Interconnection Cost Allocation determines who pays for the multi-million dollar high-voltage grid upgrades required to attach a new power plant to the system. This obscure regulatory policy is the single biggest graveyard for renewable energy projects, frequently hitting developers with unexpected $50M upgrade bills that instantly kill project economics.
When a 200MW solar farm requests to connect, ISO engineers run power flow studies (steady-state, short-circuit, and stability). If the new plant pushes an existing transmission line or transformer past its thermal or fault-current limit, a 'Network Upgrade' is required. Cost allocation rules dictate whether the developer pays 100% of this cost (Participant Funding) or if it is shared with the transmission owner and ratepayers.
Feasibility Study
Initial power flow modeling to identify thermal violations (N-0 and N-1 contingencies).
System Impact Study (SIS)
Deep engineering analysis detailing the exact transformers, breakers, or reconductoring required to safely absorb the new MWs.
Facility Study
Finalizing the +/- 20% cost estimate for the required substation expansions and issuing the Interconnection Agreement (IA).
- The 'First-Ready, First-Served' cluster study process means one developer dropping out forces the ISO to recalculate the costs for everyone else.
- Extreme shortage of qualified transmission planning engineers at the ISO level to run the required power flow models.