The Future of Gas Stations 2026: Transitioning to EV Charging Hubs

Executive Summary

Fuel retail is entering a structural transition: as battery-electric vehicles gain market share, traditional forecourts must evolve from fast-throughput, low-margin fuel pumps to multi-service EV charging hubs that monetise dwell time. The speed and shape of this transition vary by region, but operators that delay planning risk stranded assets and declining EBITDA. At Energy Solutions, we quantify the economics of retrofitting gas stations with fast chargers, the required grid upgrades, and the revenue mix needed to keep forecourts relevant.

Download Full EV Charging Hubs Report (PDF)

What You'll Learn

Technical Foundation: From Fuel Pumps to High-Power Chargers

Traditional gas stations are optimised for short dwell times and high vehicle throughput. Most sites draw modest electrical loads—lighting, pumps, HVAC, and small retail—typically below 100–300 kVA. Fast and ultrafast EV charging invert this logic: they demand very high peak power but can operate with moderate vehicle throughput if utilisation and tariffs are managed carefully.

Two main charging architectures dominate forecourt design:

For legacy sites, the key technical constraint is upstream capacity: existing utility connections may only support 200–400 kVA, far below the 1–3 MVA that a robust fast-charging hub might require. Solutions include new medium-voltage connections, on-site transformers, local storage, or hybrid systems that combine grid power with behind-the-meter batteries.

Benchmarks & Data: Power, CAPEX, and Utilisation

The economics of EV hubs are driven by three quantitative pillars: installed power and number of chargers, utilisation profiles over the day, and capital cost per installed kW and per bay. The following tables provide stylised 2026 benchmarks.

Indicative EV Charging Configurations for Existing Gas Stations (2026)

Configuration Chargers & Rating Installed Power (kW) Typical Grid Capacity Required (kVA)
Urban starter hub 4 x 150 kW DC 600 800–1,000
Urban flagship hub 6–8 x 150–200 kW (shared) 1,000–1,500 1,400–2,000
Highway corridor site 8–12 x 250–300 kW 2,000–3,000 2,500–3,500

Stylised CAPEX Benchmarks for EV Hub Retrofit (Per Site)

Component Urban Starter Urban Flagship Highway Corridor
DC chargers & cabinets 220,000–380,000 450,000–900,000 900,000–1,800,000
Transformers & grid connection 150,000–300,000 300,000–700,000 600,000–1,200,000
Civil works & canopies 80,000–200,000 150,000–350,000 250,000–500,000
Software, integration, design 60,000–150,000 100,000–250,000 150,000–300,000
Total CAPEX (indicative) 0.5–1.0 million 0.9–2.0 million 1.9–3.8 million

Ranges are indicative and exclude major site redevelopment or land acquisition.

Utilisation and Revenue Per Charger (Stylised 150–200 kW DC)

Metric Low Utilisation Base Case High Utilisation
Average utilisation (% of 24h) 4–6% 8–12% 15–20%
Energy dispensed (MWh/month) 4–7 8–13 15–22
Gross margin (USD/kWh) 0.10–0.18 0.12–0.20 0.10–0.18
Gross margin (USD/month) 400–1,200 1,000–2,600 1,800–4,000

Indicative CAPEX per Installed kW by Site Type

Source: Energy Solutions modeling for 2026 EV hub retrofits (indicative).

Annual Charger Revenue vs Utilisation

Source: Stylised 150–200 kW charger with blended retail tariffs.

EV Hub Abatement Cost vs Grid CO2 Intensity

Source: Energy Solutions abatement modeling vs ICE refuelling baseline.

Economics: TCO, Margins, and Abatement Cost

The EV hub business case combines infrastructure economics (CAPEX, connection charges, maintenance) with retail economics (charging tariffs, dwell-time spend, loyalty). Unlike conventional fuel, where gross margins often sit at 0.05–0.15 USD/litre, EV charging margins are typically framed per kWh and can be significantly higher on a relative basis—but they must cover higher fixed costs and lower asset utilisation in the early years.

For a flagship urban hub with 1–1.5 MW of installed DC capacity and total CAPEX of 1.1–1.7 million USD, annualised capital recovery at a 7–10% real WACC over 12–15 years implies capital charges of roughly 120,000–220,000 USD/year. Adding OPEX (network, software, maintenance, rent allocation) can bring fixed annual costs to 200,000–350,000 USD before energy purchase.

To break even, such a hub may need to dispense on the order of 800–1,600 MWh/year, depending on net margin per kWh. At 10–15% utilisation, this is achievable in demand-dense locations with a strong EV base, but challenging in underdeveloped markets.

Abatement Cost Perspective

For policy and ESG stakeholders, the question is how costly each tonne of CO2 avoided via EV hub deployment appears relative to continued ICE refuelling. Using stylised assumptions (EVs consuming 0.16–0.22 kWh/km, ICE cars consuming 6–8 litres/100 km, grid emissions in the 150–450 gCO2/kWh range), implied abatement costs for forecourt investments often fall between 40 and 140 USD/tCO2. Lower values are achieved where grids are relatively clean and where station CAPEX is amortised across high utilisation and strong retail cross-sales.

Case Studies: Urban Flagship Hub and Highway Corridor Site

Case Study 1 – Urban Flagship Hub in a High-EV Penetration City

A major fuel retailer converted a centrally located station into an EV-centric hub with six 200 kW chargers (1.2 MW total) and upgraded the on-site shop to emphasise foodservice and co-working.

Lessons included the importance of mobile app integration, reliable uptime (>98%), and clear pricing to avoid customer backlash. Under-investment in onsite amenities would likely have produced a weaker result.

Case Study 2 – Highway Corridor Site with Mixed Traffic

Along a major highway, a station operator deployed eight 250 kW chargers primarily targeting long-distance drivers and ride-hailing fleets.

The site illustrated that corridor hubs can be profitable but require closer coordination with route planners and fleet operators, as well as robust redundancy to avoid stranding drivers.

Infrastructure & Supply Chain: Grid, Hardware, and Software

The success of EV hubs rests on three pillars beyond the business model itself:

Supply chain constraints—particularly for power electronics and transformers—mean that operators must align rollout schedules with vendor capacity and utility planning cycles.

Devil's Advocate: Cannibalisation, Grid Constraints, and Timing Risk

A cautious view of the EV hub narrative raises several valid concerns:

These risks argue for staged investment, dynamic sizing, and flexible contracts with hardware and software partners, rather than large, one-off bets.

Outlook to 2030/2035: Role of Forecourts in the EV Era

By 2030–2035, the role of legacy gas stations will vary by region: in mature EV markets, many central urban sites may be fully electrified hubs with only limited liquid fuel presence, while rural and highway locations continue serving both ICE and EVs for longer.

The most resilient networks will likely share characteristics:

Implementation Guide: Site Segmentation and KPIs

For operators, the first step is rigorous segmentation of the existing network:

  1. Classify sites as core urban, suburban commute, highway corridor, or rural convenience.
  2. Assess grid and space constraints for each category, including potential for solar canopies or batteries.
  3. Model cross-selling uplift under different charging dwell-time scenarios.
  4. Prioritise a pilot portfolio of 5–20 sites to refine the concept before large-scale rollout.

KPIs to track include: kWh dispensed per site per day, charger utilisation%, average gross margin per kWh, incremental non-fuel revenue per charging session, and customer satisfaction / NPS scores.

Methodology note: All quantitative ranges in this article are stylised and indicative. They are based on public CPO and retailer data, Energy Solutions modeling assumptions, and typical grid tariff structures; they are not commercial offers.

FAQ: Questions from Retailers, Utilities, and Investors

How many fast chargers does a typical urban station actually need?

For most dense urban locations, 4–8 fast chargers in the 150–200 kW range are a pragmatic starting point. This provides enough capacity to serve early EV adoption while keeping grid upgrades and CAPEX manageable. Capacity can be expanded modularly as utilisation approaches 15–20% and local EV stock grows.

What payback period should operators target for EV hub retrofits?

Many investors look for simple paybacks in the 5–9 year range on incremental EV-related CAPEX, assuming reasonable utilisation growth. Shorter paybacks are achievable in high-demand nodes or when public funding supports grid or charger costs; longer paybacks may still be acceptable for strategic flagship sites.

How critical is non-charging revenue to the EV hub business case?

Non-charging revenue is often decisive. In many models, F&B, retail, and service revenues contribute 20–40% of total site EBITDA post-transition. Without a strong retail proposition, hubs may struggle to justify high upfront CAPEX, especially at moderate utilisation levels.

Should gas stations invest in batteries to reduce peak demand charges?

Behind-the-meter batteries can be attractive where demand charges or connection limits are stringent. However, they add complexity and CAPEX. They tend to be most compelling at sites with volatile high-power peaks, expensive grid capacity, and the ability to stack value streams (e.g., peak shaving, backup, tariff arbitrage).

How do EV charging hubs impact grid stability?

Concentrated fast charging can stress local distribution networks, especially if multiple hubs cluster on the same feeder. Smart charging, dynamic pricing, and coordination with distribution system operators are essential to avoid congestion and voltage issues. Over time, hubs can also provide flexibility services back to the grid.

What are common pitfalls when traditional fuel retailers move into EV charging?

Frequent pitfalls include underestimating project lead times (especially for grid upgrades), focusing solely on hardware rather than customer experience, neglecting software integration, and misaligning pricing with local competition. A phased, data-driven rollout with clear KPIs and cross-functional governance helps mitigate these risks.