Permitting & Red Tape · Mexico · Verified Nov 2026

Mexico: CNE distributed generation rules

Under Mexico's March 2025 Ley del Sector Eléctrico, permit-exempt distributed generation (Generación Distribuida) expanded from 0.5 MW to below 0.7 MW on qualifying distribution circuits, supervised by the new Comisión Nacional de Energía (CNE) replacing CRE. Projects from 0.7 MW to 20 MW enter the permitted Autoconsumo track, while all sub-0.7 MW systems still require CFE Distribución technical interconnection approval.
<0.7 MW Permit-Exempt CNE Replaced CRE 0.7-20 MW Autoconsumo
Primary sources: DOF Ley del Sector Eléctrico 2025 · CNE Official Portal. Verified Nov 2026.
DG Permit Ceiling
< 0.7 MW
Raised from 0.5 MW on Mar 18, 2025.
Autoconsumo Track
0.7-20 MW
Simplified CNE permit & VUA filing.
Competent Regulator
CNE
Replaced CRE under SENER oversight.
H1 2026 Capacity
5,675 MW
655,417 requests; 99.5% solar PV.

Institutional Regulatory Summary

Mexico's 2025-2026 electricity overhaul repealed the 2014 Electricity Industry Law (LIE), dissolved the autonomous CRE into the SENER-aligned Comisión Nacional de Energía (CNE), and redrew the statutory boundary between exempt distributed generation and permitted industrial self-supply.

Mechanism Status Authority Effective Window Key Threshold
Ley del Sector Eléctrico (LSE 2025)
Exempt Distributed Generation (Generador Exento)
Enacted Statute DOF / CNE Published Mar 18, 2025 onward < 0.7 MW (700 kW) on distribution circuits; permit-exempt
Autoconsumo DACGs & VUA Platform
On-Site Industrial & Commercial Generation
Active Regulatory Track CNE / SENER / CENACE 2025-2026 Implementation 0.7 MW to 20 MW simplified CNE permit; backup/storage if exporting
CNE Unified Interconnection Contract Model
RNT/RGD Contract & SAEE Storage Rules
Enacted Agreement DOF / CNE Published Mar 17, 2026 Applies to ≥0.7 MW plants, SAEE storage, & ≥1 MW loads; excludes sub-0.7 MW GD
Legacy GD DACGs (RES/142/2017 & RES/054/2017 Lineage)
Interconnection & Compensation Frameworks
Transitional Basis CNE / CFE Distribución Active until superseded by CNE GD DACGs Medición Neta, Facturación Neta (PML), and Venta Total models

March 2025 Ley del Sector Eléctrico: From 0.5 MW to 0.7 MW and CRE to CNE

Published in the Diario Oficial de la Federación (DOF) on March 18, 2025, the Ley del Sector Eléctrico (LSE) replaced the 2014 Ley de la Industria Eléctrica (LIE) and restructured Mexico's institutional governance and distributed generation capacity ceilings.

The 40% Ceiling Expansion (< 0.7 MW)

Under the repealed LIE, permit-exempt distributed generation stopped at 0.5 MW (500 kW). The 2025 LSE raised that statutory threshold to strictly below 0.7 MW (700 kW) for generation units interconnected to a qualifying distribution circuit. For commercial rooftops, cold-storage warehouses, and light industrial parks in nearshoring corridors, an additional 200 kW of inverter capacity per meter avoids formal generation licensing altogether.

CRE Abolished, CNE Empowered

The constitutional and statutory overhaul dissolved the former Comisión Reguladora de Energía (CRE) and transferred regulatory authority to the Comisión Nacional de Energía (CNE), operating as a decentralized technical organ within the Ministry of Energy (SENER). CNE issues generation permits, drafts Disposiciones Administrativas de Carácter General (DACGs), approves standardized interconnection contracts, and publishes official capacity statistics.

Scale of Adoption (H1 2026 Baseline)

According to official CNE reporting through the end of the first half of 2026, Mexico's distributed generation fleet reached 5,675.47 MW of cumulative installed capacity across 655,417 interconnection requests, up roughly 9.4% from 5,189.71 MW at year-end 2025. Solar photovoltaics account for over 99.5% (5,649.34 MW), representing more than 14.58 billion USD in cumulative capital deployment led by Jalisco, Nuevo León, and Chihuahua.

Capacity Tiers Under the 2025-2026 Mexican Regulatory Regime

Crossing the 0.7 MW boundary changes a project's entire legal classification, permit timeline, grid-study authority, and storage requirement. Sponsors sizing industrial behind-the-meter solar arrays must map their AC inverter nameplate cleanly against these three statutory bands.

Installed AC Capacity Band Legal Classification CNE Generation Permit Grid Study & Contract Route Surplus Injection & Backup Rules
Below 0.7 MW (< 700 kW) Generación Distribuida (Generador Exento) Exempt (No CNE permit required) CFE Distribución feeder feasibility review + GD DACG contract Medición Neta, Facturación Neta (PML), or Venta Total
0.7 MW to 20 MW Autoconsumo Interconectado (Simplified Track) Mandatory (Simplified CNE permit via VUA) CENACE interconnection study + CFE/RGD or RNT + Mar 2026 unified contract Surplus sold only to CFE or injected per CNE terms; BESS/backup required for intermittent export
Above 20 MW (> 20 MW) Autoconsumo / Utility Generation Mandatory (Full CNE permit & SENER planning alignment) Full CENACE RNT/RGD studies, MISSE social impact, Mar 2026 unified contract Subject to PLADESE planning, strict dispatch/backup compliance, and state-led grid priority

RES/054/2017, RES/142/2017 Lineage & the Three Settlement Models

While CNE updates secondary Disposiciones Administrativas de Carácter General (DACGs) to reflect the 0.7 MW ceiling, practical interconnection and settlement for exempt generators continue to rely on the three compensation structures established under the 2017 CRE regulatory framework.

Commercial sponsors and legal teams often reference RES/054/2017 alongside RES/142/2017 when auditing Mexican distributed generation portfolios. Published in the DOF on March 7, 2017, RES/142/2017 enacted the core DACGs, model interconnection contracts, technical specifications, and counter-value formulas for clean distributed generation, whereas RES/054/2017 governed transitional migration rules for legacy small- and medium-scale contracts executed under the pre-2014 public service law. Under the 2025 LSE transitional clauses, existing contracts and technical manuals remain valid until explicitly superseded by CNE replacement instruments.

Significantly, on March 17, 2026, CNE published a landmark DOF agreement (Acuerdo) establishing a single unified model contract for interconnection to the National Transmission Grid (RNT) and General Distribution Networks (RGD), formally incorporating standalone Energy Storage Systems (Sistemas de Almacenamiento de Energía Eléctrica, SAEE) and load centers of 1 MW or above. That March 2026 order explicitly carves out Distributed Generation below 0.7 MW, confirming that exempt sub-0.7 MW projects continue using dedicated distributed generation contract templates rather than full utility-scale RNT/RGD agreements.

Compensation Model Supply Contract Link Export Valuation Mechanism Credit Carryforward & Cash-Out Primary Commercial Fit
Medición Neta (Net Metering) Requires active CFE Basic Supply (Suministro Básico) contract 1:1 kWh volumetric offset against grid energy imported in billing cycle Excess kWh banked for up to 12 months; liquidated at cycle end per DACG rules Residential, SMEs, and daytime commercial loads with balanced tariffs
Facturación Neta (Net Billing) Requires active CFE supply contract; dual independent energy flows Imports billed at regulated CFE tariff; exports credited in MXN at hourly nodal PML Monetary credit applied against CFE bill; reduces exposure to tariff tier distortion Industrial/commercial sites (GDMTH/GDMTO) with mid-day export surpluses
Venta Total (Full Export) No associated load supply contract on that interconnection point 100% of metered generation compensated in MXN at hourly nodal PML Monthly monetary settlement by CFE; exposed to nodal congestion & solar cannibalization Dedicated sub-0.7 MW merchant or community plots without host load

CFE Distribución Bottlenecks & the 0.7-20 MW Autoconsumo Track

Raising the statutory permit-exemption ceiling to 0.7 MW removes CNE licensing friction, but physical grid access through CFE Distribución and the 0.7-20 MW Autoconsumo rules remain decisive project gates.

CFE Distribución Viability Is Not Automatic

Even for a 450 kW or 690 kW rooftop system exempt from a CNE generation permit, interconnection to CFE Distribución's General Distribution Networks (RGD) is never guaranteed. CFE evaluates local feeder thermal capacity, transformer loading, short-circuit contribution, and voltage rise. On saturated industrial park circuits in Monterrey, Guadalajara, or Querétaro, CFE can require transformer upgrades, zero-export relay settings, or feeder reinforcements funded directly by the developer before energizing.

0.7-20 MW Autoconsumo & VUA

Industrial facilities requiring 700 kW to 20 MW must apply for a CNE Autoconsumo generation permit. To accelerate industrial nearshoring builds, SENER, CNE, CENACE, and CFE launched the Ventanilla Única de Autoconsumo (VUA), integrating CENACE grid studies, CFE Distribución reviews, SENER's Social Impact Assessment (MISSE), and CNE electronic filing (OPE) with bounded institutional review clocks. Note that intermittent plants exporting surpluses face mandatory storage (BESS) or backup obligations and minimum self-consumption utilization thresholds to prevent permit revocation.

Sponsor Equity & EPC Diligence

Project sponsors structuring commercial and industrial rooftop portfolios in Mexico should avoid splitting a single 1.4 MW industrial roof into two artificial 699 kW systems at the same electrical point of common coupling, as CFE and CNE enforce anti-fragmentation aggregation checks. Equity returns should be underwritten strictly on self-consumption tariff avoidance rather than speculative nodal PML export revenues, while EPC agreements must condition milestone payments on formal CFE feasibility clearance and bidirectional meter commissioning.

Executive Regulatory Q&A

What is the maximum size for permit-exempt distributed generation in Mexico after March 2025?
Under Mexico's Ley del Sector Eléctrico published on March 18, 2025, permit-exempt distributed generation (Generación Distribuida or Generador Exento) applies to plants with capacity strictly below 0.7 MW (700 kW) connected to a qualifying distribution circuit. This raised the prior 0.5 MW limit from the repealed 2014 Electricity Industry Law by 40%.
Which agency replaced the CRE for distributed generation and interconnection oversight?
The Comisión Nacional de Energía (CNE), established as a decentralized technical body under the Ministry of Energy (SENER), replaced the former Comisión Reguladora de Energía (CRE). The CNE now oversees generation permits, DACG rules, interconnection contract models, and compensation methodologies, coordinating grid studies with CENACE and CFE Distribución.
Does an exempt plant below 0.7 MW bypass CFE Distribución interconnection approval?
No. Permit exemption under the Ley del Sector Eléctrico only waives the CNE generation permit requirement. Every sub-0.7 MW installation must still submit a formal interconnection request to CFE Distribución, pass circuit hosting-capacity and technical viability checks, install compliant bidirectional metering, and execute the applicable interconnection contract.
How are commercial projects between 0.7 MW and 20 MW regulated in Mexico?
Projects at or above 0.7 MW fall outside distributed generation and enter the permitted Autoconsumo regime. Under CNE Disposiciones Administrativas de Carácter General (DACGs), interconnected projects from 0.7 MW to 20 MW qualify for a streamlined permit track processed through the Ventanilla Única de Autoconsumo alongside CENACE studies and storage or backup requirements for surplus injection.
What is the difference between Medición Neta, Facturación Neta, and Venta Total?
Medición Neta (Net Metering) offsets exported kilowatt-hours against consumed kilowatt-hours with annual credit carryforward. Facturación Neta (Net Billing) settles consumption at the regulated CFE tariff while crediting exports at the hourly nodal Precio Marginal Local (PML). Venta Total exports 100% of output without an associated supply load at hourly PML.
Does the March 17, 2026 CNE unified interconnection contract apply to sub-0.7 MW rooftop solar?
No. The March 17, 2026 DOF agreement by CNE establishes a single unified interconnection and connection contract model for transmission and distribution assets such as autoconsumo plants, large loads of 1 MW or more, and standalone battery systems. Sub-0.7 MW distributed generation remains governed by dedicated distributed generation DACG contracts.

Official references used

Links point to Mexico's Diario Oficial de la Federación, the Comisión Nacional de Energía, and CENACE grid portals. Verified November 2026.

Regulatory Verification & Primary Basis

Every statutory status, threshold, and compliance boundary in this briefing is anchored directly to the Diario Oficial de la Federación, CNE resolutions, and CENACE technical registries cited above. ESI maintains strict separation between enacted legal provisions and commercial projections.

Primary-Source AnchoringAll capacity ceilings, Autoconsumo permit tiers, contract exclusions, and H1 2026 deployment volumes are verified against official Mexican government publications rather than secondary estimates.
Underwriting & Diligence ProtocolBefore capital deployment or EPC execution, sponsors should confirm local CFE Distribución circuit hosting capacity, anti-fragmentation aggregation rules, and active CNE DACG contract templates with Mexican energy counsel.
Reviewed & Verified by Khaled Shawky · Lead Energy Policy & Infrastructure Analyst, Energy Solutions Intelligence Verification Cycle: November 2026