UAE: Barakah Nuclear Program & FANR Licensing

All four APR-1400 reactors at the Barakah Nuclear Energy Plant (5.6 GW total capacity) have been commercially operational since September 2024, generating roughly 40 TWh annually or 25% of UAE electricity. Operated by Nawah Energy Company under 60-year FANR operating licenses, Barakah feeds EWEC's grid and Clean Energy Certificates while expansion studies remain pre-licensing.
5,600 MW (4x APR-1400) 60-Year FANR Licenses ~40 TWh / 25% UAE Grid
Fleet Capacity
5,600 MW
Four commercial APR-1400 units
Annual Output
~40 TWh
Supplies ~25% of UAE power
Operating License
60 Years
Per-unit FANR authorisation
Unit 5 / 6 Status
Unlicensed
Exploratory evaluation only

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
UAE Peaceful Nuclear Program (Barakah Units 1-4)
Federal Decree-Law No. 6 of 2009 & FANR Regulations
All 4 Units Commercial (Sep 2024+) FANR / ENEC & Nawah Unit 1 (Apr 2021) through Unit 4 (Sep 2024); 60-year operating license term 5.6 GW total capacity; ~40 TWh/yr (~25% UAE electricity); 82% ENEC / 18% KEPCO JV

Barakah Governance: ENEC, Nawah, Barakah One & FANR

Located in the Al Dhafra region of Abu Dhabi, the Barakah Nuclear Energy Plant represents the Arab world's first multi-unit commercial nuclear power station. Its regulatory architecture rests on Federal Decree-Law No. 6 of 2009 Concerning the Peaceful Uses of Nuclear Energy, which separated commercial project ownership from independent safety regulation.

Independent Safety Regulator (FANR)

The Federal Authority for Nuclear Regulation (FANR) exercises independent licensing, inspection, radiation protection, nuclear security, and IAEA safeguards oversight. FANR prohibited domestic enrichment and reprocessing in UAE policy, requiring unit-specific construction approvals and 60-year operating licenses prior to fuel load and criticality.

82% / 18% Equity Joint Ventures

The Emirates Nuclear Energy Corporation (ENEC) serves as state project owner and holds an 82% equity stake alongside South Korea's Korea Electric Power Corporation (KEPCO) at 18% across two operating vehicles: Nawah Energy Company (licensed nuclear operator) and Barakah One Company (commercial power and PPA counterparty).

EWEC Long-Term Physical Offtake

Barakah One Company supplies 100% of generated electricity under a long-term Power Purchase Agreement (PPA) to the Emirates Water and Electricity Company (EWEC), Abu Dhabi's sole power and water procurer. This contracted baseload offtake anchors plant cashflows without exposing grid dispatch to merchant fuel price spikes.


Unit-by-Unit Commissioning & Commercial Operation Record

Each of Barakah's four South Korean-designed APR-1400 pressurized water reactors underwent sequential construction, FANR operating license issuance, nuclear fuel loading, grid synchronization, and full-power commercial acceptance between 2020 and September 2024.

Reactor Unit Design & Nameplate Rating Commercial Operation Date (COD) Licensed Operator & Term 2025-2026 Operational Status
Barakah Unit 1 APR-1400 PWR (up to 1,400 MW) April 2021 Nawah Energy Company (60-year FANR license) Full commercial baseload operation & scheduled refueling cycles
Barakah Unit 2 APR-1400 PWR (up to 1,400 MW) March 2022 Nawah Energy Company (60-year FANR license) Full commercial baseload operation & scheduled refueling cycles
Barakah Unit 3 APR-1400 PWR (up to 1,400 MW) February 2023 Nawah Energy Company (60-year FANR license) Full commercial baseload operation & scheduled refueling cycles
Barakah Unit 4 APR-1400 PWR (up to 1,400 MW) September 2024 (Grid link Mar 2024) Nawah Energy Company (60-year FANR license) Full commercial operation completing 5.6 GW four-unit fleet

EWEC Clean Energy Certificates & Unit 5/6 Expansion Evaluation

With Unit 4 entering commercial service in September 2024, Barakah transitioned from a decade-long construction program into steady-state fleet operations supplying roughly 40 TWh per year, displacing millions of tonnes of natural-gas-fired power emissions and underpinning Abu Dhabi's Clean Energy Certificates (CECs) registry.

Abu Dhabi Clean Energy Certificates (CECs)

Operated by EWEC as Single Registrant and Scheme Operator under Abu Dhabi Department of Energy rules, the CEC registry tracks zero-carbon nuclear and solar attributes:

Tracking Unit1 CEC = 1 MWh zero-carbon power
Eligible GeneratorsBarakah nuclear & utility solar PV
Market MechanismPeriodic EWEC auctions & bilateral trades
Corporate Use CaseVerified Scope 2 carbon accounting

2025-2026 Expansion & SMR Feasibility

Rapid electricity load growth from AI data centers, industrial aluminum smelting, and desalination has spurred policy evaluations beyond the four existing reactors:

Barakah Units 5 & 6Not licensed; no ground broken
ENEC-KEPCO TalksExploratory expansion feasibility
SMR & Advanced NuclearIndustrial & ADNOC process-heat review
FANR Regulatory GatePrior site, design & EIS approval required

Regulatory Lifecycle & Commercial Diligence Boundaries

Lifecycle Stage / Instrument Governing Authority Current 2026 Standing Institutional Underwriting Takeaway
60-Year Reactor Operating Licenses FANR (Federal Decree-Law No. 6/2009) Active across Units 1, 2, 3, and 4 Each unit maintains an independent license subject to ongoing outage inspections, Periodic Safety Reviews, and decommissioning reserve audits
Power Purchase Agreement (PPA) & Grid Dispatch EWEC & Abu Dhabi DoE Active full-fleet baseload dispatch Barakah supplies ~25% of UAE electricity; seasonal maintenance and refueling outages must be balanced with solar PV and gas-turbine reserves
Clean Energy Certificates (CECs) EWEC / Abu Dhabi DoE Registry Active periodic auctions Industrial energy users and data-center operators must purchase and retire CECs directly to substantiate 24/7 or annual clean-power procurement claims
Potential New Reactors (Units 5/6 or SMRs) ENEC / FANR / UAE Federal Cabinet Pre-application / exploratory stage No statutory construction timeline, fixed tariff, or site permit exists yet for Units 5/6; investment models must exclude unapproved capacity

Implications for Hyperscale Compute, Industry & Clean Molecules

Barakah's 5.6 GW baseload profile alters UAE industrial power economics by pairing daytime solar photovoltaic surpluses with firm, dispatchable 24/7 zero-carbon electricity across the Emirates National Grid.

Hyperscale AI & Data-Center Baseload

Unlike intermittent solar parks, Barakah's four APR-1400 units operate at high annual capacity factors across summer peak cooling seasons. Hyperscale data-center campuses in Abu Dhabi leverage EWEC grid supply paired with nuclear-backed CECs to satisfy corporate zero-carbon commitments without oversized on-site battery arrays.

Green Hydrogen & Low-Carbon Industrial Exports

Export-oriented UAE aluminum, steel, and low-carbon hydrogen or ammonia producers subject to the EU Carbon Border Adjustment Mechanism (CBAM) rely on verifiable electricity emission factors. Formal CEC retirement linked to Barakah nuclear generation provides auditable zero-emission electricity provenance for Scope 2 calculations.

Refueling Outages & Decommissioning Reserves

Operational underwriting across the 60-year license window requires accounting for staggered 12-to-18-month refueling and maintenance outages per unit, nuclear fuel supply-chain diversification, and FANR-mandated spent-fuel storage and end-of-life decommissioning asset reserves maintained over the plant's operating horizon.

Executive Regulatory Q&A

What is the operational status of all four Barakah nuclear units in 2026?
All four APR-1400 pressurized water reactors at Barakah in Al Dhafra, Abu Dhabi are commercially operational. Unit 1 entered commercial operation in April 2021, Unit 2 in March 2022, Unit 3 in February 2023, and Unit 4 in September 2024. Combined nameplate capacity is 5,600 MW (5.6 GW), generating roughly 40 TWh annually or 25 percent of UAE electricity.
How are ENEC, Nawah Energy Company, and Barakah One structured?
The Emirates Nuclear Energy Corporation (ENEC) owns 82 percent and Korea Electric Power Corporation (KEPCO) holds an 18 percent equity stake in the project's operating and commercial joint ventures. Nawah Energy Company serves as the FANR-licensed nuclear operator, while Barakah One Company manages commercial power sales under a long-term Power Purchase Agreement with EWEC.
What regulatory lifecycle governs Barakah under FANR licensing?
The Federal Authority for Nuclear Regulation (FANR), established as an independent regulator under Federal Decree-Law No. 6 of 2009, issues separate unit-by-unit construction and 60-year operating licenses to Nawah Energy Company. Throughout the 60-year operating period, FANR enforces continuous nuclear safety inspections, physical protection rules, radiation protection, and decommissioning funding verification.
How do UAE businesses procure nuclear attributes via EWEC Clean Energy Certificates?
Under the Abu Dhabi Department of Energy framework, Emirates Water and Electricity Company (EWEC) operates as Single Registrant and Scheme Operator for Clean Energy Certificates (CECs). Issued in 1 MWh units for verified zero-carbon generation from Barakah and solar plants, CECs are auctioned to UAE corporations to substantiate Scope 2 decarbonization claims.
Have Barakah Units 5 or 6 been approved or licensed for construction as of 2026?
No. Only Units 1 through 4 are constructed and licensed at the Barakah site. While ENEC has held exploratory feasibility discussions with South Korean partners regarding potential additional large reactors and evaluated Small Modular Reactors (SMRs) for industrial demand, FANR has not issued construction or operating licenses for Unit 5 or Unit 6.
What should industrial power buyers verify before relying on Barakah clean power claims?
Corporate energy buyers and data-center developers cannot claim nuclear electricity solely from grid connection proximity. Buyers must acquire and retire matching Clean Energy Certificates through EWEC quarterly auctions or bilateral registrations, verify Abu Dhabi Department of Energy registry retirement statements, and account for scheduled refueling outage windows across the four-unit fleet.

Official References & Regulatory Records

All operational capacities, 60-year license terms, equity joint-venture shares, and clean energy certificate rules are anchored directly to ENEC, FANR, and EWEC institutional records.

Regulatory Verification & Primary Basis

Every capacity metric, licensing term, and joint-venture structure in this briefing is anchored directly to official ENEC, FANR, and EWEC publications cited above. ESI maintains strict separation between licensed commercial capacity and exploratory expansion proposals.

Primary-Source AnchoringAll reactor commissioning dates (2021-2024), 60-year FANR license terms, and CEC registry governance details are verified against primary UAE federal and emirate-level authorities.
Underwriting & Diligence ProtocolIndustrial buyers and CBAM-exposed exporters should verify executed EWEC Clean Energy Certificate retirements and Abu Dhabi DoE metering confirmations rather than relying on aggregate UAE grid averages.