Oman: Green Hydrogen Framework & Hydrom Auctions

Enacted under Royal Decree 10/2023, Oman's green hydrogen regime empowers state orchestrator Hydrom to sub-contract state land usufruct blocks via competitive auctions overseen by the Ministry of Energy and Minerals. Following eight Round 1 and 2 awards across Duqm and Dhofar, Hydrom announced two Round 3 Duqm consortia in November 2026 targeting 2032 output alongside OQGN's 400 km open-access hydrogen pipeline network.
Royal Decree 10/2023 Hydrom Rounds 1-4 OQGN 400 km CUI
Primary source: Hydrom Official Auction Portal & MEM Framework. Verified Nov 2026.
Statutory Anchor
RD 10/2023
Earmarks state land & Hydrom usufruct rights.
2030 Target Pipeline
1.0-1.5 Mt/yr
Eight Round 1 & 2 blocks across Duqm & Dhofar.
Round 3 Min Block
100 sq km
Flexible Duqm footprint; Nov 2026 awards for 2032.
OQGN Corridor
~400 km
Purpose-built common-user hydrogen pipeline plan.

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
Royal Decree No. 10/2023 (Land & Usufruct)
Sovereign Renewable & Clean Hydrogen Land Allocation
Enacted Primary Legislation Ministry of Energy & Minerals (MEM) Enacted 2023 (Active) Grants state land usufruct to Hydrom for developer sub-allocation
Hydrom Auction Rounds 1 & 2 (Phase A/B)
Duqm (Al Wusta) & Salalah (Dhofar) Concessions
Awarded; Engineering & FEED Hydrogen Oman SPC (Hydrom) Awarded 2023-2024; 2030+ COD targets 8 project blocks (~1.38-1.5 Mt/yr headline H2 target)
Hydrom Round 3 & Round 4 Auctions
Flexible Duqm Blocks & Data-Center Coupling
R3 Awarded / R4 Launched Nov 2026 Hydrom R3 Awards Nov 2026 (2032 COD); R4 Open Nov 2026 100 sq km minimum block; R3 awards 625k tpa AN + 400k tpa NH3
OQGN Common-User Infrastructure (CUI)
Open-Access Hydrogen Pipeline & Utility Corridors
Feasibility & Commercial Structuring OQ Gas Networks (OQGN) / Hydrom 2025-2026 Engineering; Late-Decade Commissioning ~400 km total (~200 km in Duqm + Salalah port corridor)

Royal Decree 10/2023 & Hydrom Rounds 1 through 4

Oman centralized land assembly under Hydrom to eliminate fragmented bilateral land speculation and recalibrated its Round 3 terms in 2025-2026 to reflect slower global FID timelines.

Oman's regulatory model separates sovereign land assembly from downstream industrial execution. Under Royal Decree No. 10/2023, the Sultanate formally earmarked expansive desert zones in Al Wusta (Duqm and Al Jazir) and Dhofar (Salalah) exclusively for utility-scale renewable electricity and clean hydrogen production. Article III of the decree transfers usufruct rights over those state lands to Hydrogen Oman SPC (Hydrom) at the request of the Ministry of Energy and Minerals (MEM), enabling Hydrom to carve standardized blocks and award sub-usufruct concessions through competitive public tenders while MEM retains statutory oversight of sector licensing and technical compliance.

Rounds 1 and 2 established Oman's headline 2030 ambition of 1.0 to 1.5 million tonnes per year (Mt/yr) of green hydrogen across eight awarded and legacy-integrated blocks in Duqm and Dhofar. Round 1 (awards finalized March-June 2023) selected major consortia in Duqm: Amnah (Copenhagen Infrastructure Partners, Blue Power Partners, and Al Khadra targeting ~200 ktpa green hydrogen for Port of Duqm green steel), Green Energy Oman (OQ, Shell, EnerTech, InterContinental Energy, and Golden Wellspring Wealth), BP Oman, Hyport Duqm (OQ Alternative Energy and DEME Concessions, 1.3 GW Phase 1), and the POSCO-ENGIE consortium (POSCO Holdings, MESCAT, Samsung Engineering, EWP, KOSPO, and FutureTech targeting 1.2 Mtpa green ammonia). Round 2 (awards signed April-May 2024) expanded into Dhofar with the Actis-Fortescue alliance (~4.5 GW wind/solar targeting up to 200 ktpa hydrogen into ammonia via Salalah) and the EDF-JERA-Yamna consortium.

Between 2025 and November 2026, global hydrogen market headwinds prompted Hydrom to adjust project pacing and redesign Round 3 rather than push unrealistic 2030 FID assumptions. Launched in late April 2025 with RFP submissions closing 31 January 2026, Round 3 offered up to 300 square kilometers in Duqm while cutting the minimum entry footprint to 100 square kilometers, extending bid preparation to nine months, lowering development-stage land lease costs, removing rigid two-sided pricing structures, permitting surplus renewable electricity sales to Oman's grid, and allowing downstream diversification beyond ammonia. On the sidelines of COP31 in November 2026, Hydrom executed Round 3 awards for two consortia targeting commercial operation by 2032, and simultaneously launched Round 4 with explicit provisions allowing developers to couple green hydrogen sites with dedicated renewable power supply for data centers.

Hydrom Round Geography & Window Key Awarded Consortia / Sponsors Target Scale & Product Key Regulatory Evolution
Round 1 (Phase A) Duqm / Al Wusta (Awards Mar-Jun 2023) Amnah (CIP/Al Khadra), GEO (OQ/Shell/EnerTech/ICE), BP Oman, Hyport Duqm (OQ/DEME), POSCO-ENGIE ~1 Mtpa national anchor; multi-GW renewables for export NH3 & Duqm green steel First centralized sub-usufruct auction under RD 10/2023
Round 2 Dhofar / Salalah (Awards Apr-May 2024) Actis & Fortescue; EDF, JERA & Yamna consortium Portfolios totaling ~1.38-1.5 Mt/yr national pipeline across R1+R2; Salalah export NH3 Expanded solar-wind complementarity into southern monsoon wind corridor
Round 3 Duqm (Launched Apr 2025; Awarded Nov 2026 at COP31) (1) Petrogas E&P & Bio3Energy; (2) PLN Indonesia Power, Alawi Enterprises & HBA Offshore (1) 625k tpa green ammonium nitrate (1.16 GW RE); (2) 400k tpa green NH3 (1.45 GW PV / 1 GW electrolyzer) by 2032 100 sq km min block, reduced early land fees, grid-surplus monetization, 2032 COD horizon
Round 4 Designated State Blocks (Launched Nov 2026 at COP31) Open competitive qualification window Integrated clean hydrogen and co-located data-center renewable power Couples electrolysis flexibility with hyperscale data-center load bankability

OQGN Hydrogen Corridors, MEM Royalties & Usufruct Terms

Oman pairs project-specific land-lease scaling and MEM royalty mechanics with OQGN's open-access common-user infrastructure to avoid redundant pipeline CAPEX.

Royal Decree 10/2023 establishes the legal ownership of hydrogen land blocks without locking rigid statutory royalty percentages or flat land-lease tariffs into primary legislation. Instead, financial obligations are governed through MEM policy schedules and bespoke Project Development Agreements (PDAs) and Sub-Usufruct Agreements executed with Hydrom. Because large-scale electrolysis requires hundreds of square kilometers of desert land for wind turbines and photovoltaic arrays long before revenue begins, MEM and Hydrom structured Round 1 through Round 3 with stepped usufruct charges: fees remain heavily discounted during FEED and construction windows and step up to full commercial lease rates upon Commercial Operation Date (COD).

Government take combines scaled land usufruct fees with production- or revenue-linked royalties, upside sharing mechanisms, and sovereign back-in rights allowing designated state entities (such as Energy Development Oman or OQ vehicles) to take equity participation at defined project milestones, balanced against targeted corporate tax exemptions during initial capital recovery. Exact royalty percentages and equity back-in thresholds are not fixed in primary statute; they are determined per auction tender rules and individual project agreements.

To prevent each consortium from building isolated pipelines and seawater desalination intakes across coastal Duqm and Salalah, Oman mandated a Common-User Infrastructure (CUI) model led by national gas grid operator OQ Gas Networks (OQGN) alongside Hydrom. Across 2025 and 2026, OQGN advanced engineering and commercial studies for roughly 400 kilometers of dedicated, purpose-built open-access green hydrogen pipelines, led by approximately 200 kilometers inside Al Duqm plus dedicated export corridors in Salalah and Al Jazir. Critically, OQGN confirmed it will construct new hydrogen-grade pipelines rather than repurposing existing natural gas transmission lines, which remain fully committed to domestic gas demand.

Regulatory / Infrastructure Parameter Governing Institution Legal & Commercial Mechanism Impact on Project Economics & Permitting
Sub-Usufruct Land Lease Fees Hydrom / MEM RD 10/2023 land transfer; stepped lease schedule in auction rounds Discounted fees during FEED/construction; full commercial rates post-COD
Production Royalties & State Back-In MEM / Ministry of Finance / EDO Not fixed in primary statute; governed per auction & PDA terms Combines base production/revenue royalties with state equity back-in options
OQGN Duqm & Salalah Hydrogen Pipelines OQGN / Hydrom Steering Committee ~400 km total open-access CUI (~200 km in Duqm + Salalah corridor) Purpose-built H2 lines; removes single-project pipeline duplication CAPEX
Grid Surplus & Data-Center Coupling Hydrom / Nama Power & Water Procurement / APSR Round 3 grid-sale option & Round 4 data-center power pairing Allows surplus RE monetization during electrolyzer curtailment or ramp phases

Development Milestones, Offtake Realities & Permitting Controls

Awarded Hydrom land blocks represent conditional development rights rather than financed construction assets; sponsors must navigate CUI tariffs, grid permits, and European/Asian certification.

Hydrom's 2025-2026 recalibration underscores a critical distinction for institutional investors: winning a land sub-usufruct auction in Oman establishes exclusivity over solar and wind resources, not an unconditional construction permit or commercial return. Earlier Round 1 and Round 2 consortia continue progressing through multi-year wind-resource measurement campaigns, Front-End Engineering Design (FEED), environmental permitting under the Environment Authority (EA), and port-terminal allocation inside Special Economic Zone at Duqm (SEZAD) or Port of Salalah. Shifting target CODs in Round 3 out to 2032 reflects realistic electrolyzer stack delivery schedules, port ammonia tank buildouts, and binding offtake negotiations in Europe, Japan, South Korea, and India.

For equity sponsors and industrial offtakers evaluating Oman hydrogen allocations, diligence should concentrate on three binding execution interfaces:

Common-User Tariff & COD Alignment

Individual project FID schedules depend on OQGN finalizing open-access pipeline transportation tariffs, desalination water-corridor charges, and SEZAD/Salalah berth readiness. Sponsors must verify step-in remedies and schedule-coordination clauses if shared CUI commissioning lags behind private electrolyzer construction.

RFNBO & CertifHy Compliance

Export-oriented ammonia consortia targeting European industrial buyers must structure wind/solar temporal correlation and grid-connection boundaries to satisfy EU Renewable Fuels of Non-Biological Origin (RFNBO) delegated acts, particularly when utilizing Round 3 surplus electricity export options.

Phased Land & Milestone Relinquishment

Sub-usufruct agreements under Hydrom attach strict development milestone dates to land retention, such as the 100 sq km base plus 100 sq km expansion reserve in Round 3. Capital budgets should stage equity commitments strictly behind meteorological mast completion, EA environmental permits, and binding physical offtake contracts.

Executive Regulatory Q&A

What legal authority does Royal Decree 10/2023 grant to Hydrom?
Royal Decree 10/2023 earmarks designated state-owned land blocks in Oman exclusively for renewable power and clean hydrogen projects and grants usufruct rights over those blocks to Hydrogen Oman SPC (Hydrom) upon request by the Ministry of Energy and Minerals. Hydrom divides those blocks and grants sub-usufruct rights to winning consortia through competitive auctions.
Which major consortia won Round 1 and Round 2 land blocks in Duqm and Dhofar?
Rounds 1 and 2 awarded eight project blocks across Duqm and Dhofar targeting roughly 1.38 to 1.5 million tonnes per year of green hydrogen capacity toward 2030. Awarded Round 1 Duqm consortia include Amnah, Green Energy Oman, BP Oman, Hyport Duqm, and POSCO-ENGIE, followed in Round 2 Dhofar by Actis-Fortescue and the EDF-JERA-Yamna alliance.
What changed in Hydrom Round 3 and what was awarded in November 2026?
Hydrom's Round 3 introduced smaller 100 square kilometer minimum footprints within 300 square kilometers in Duqm, discounted early-stage land fees, surplus grid-power sales options, and downstream product flexibility. Announced at COP31 in November 2026, awards went to Petrogas-Bio3Energy for 625,000 tpa green ammonium nitrate and PLN-Alawi-HBA for 400,000 tpa green ammonia by 2032.
How does OQGN's Common-User Infrastructure pipeline model reduce project CAPEX?
OQ Gas Networks (OQGN) is structuring roughly 400 kilometers of purpose-built open-access green hydrogen pipelines, anchored by about 200 kilometers in Al Duqm plus Salalah export corridors, rather than repurposing existing natural gas lines. Shared common-user pipelines, power corridors, and water networks prevent duplicate coastal transmission buildouts across multiple consortia.
Are land lease fees and production royalties fixed in Royal Decree 10/2023?
No. Royal Decree 10/2023 establishes the land-usufruct framework without fixing static numerical royalty percentages in primary statute. Usufruct fees, scaled development-phase discounts, production royalties, and state back-in equity rights are set per auction schedule and project development agreement overseen by the Ministry of Energy and Minerals and Hydrom.
What new feature did Hydrom introduce with Round 4 at COP31 in November 2026?
Launched alongside the Round 3 awards at COP31 in November 2026, Hydrom's Round 4 expands land-allocation flexibility by permitting developers to couple green hydrogen production directly with dedicated renewable power supply for data centers, broadening domestic commercial monetization pathways beyond maritime ammonia exports.

Official References & Statutory Filings

Links point to Omani ministerial portals, Hydrom auction documentation, legislative registries, and national grid operators reviewed through November 2026.

Regulatory Verification & Primary Basis

Every statutory status, threshold, and compliance boundary in this briefing is anchored directly to the primary legislative registers, regulatory orders, and ministerial publications cited above. ESI maintains strict separation between enacted legal provisions and commercial projections.

Primary-Source Anchoring: All programme parameters, eligibility rules, and award records are verified against official issuing-authority documentation rather than secondary press estimates.
Underwriting & Diligence Protocol: Before capital deployment or financial close, funds and project sponsors should confirm active statutory windows, transitional grandfathering rules, and site-specific legal/tax counsel sign-off.
Reviewed & Verified by Khaled Shawky Β· Senior Data Analyst, Energy Solutions Intelligence Verification Cycle: November 2026