Cargo_Type,Container_Class,Tare_Tonnes,Payload_Tonnes,Gross_Tonnes,Global_Fleet_Share_Pct,Lost_Slots_Count,Ocean_Normal_USD,Total_Door_Normal_USD,Ocean_Crisis_USD,Total_Door_Crisis_USD,Crisis_Jump_Pct,Crisis_USD_Per_Payload_Tonne,Technical_Notes "Solar PV Modules (280 kWp, Light/Volumetric)",40ft High-Cube Dry (COC),3.95,23.50,27.45,64.0,0,3200,4050,6150,7300,80.2,311,Baseline reference; cubes out before hitting 30.48t ISO MGM or highway weight limits GOES Steel & Copper Rod Coils (HS 7225 / 7408),20ft Heavy-Tested Dry (30.48t MGM),2.25,27.20,29.45,11.5,0,2550,4000,5350,7450,86.3,274,Weighs out at 25% cubic fill; requires heavy-tested floor & tri-axle overweight drayage 5 MWh Utility LFP BESS Unit (HS 8507.60 / UN 3536),20ft 45t Heavy-Tested SOC (Class 9 DG),4.40,36.60,41.00,0.0,1,5950,9750,11900,17100,75.4,467,"41.0t gross breaks 30.48t ISO standard; needs CSC 45t plate, Class 9 UN 3536, heavy-haul chassis" Central Inverter / MV Transformer Skid (HS 8504.40),40ft Collapsible Flat-Rack (OOG Over-Height/Width),5.40,34.00,39.40,1.8,3,10800,15000,22000,27900,86.0,821,Only ~1.8% of global box fleet; OOG protrusions trigger 3x lost-slot dead-space billing GIS Switchgear Bay / High-Voltage Busbar (HS 8537.20),40ft Open-Top (OOG Over-Height +25 cm),4.35,21.80,26.15,1.4,1,6600,8550,13300,16050,87.7,736,Single +25cm height overage consumes entire upper stack slot and adds 3-6 wk OT wait