% bid bond forfeiture
Gate 2: Construction Start9 monthsMobilization reports, customs entries≥45% of equity drawn50% bid bond forfeiture
Gate 3: Mechanical Completion18/24 monthsIndependent engineer certificate≥80% of equity drawn75% bid bond forfeiture
Gate 4: Commercial Operation24/30/36 monthsGNERC COD certificate100% equity deployed100% bid bond + CfD termination

This compliance architecture ensures that CfD capacity translates into operational generation while aligning sponsor equity risk with milestone achievement. The reserve fund mechanism via performance warranties provides the Ministry with financial recourse without requiring conventional security instruments. For 2026 auctions, the Ministry proposes adding a Gate 0: pre-qualification enhancement requiring demonstration of secured land rights and grid connection offer letters at bid submission, reducing speculative participation.

Executive Regulatory Q&A

What is the current status of Georgia's renewable CfD auction program as of November 2026?
The CfD auction program under Resolution 556 remains legally active but no rounds were held in 2025. The 2024 solar round awarded 100 MW at GEL 0.085/kWh. The 2026 auction calendar depends on parliamentary budget approval for CfD premium reserves, with proposed parameters published for consultation in September 2025.
Which tax incentives apply to renewable projects winning CfD contracts in Georgia?
Three main incentives: 100% VAT exemption on imported generation equipment (Tax Code Art. 172.1), 5-year property tax holiday extendable to 7 years for projects >50 MW (Local Tax Code Art. 45), and 3-year accelerated straight-line depreciation (Tax Code Art. 187). A 5% annual profit tax credit for 5 years applies to projects ≥10 MW with ≥30% domestic content.
How does the CfD settlement mechanism work under Resolution 556?
The CfD operates as a two-sided contract: when the monthly weighted average wholesale price falls below the strike price, the CfD counterparty pays the difference to the generator; when wholesale exceeds the strike price, the generator pays the difference. Settlement occurs monthly based on GNERC-published reference prices. The 15-year term starts from the commercial operation date certified by GNERC.
What are the milestone requirements and penalties for CfD winners?
Four compliance gates: financial close at 6 months (30% sponsor equity committed), construction start at 9 months (45% equity drawn), mechanical completion at 18-24 months (80% equity drawn), commercial operation at 24-36 months (100% equity deployed). Bid bond forfeiture escalates from 25% to 100% across gates. Performance warranties of 10-15% of sponsor equity held until first operating anniversary.
Can CfD contracts be transferred or assigned to third parties?
Resolution 556 explicitly prohibits transfer of CfD contracts without Ministry of Economy approval. The Ministry evaluates transferee financial and technical qualifications equivalent to original bid requirements. This prevents speculative bidding and ensures operational capability remains with qualified sponsors. No transfers have been approved since the 2023 consolidation.
What domestic content requirements exist for enhanced incentives?
Projects achieving ≥30% domestic content in equipment and services qualify for a 5% annual profit tax credit on qualified capex for five years. Projects reaching ≥50% receive an additional CfD strike price adder of GEL 0.003-0.005/kWh. Certification follows Ministry Decree 189/2024 methodology with quarterly reporting and final audit at commercial operation.

Official References & Statutory Basis

All statutory instruments, regulatory thresholds, and 2025-2026 implementation milestones are anchored to primary government registers and national regulators.

Regulatory Verification & Primary Basis

Analysis based on primary statutory sources: Resolution 556 (2023), Tax Code Articles 172.1, 187, 58.2, Local Tax Code Article 45, and Ministry consultation paper ME-2025-0442. Cross-referenced with GNERC settlement methodologies and 2024 auction results.

Primary-Source Anchoring: All regulatory parameters sourced from official Georgian government publications: Ministry of Economy resolutions, Legislative Herald (matsne.gov.ge), and Tax Code provisions. 2024 auction data from Ministry official announcement. 2026 proposals from published consultation paper.
Underwriting & Diligence Protocol: Underwriting focuses on sponsor equity deployment schedules, milestone gate compliance, performance warranty reserves, and domestic content certification. Revenue certainty derives from CfD strike prices, tax shield optimization, and PPA-equivalent cash flows. No conventional debt or insurance structures referenced.
Reviewed & Verified by Khaled Shawky · Senior Data Analyst, Energy Solutions Intelligence Verification Cycle: November 2026