Mexico's 2025-2026 electricity overhaul repealed the 2014 Electricity Industry Law (LIE), dissolved the autonomous CRE into the SENER-aligned Comisión Nacional de Energía (CNE), and redrew the statutory boundary between exempt distributed generation and permitted industrial self-supply.
| Mechanism | Status | Authority | Effective Window | Key Threshold |
|---|---|---|---|---|
| Ley del Sector Eléctrico (LSE 2025) Exempt Distributed Generation (Generador Exento) |
Enacted Statute | DOF / CNE | Published Mar 18, 2025 onward | < 0.7 MW (700 kW) on distribution circuits; permit-exempt |
| Autoconsumo DACGs & VUA Platform On-Site Industrial & Commercial Generation |
Active Regulatory Track | CNE / SENER / CENACE | 2025-2026 Implementation | 0.7 MW to 20 MW simplified CNE permit; backup/storage if exporting |
| CNE Unified Interconnection Contract Model RNT/RGD Contract & SAEE Storage Rules |
Enacted Agreement | DOF / CNE | Published Mar 17, 2026 | Applies to ≥0.7 MW plants, SAEE storage, & ≥1 MW loads; excludes sub-0.7 MW GD |
| Legacy GD DACGs (RES/142/2017 & RES/054/2017 Lineage) Interconnection & Compensation Frameworks |
Transitional Basis | CNE / CFE Distribución | Active until superseded by CNE GD DACGs | Medición Neta, Facturación Neta (PML), and Venta Total models |
Published in the Diario Oficial de la Federación (DOF) on March 18, 2025, the Ley del Sector Eléctrico (LSE) replaced the 2014 Ley de la Industria Eléctrica (LIE) and restructured Mexico's institutional governance and distributed generation capacity ceilings.
Under the repealed LIE, permit-exempt distributed generation stopped at 0.5 MW (500 kW). The 2025 LSE raised that statutory threshold to strictly below 0.7 MW (700 kW) for generation units interconnected to a qualifying distribution circuit. For commercial rooftops, cold-storage warehouses, and light industrial parks in nearshoring corridors, an additional 200 kW of inverter capacity per meter avoids formal generation licensing altogether.
The constitutional and statutory overhaul dissolved the former Comisión Reguladora de Energía (CRE) and transferred regulatory authority to the Comisión Nacional de Energía (CNE), operating as a decentralized technical organ within the Ministry of Energy (SENER). CNE issues generation permits, drafts Disposiciones Administrativas de Carácter General (DACGs), approves standardized interconnection contracts, and publishes official capacity statistics.
According to official CNE reporting through the end of the first half of 2026, Mexico's distributed generation fleet reached 5,675.47 MW of cumulative installed capacity across 655,417 interconnection requests, up roughly 9.4% from 5,189.71 MW at year-end 2025. Solar photovoltaics account for over 99.5% (5,649.34 MW), representing more than 14.58 billion USD in cumulative capital deployment led by Jalisco, Nuevo León, and Chihuahua.
Crossing the 0.7 MW boundary changes a project's entire legal classification, permit timeline, grid-study authority, and storage requirement. Sponsors sizing industrial behind-the-meter solar arrays must map their AC inverter nameplate cleanly against these three statutory bands.
| Installed AC Capacity Band | Legal Classification | CNE Generation Permit | Grid Study & Contract Route | Surplus Injection & Backup Rules |
|---|---|---|---|---|
| Below 0.7 MW (< 700 kW) | Generación Distribuida (Generador Exento) | Exempt (No CNE permit required) | CFE Distribución feeder feasibility review + GD DACG contract | Medición Neta, Facturación Neta (PML), or Venta Total |
| 0.7 MW to 20 MW | Autoconsumo Interconectado (Simplified Track) | Mandatory (Simplified CNE permit via VUA) | CENACE interconnection study + CFE/RGD or RNT + Mar 2026 unified contract | Surplus sold only to CFE or injected per CNE terms; BESS/backup required for intermittent export |
| Above 20 MW (> 20 MW) | Autoconsumo / Utility Generation | Mandatory (Full CNE permit & SENER planning alignment) | Full CENACE RNT/RGD studies, MISSE social impact, Mar 2026 unified contract | Subject to PLADESE planning, strict dispatch/backup compliance, and state-led grid priority |
While CNE updates secondary Disposiciones Administrativas de Carácter General (DACGs) to reflect the 0.7 MW ceiling, practical interconnection and settlement for exempt generators continue to rely on the three compensation structures established under the 2017 CRE regulatory framework.
Commercial sponsors and legal teams often reference RES/054/2017 alongside RES/142/2017 when auditing Mexican distributed generation portfolios. Published in the DOF on March 7, 2017, RES/142/2017 enacted the core DACGs, model interconnection contracts, technical specifications, and counter-value formulas for clean distributed generation, whereas RES/054/2017 governed transitional migration rules for legacy small- and medium-scale contracts executed under the pre-2014 public service law. Under the 2025 LSE transitional clauses, existing contracts and technical manuals remain valid until explicitly superseded by CNE replacement instruments.
Significantly, on March 17, 2026, CNE published a landmark DOF agreement (Acuerdo) establishing a single unified model contract for interconnection to the National Transmission Grid (RNT) and General Distribution Networks (RGD), formally incorporating standalone Energy Storage Systems (Sistemas de Almacenamiento de Energía Eléctrica, SAEE) and load centers of 1 MW or above. That March 2026 order explicitly carves out Distributed Generation below 0.7 MW, confirming that exempt sub-0.7 MW projects continue using dedicated distributed generation contract templates rather than full utility-scale RNT/RGD agreements.
| Compensation Model | Supply Contract Link | Export Valuation Mechanism | Credit Carryforward & Cash-Out | Primary Commercial Fit |
|---|---|---|---|---|
| Medición Neta (Net Metering) | Requires active CFE Basic Supply (Suministro Básico) contract | 1:1 kWh volumetric offset against grid energy imported in billing cycle | Excess kWh banked for up to 12 months; liquidated at cycle end per DACG rules | Residential, SMEs, and daytime commercial loads with balanced tariffs |
| Facturación Neta (Net Billing) | Requires active CFE supply contract; dual independent energy flows | Imports billed at regulated CFE tariff; exports credited in MXN at hourly nodal PML | Monetary credit applied against CFE bill; reduces exposure to tariff tier distortion | Industrial/commercial sites (GDMTH/GDMTO) with mid-day export surpluses |
| Venta Total (Full Export) | No associated load supply contract on that interconnection point | 100% of metered generation compensated in MXN at hourly nodal PML | Monthly monetary settlement by CFE; exposed to nodal congestion & solar cannibalization | Dedicated sub-0.7 MW merchant or community plots without host load |
Raising the statutory permit-exemption ceiling to 0.7 MW removes CNE licensing friction, but physical grid access through CFE Distribución and the 0.7-20 MW Autoconsumo rules remain decisive project gates.
Even for a 450 kW or 690 kW rooftop system exempt from a CNE generation permit, interconnection to CFE Distribución's General Distribution Networks (RGD) is never guaranteed. CFE evaluates local feeder thermal capacity, transformer loading, short-circuit contribution, and voltage rise. On saturated industrial park circuits in Monterrey, Guadalajara, or Querétaro, CFE can require transformer upgrades, zero-export relay settings, or feeder reinforcements funded directly by the developer before energizing.
Industrial facilities requiring 700 kW to 20 MW must apply for a CNE Autoconsumo generation permit. To accelerate industrial nearshoring builds, SENER, CNE, CENACE, and CFE launched the Ventanilla Única de Autoconsumo (VUA), integrating CENACE grid studies, CFE Distribución reviews, SENER's Social Impact Assessment (MISSE), and CNE electronic filing (OPE) with bounded institutional review clocks. Note that intermittent plants exporting surpluses face mandatory storage (BESS) or backup obligations and minimum self-consumption utilization thresholds to prevent permit revocation.
Project sponsors structuring commercial and industrial rooftop portfolios in Mexico should avoid splitting a single 1.4 MW industrial roof into two artificial 699 kW systems at the same electrical point of common coupling, as CFE and CNE enforce anti-fragmentation aggregation checks. Equity returns should be underwritten strictly on self-consumption tariff avoidance rather than speculative nodal PML export revenues, while EPC agreements must condition milestone payments on formal CFE feasibility clearance and bidirectional meter commissioning.
Links point to Mexico's Diario Oficial de la Federación, the Comisión Nacional de Energía, and CENACE grid portals. Verified November 2026.
Every statutory status, threshold, and compliance boundary in this briefing is anchored directly to the Diario Oficial de la Federación, CNE resolutions, and CENACE technical registries cited above. ESI maintains strict separation between enacted legal provisions and commercial projections.
Connect policy insights directly to interactive engineering calculators, supply-chain bottlenecks, and cost models.