Executive Summary
Offshore oil and gas platforms have traditionally relied on simple-cycle gas turbines to generate power
from produced gas, resulting in high Scope 1 emissions and low efficiency. Electrifying platforms via
subsea power cables connected to shore grids or offshore wind clusters can materially reduce operating
expenditure (OPEX) and emissions intensity, but only when deployment is carefully sequenced with field
life, distance to shore, and power demand. At
Energy
Solutions Intelligence,
we model offshore electrification as a transition lever rather than a binary switch, focusing on
realistic returns on invested capital for operators and infrastructure investors.
- Indicative full-platform power demand for mature assets typically ranges between 20–80
MW, with legacy gas turbines operating at net electrical efficiencies of
22–30%, translating into high fuel burn and CO₂ intensity.
- Subsea high-voltage cable systems for distances of 50–200 km typically exhibit
installed costs of 1.8–3.5 million USD/km including export cable, topside
integration, and onshore substation work, depending on water depth and route complexity.
- For platforms with remaining lifetimes of 15–25 years, replacing gas turbines with
grid-supplied power can reduce direct CO₂ emissions by 0.3–0.7 tCO₂e/boe and
deliver abatement costs in the range of 40–110 USD/tCO₂, assuming conservative
power prices and cable CAPEX.
- Where offshore wind hubs already exist, tie-in electrification can improve project economics by
10–20% relative to stand-alone cable projects, by sharing export infrastructure and
increasing capacity factors of the offshore grid node.
- Energy Solutions analysis indicates internal rates of return (IRR) of 8–15% are
achievable for well-sited projects when carbon pricing or explicit emissions penalties exceed
80–120 USD/tCO₂, particularly in OECD markets targeting aggressive upstream
decarbonization.
Technical Foundation: How Offshore Platforms Use Power Today
Offshore production platforms are effectively small power plants at sea. They run complex process equipment,
compression, separation, water injection, safety systems and accommodation loads. Historically, this power
has been supplied by simple-cycle gas turbines burning produced gas or imported fuel, sized with significant
redundancy to avoid unplanned shutdowns.
Typical installed power demand for a medium-sized fixed platform lies between 20–50 MW,
while large integrated processing hubs may exceed 80–120 MW across multiple turbine units.
Because turbines rarely operate at their rated capacity, real-world electrical efficiency drops to
22–30%, well below combined-cycle plants onshore.
As climate policies harden and investors scrutinize Scope 1 emissions, these legacy configurations become a
liability. Each incremental barrel produced carries both a commodity margin and a carbon penalty.
Electrification aims to decouple production from on-platform combustion by importing low-carbon electricity
via subsea cables.
Emissions Intensity of Offshore Production: Turbines vs.
Electrified (Indicative)
The chart below illustrates stylised emissions intensity ranges (in kgCO₂e/boe) for conventional
turbine-powered platforms versus electrified platforms connected to relatively low-carbon grids.
Source: Energy Solutions offshore electrification model (indicative ranges, 2026).
Benchmarks & Cost Data: Turbines vs. Subsea Cables
Electrification economics are driven by three main variables: avoided turbine OPEX (fuel and maintenance),
subsea cable and grid connection CAPEX, and residual backup generation costs. Operators rarely decommission
all turbines; they are typically retained for black-start and contingency.
Indicative Installed Cost Benchmarks (2026, Stylised)
| Configuration |
Typical Power Range (MW) |
Installed CAPEX |
Indicative Cost Metric |
| Legacy Gas Turbine Replacement (Like-for-like) |
20–60 |
80–220 million USD |
1,400–2,200 USD/kW (turbine, auxiliaries, integration) |
| Subsea HV Cable 132–220 kV (50–150 km) |
50–200 |
120–420 million USD |
1.8–2.8 million USD/km (including installation) |
| Subsea HV Cable 220–320 kV (150–250 km, deep water) |
100–300 |
260–750 million USD |
2.5–3.5 million USD/km (including deep-water routing) |
| Offshore Wind Hub Tie-in (shared export route) |
50–200 |
70–180 million USD |
900–1,600 USD/kW (incremental for platform offtake) |
All values are indicative, based on stylised 2026 cost ranges and do not represent commercial offers.
Routes with complex seabed conditions, high rock-dumping requirements, or multiple landfalls can sit at
the upper end of the range or above it.
OPEX and Fuel Burn Comparison
Gas turbines consume significant volumes of fuel gas per unit of delivered electricity. For a typical
platform:
- Fuel intensity often ranges between 260–340 Sm³ of natural gas/MWh of electrical
output, depending on load and turbine technology.
- This equates to a variable fuel cost of roughly 35–60 USD/MWh at gas values of
4–8 USD/MMBtu, before considering CO₂ pricing.
- Maintenance OPEX, including major overhauls, commonly adds 15–25 USD/MWh on a levelized
basis over turbine life.
Illustrative OPEX Comparison (Turbines vs. Imported Power)
| Scenario |
Fuel + Maintenance OPEX (USD/MWh) |
CO₂ Cost @ 80 USD/tCO₂ (USD/MWh) |
Total Effective Cost (USD/MWh) |
| On-platform Turbines (Low Gas Value) |
45–65 |
20–30 |
65–95 |
| On-platform Turbines (High Gas Value) |
65–95 |
20–30 |
85–125 |
| Imported Grid Power (Medium-carbon Grid) |
70–110 (energy tariff) |
5–15 (residual emissions) |
75–125 |
| Imported Offshore Wind Power (Long-term PPA) |
55–85 |
5–10 |
60–95 |
These values assume steady operation and do not account for curtailment or emergency diesel use. They
indicate that electrification OPEX is competitive when gas is valuable, carbon prices are material, or
when wind PPAs can be secured at relatively low LCOE.
Levelized Cost of Power Supply to Platforms (Stylised
2026)
The bar chart below compares stylised levelized power supply costs under three configurations: legacy
turbines, grid-connected electrification, and offshore wind hub tie-in.
Source: Energy Solutions analysis using indicative CAPEX/OPEX ranges and 20-year asset life.
Economics & Abatement: LCOE, OPEX and USD/tCO₂
From an operator’s perspective, the key questions are: What is the internal rate of return (IRR) on
electrification investment, and what abatement cost (USD/tCO₂) does the project deliver relative to a
turbine-based baseline?
For a representative 50 MW power demand platform with a remaining life of 20 years and a load factor of 80%,
annual electricity demand sits around 350–380 GWh. Moving from on-platform turbines (with
total effective cost of 75–110 USD/MWh) to imported power at 60–95 USD/MWh
can unlock annual savings of 7–18 million USD, depending on gas value and carbon pricing.
Stylised Abatement Economics for a 50 MW Platform
| Parameter |
Turbine Baseline |
Electrified (Wind Hub Tie-in) |
Change |
| Annual Power Demand (GWh) |
360 |
360 |
0 |
| Emissions Intensity (kgCO₂e/boe, aggregated) |
0.45–0.70 |
0.10–0.25 |
-0.30–0.45 |
| Annual CO₂ Emissions (ktCO₂e) |
260–340 |
60–110 |
-180–260 |
| Annual Power Cost (million USD) |
28–40 |
22–34 |
-6–8 |
| Indicative Abatement Cost (USD/tCO₂) |
– |
40–110 |
Depends on CAPEX and carbon price |
Abatement cost ranges of 40–110 USD/tCO₂ place offshore electrification competitively
against many large-scale industrial decarbonization options, particularly where electrification can be
aligned with grid reinforcement or offshore wind build-out already underway.
Integration Architecture: Grid, Offshore Wind and Redundancy
Power-to-platform schemes can be configured in several architectures. The most common in 2026 are:
- Direct Grid Connection: A subsea cable connects the platform to a strong onshore
transmission node. The platform effectively becomes a large industrial customer with dedicated
connection assets and protection schemes.
- Offshore Wind Hub Connection: The platform connects to a nearby offshore wind
substation, sharing export cables and potentially offering flexible offtake to mitigate curtailment
during low onshore demand periods.
- Hybrid Schemes: Platforms may use a combination of imported power, battery systems (to
smooth short-term fluctuations) and existing turbines as backup generation.
Redundancy remains non-negotiable. Even in fully electrified configurations, operators keep a subset of
turbines or diesel generators available to support black-start, cable failure scenarios or onshore grid
contingencies. In practice, many “electrified” platforms operate in a hybrid mode for several years before
full reliance on imported power is acceptable to all stakeholders.
Share of Offshore Oil & Gas Production on Electrified Platforms
(Indicative)
The line chart below shows a stylised view of the share of offshore production from electrified
platforms in three regions under a moderate policy scenario.
Source: Energy Solutions scenario analysis, 2026 (illustrative adoption curves).
Case Studies: North Sea and Middle East Shallow-Water Platforms
Case Study 1 – North Sea Integrated Hub (50 MW Tie-in)
A mature North Sea integrated processing platform with an average power demand of 50 MW
and a remaining field life of 18 years evaluates electrification via a 132 kV subsea
cable connected to an onshore grid node 120 km away.
- Investment Scope: Single 132 kV cable system (plus spare fibre), onshore substation
upgrades, platform transformer modules and switchgear. Total CAPEX estimated at 320–380
million USD.
- Baseline: Three gas turbines with combined efficiency of 28%, annual fuel gas
consumption of roughly 320–360 GWh (equivalent), resulting in 280–320
ktCO₂e per year.
- Post-electrification: Imported power priced at 70–90 USD/MWh under
long-term contract, with residual emissions intensity driven by a moderately decarbonized onshore
grid.
Under a carbon price of 90 USD/tCO₂ and assuming mid-range power tariffs, Energy
Solutions modelling shows a project IRR of 11–14% and a simple payback period of
8–11 years. The project becomes significantly more attractive when the onshore grid mix
continues to decarbonize, further lowering residual emissions without additional offshore CAPEX.
Case Study 2 – Shallow-Water Platform Cluster (Offshore Wind Hub)
In a shallow-water basin in the Middle East, a cluster of three platforms (combined 60 MW demand)
connects to a 600 MW offshore wind hub via a shared 220 kV AC export system.
- Investment Scope: Incremental hub transformers, platform connection equipment and
cluster-level cable links, with incremental CAPEX of 180–260 million USD attributed
to the oil and gas cluster.
- Baseline: Multiple simple-cycle turbines and diesel backup units, with annual
emissions around 350–400 ktCO₂e.
- Outcomes: Annual emissions reduced by 65–75%, and operating fuel
costs fall by 40–55% relative to the baseline.
Co-optimizing the wind hub for both onshore demand and platform offtake allows higher capacity factors
and improves offshore wind economics by 5–10 USD/MWh, effectively sharing value between
the upstream operator and the power investor. The resulting abatement cost falls towards the lower end
of the 40–110 USD/tCO₂ range.
Supply Chain, Timeline and Execution Risks
The supply chain for subsea cable electrification overlaps with offshore wind and interconnector projects.
Key constraints in 2026 include:
- Cable manufacturing slots: High-voltage cable factories operate close to capacity in
many regions, with lead times of 24–36 months for large projects.
- Specialized vessels: Cable-laying and trenching vessels are shared across
interconnectors, wind farms and electrification projects, pushing installation windows into narrow
seasonal windows.
- Regulatory approvals: Cross-border cable routes require environmental permits and
coordination across multiple jurisdictions, adding 12–24 months to project schedules.
For upstream owners, this implies electrification must be planned early in field life extensions. Waiting
until fields are in their late tail-phase compresses the payback window and risks creating stranded cable
assets if production declines faster than expected.
Devil's Advocate: Stranded Assets, Curtailed Power and Regulatory Drag
Offshore electrification is not a one-way bet. Several material risks can erode value if not properly
structured.
- Field life uncertainty: If reservoir performance under-delivers, electrification CAPEX
may be amortized over fewer barrels, pushing effective abatement costs above 150–200
USD/tCO₂.
- Grid decarbonization pace: Connecting to a high-emissions grid can shift emissions from
Scope 1 to Scope 2 without achieving genuine decarbonization. Investors increasingly scrutinize full
lifecycle emissions, not just on-platform combustion.
- Cable failure and downtime: While rare, major cable faults can take months to diagnose
and repair. This may force operators back onto turbines, undermining emissions targets and complicating
reporting.
- Policy instability: Electrification often depends on carbon pricing, tax incentives or
regulatory obligations. Changes in policy design, such as cap adjustments or concession-specific rules,
can alter project economics mid-life.
- Lock-in risk: Investing heavily in electrification without parallel efforts on process
optimization, methane abatement and decommissioning preparation may inadvertently prolong high-emissions
assets rather than enabling an orderly transition.
A credible strategy treats electrification as part of a broader transformation of upstream portfolios,
linked to demand-side and midstream decarbonization, rather than as an isolated engineering project.
Outlook to 2030/2035: Carbon-Constrained Upstream Portfolios
By 2030, leading upstream companies are expected to electrify a significant share of their North Sea and
Norwegian Sea production volumes, with electrified platforms accounting for 35–55% of
regional offshore production. Other basins will lag due to weaker policy drivers and less supportive grid
infrastructure.
By 2035:
- Electrification will likely be standard for new large hubs within 150–200 km of strong
grids or major offshore wind clusters.
- Standalone turbine-based developments will face higher internal carbon pricing and elevated hurdle
rates, particularly in OECD markets.
- Investors will increasingly assess “carbon-adjusted breakeven” metrics, where electrification is a
prerequisite to keeping upstream assets investable within diversified portfolios.
Implementation Guide: Screening Checklist for Operators
For upstream asset teams and corporate strategy functions, the first question is not how to engineer the
cable, but whether a project belongs in the priority electrification pipeline at all. A structured screening
process can avoid misallocating capital.
- Resource and field life: Confirm remaining 2P reserves and production plateau duration.
Projects with >15 years of remaining economic life are stronger candidates.
- Distance and bathymetry: Evaluate route length, water depth and seabed conditions.
Segments beyond 200 km or in very deep water significantly increase CAPEX and risk.
- Grid carbon intensity: Estimate current and projected grid emissions (gCO₂/kWh).
Prioritize grids on a decarbonization pathway aligned with corporate targets.
- Policy environment: Map carbon pricing, emissions performance standards and any
electrification mandates across jurisdictions, as these shape both economics and social licence.
- Synergies with offshore wind: Identify existing or planned wind hubs. Cable-sharing or
hybrid hub designs can materially reduce per-MW connection costs.
- Stakeholder alignment: Ensure joint venture partners, regulators and communities share
a sufficiently long-term perspective to support the project.
Platforms that score highly across these criteria are strong candidates for more detailed techno-economic
assessments and front-end engineering design (FEED) work.
Methodology note: All cost and performance values in this article are stylised and
indicative, based on typical 2026 supply chain conditions, and should not be interpreted as binding offers
or project-specific estimates. Individual project economics can deviate materially due to local regulatory,
technical and contractual factors.