  "dataset_title": "Long-Lead Energy Equipment Working Capital, Milestone Prepayments & Retention Benchmark (FY2023-Q1 2026)",
  "publisher": "Energy Solutions Intelligence",
  "article_id": "SC-443",
  "canonical_url": "https://energy-solutions.co/supply-chain/procurement-finance/working-capital-long-lead-equipment",
  "date_published": "2026-11-01",
  "data_cutoff_date": "2026-05-15",
  "coverage_period": "FY2023 to Q1 2026 (ended March 31, 2026)",
  "methodology_note": "Quantifies the working-capital mechanics of long-lead energy equipment (gas turbines, HVDC transformers, EHV cables, wind turbines, and turnkey EPC) across six global and MENA suppliers. Measures Customer Contract Liabilities relative to Equipment Backlog (RPO), Net Milestone Float (Equipment Contract Liabilities minus Equipment Contract Assets), Upstream Prepayment Pass-Through Ratios (Supplier Advances Paid / Customer Contract Liabilities), Supply-Chain Finance (SCF) utilization, and Asymmetric Retention Holdbacks.",
  "records": [
    {
      "record_id": "GEV-FY2025",
      "company_name": "GE Vernova Inc.",
      "ticker": "GEV",
      "headquarters_region": "North America (USA / Global)",
      "primary_segment": "Gas Turbines (83 GW Backlog+SRAs), Grid HVDC/Transformers & Wind",
      "accounting_standard": "US GAAP",
      "reporting_period": "FY2025",
      "period_end_date": "2025-12-31",
      "currency": "USD",
      "unit": "millions",
      "revenue_total": 38068.0,
      "equipment_backlog_rpo": 64245.0,
      "total_backlog_rpo": 150238.0,
      "contract_liabilities_current": 25774.0,
      "contract_liabilities_equipment_only": 23798.0,
      "contract_assets_current_total": 9294.0,
      "contract_assets_equipment_only": 3877.0,
      "inventories_net": 10429.0,
      "supplier_advances_paid_total": 2403.0,
      "supply_chain_finance_outstanding": 1542.0,
      "equipment_project_payables": 1210.0,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 8019.0,
      "benchmark_financing_rate_pct": 5.15,
      "data_status": "Observed (Audited US GAAP Form 10-K & Q1 2026 Form 10-Q Notes 4, 9, 12)",
      "source_citation": "GE Vernova FY2025 Form 10-K & Q1 2026 Form 10-Q (Notes 4, 9, 12, pp. 6-14)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000064/gev-20260331.htm",
      "net_milestone_float_equipment": 19921.0,
      "net_milestone_float_to_rev_pct": 52.3,
      "contract_liabilities_to_rev_pct": 67.7,
      "equipment_advances_to_eq_backlog_pct": 37.0,
      "upstream_pass_through_ratio_pct": 9.3,
      "net_prepayment_surplus_after_wip_inv_adv": 7089.0,
      "net_prepayment_surplus_to_rev_pct": 18.6,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    },
    {
      "record_id": "GEV-Q12026",
      "company_name": "GE Vernova Inc.",
      "ticker": "GEV",
      "headquarters_region": "North America (USA / Global)",
      "primary_segment": "Gas Turbines, Electrification (incl. Prolec GE) & Wind",
      "accounting_standard": "US GAAP",
      "reporting_period": "Q1 2026 (Ann. Rev / Mar 31, 2026 B/S)",
      "period_end_date": "2026-03-31",
      "currency": "USD",
      "unit": "millions",
      "revenue_total": 37356.0,
      "equipment_backlog_rpo": 75924.0,
      "total_backlog_rpo": 163276.0,
      "contract_liabilities_current": 31830.0,
      "contract_liabilities_equipment_only": 29913.0,
      "contract_assets_current_total": 9609.0,
      "contract_assets_equipment_only": 4225.0,
      "inventories_net": 11919.0,
      "supplier_advances_paid_total": 2495.0,
      "supply_chain_finance_outstanding": 1804.0,
      "equipment_project_payables": 1121.0,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 22296.0,
      "benchmark_financing_rate_pct": 5.15,
      "data_status": "Observed (Reviewed US GAAP Q1 2026 Form 10-Q Notes 4, 9, 12, 14)",
      "source_citation": "GE Vernova Q1 2026 Form 10-Q (Ended March 31, 2026, Notes 4, 9, 12, 14, pp. 6-15)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000064/gev-20260331.htm",
      "net_milestone_float_equipment": 25688.0,
      "net_milestone_float_to_rev_pct": 68.8,
      "contract_liabilities_to_rev_pct": 85.2,
      "equipment_advances_to_eq_backlog_pct": 39.4,
      "upstream_pass_through_ratio_pct": 7.8,
      "net_prepayment_surplus_after_wip_inv_adv": 11274.0,
      "net_prepayment_surplus_to_rev_pct": 30.2,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    },
    {
      "record_id": "SE-FY2024",
      "company_name": "Siemens Energy AG",
      "ticker": "ENR.DE",
      "headquarters_region": "Europe (Germany / Global)",
      "primary_segment": "Gas Services, Grid Technologies (HVDC/Transformers) & Siemens Gamesa",
      "accounting_standard": "IFRS",
      "reporting_period": "FY2024",
      "period_end_date": "2024-09-30",
      "currency": "EUR",
      "unit": "millions",
      "revenue_total": 34465.0,
      "equipment_backlog_rpo": 63960.0,
      "total_backlog_rpo": 123000.0,
      "contract_liabilities_current": 18867.0,
      "contract_liabilities_equipment_only": 18867.0,
      "contract_assets_current_total": 4190.0,
      "contract_assets_equipment_only": 4190.0,
      "inventories_net": 9792.0,
      "supplier_advances_paid_total": null,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 3216.0,
      "benchmark_financing_rate_pct": 5.0,
      "data_status": "Observed (Audited IFRS Annual Report 2025)",
      "source_citation": "Siemens Energy Annual Report 2025 & Q4 FY2025 Earnings Release (pp. 12-13)",
      "source_url": "https://assets.siemens-energy.com/dam/32b27e9a-af91-4915-8b51-b3af012d0d98/A-Siemens_Energy_Annual_Report_2025-pdf_Original%20file.pdf",
      "net_milestone_float_equipment": 14677.0,
      "net_milestone_float_to_rev_pct": 42.6,
      "contract_liabilities_to_rev_pct": 54.7,
      "equipment_advances_to_eq_backlog_pct": 29.5,
      "upstream_pass_through_ratio_pct": null,
      "net_prepayment_surplus_after_wip_inv_adv": 4885.0,
      "net_prepayment_surplus_to_rev_pct": 14.2,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    },
    {
      "record_id": "SE-FY2025",
      "company_name": "Siemens Energy AG",
      "ticker": "ENR.DE",
      "headquarters_region": "Europe (Germany / Global)",
      "primary_segment": "Gas Services, Grid Technologies (HVDC/Transformers) & Siemens Gamesa",
      "accounting_standard": "IFRS",
      "reporting_period": "FY2025",
      "period_end_date": "2025-09-30",
      "currency": "EUR",
      "unit": "millions",
      "revenue_total": 39077.0,
      "equipment_backlog_rpo": 74520.0,
      "total_backlog_rpo": 138000.0,
      "contract_liabilities_current": 22321.0,
      "contract_liabilities_equipment_only": 22321.0,
      "contract_assets_current_total": 4295.0,
      "contract_assets_equipment_only": 4295.0,
      "inventories_net": 10377.0,
      "supplier_advances_paid_total": null,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 3976.0,
      "benchmark_financing_rate_pct": 5.0,
      "data_status": "Observed (Audited IFRS Annual Report 2025)",
      "source_citation": "Siemens Energy Annual Report 2025 & Q4 FY2025 Earnings Release (pp. 12-13, 20)",
      "source_url": "https://assets.siemens-energy.com/dam/32b27e9a-af91-4915-8b51-b3af012d0d98/A-Siemens_Energy_Annual_Report_2025-pdf_Original%20file.pdf",
      "net_milestone_float_equipment": 18026.0,
      "net_milestone_float_to_rev_pct": 46.1,
      "contract_liabilities_to_rev_pct": 57.1,
      "equipment_advances_to_eq_backlog_pct": 30.0,
      "upstream_pass_through_ratio_pct": null,
      "net_prepayment_surplus_after_wip_inv_adv": 7649.0,
      "net_prepayment_surplus_to_rev_pct": 19.6,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    },
    {
      "record_id": "VWS-FY2025",
      "company_name": "Vestas Wind Systems A/S",
      "ticker": "VWS.CO",
      "headquarters_region": "Europe (Denmark / Global)",
      "primary_segment": "Onshore & Offshore Wind Turbines (Power Solutions) & Service",
      "accounting_standard": "IFRS",
      "reporting_period": "FY2025",
      "period_end_date": "2025-12-31",
      "currency": "EUR",
      "unit": "millions",
      "revenue_total": 18822.0,
      "equipment_backlog_rpo": 33200.0,
      "total_backlog_rpo": 71900.0,
      "contract_liabilities_current": 9270.0,
      "contract_liabilities_equipment_only": 9270.0,
      "contract_assets_current_total": 2747.0,
      "contract_assets_equipment_only": 2747.0,
      "inventories_net": 5721.0,
      "supplier_advances_paid_total": null,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 860.0,
      "benchmark_financing_rate_pct": 4.95,
      "data_status": "Observed (Audited IFRS Annual Report 2025 & Announcement 01/2026)",
      "source_citation": "Vestas Annual Report 2025 & Company Announcement No. 01/2026 (pp. 3-4)",
      "source_url": "https://www.vestas.com/content/dam/vestas-com/global/en/investor/reports-and-presentations/financial/2025/fy-2025/260205_01_Company_Announcement.pdf.coredownload.inline.pdf",
      "net_milestone_float_equipment": 6523.0,
      "net_milestone_float_to_rev_pct": 34.7,
      "contract_liabilities_to_rev_pct": 49.3,
      "equipment_advances_to_eq_backlog_pct": 27.9,
      "upstream_pass_through_ratio_pct": null,
      "net_prepayment_surplus_after_wip_inv_adv": 802.0,
      "net_prepayment_surplus_to_rev_pct": 4.3,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    },
    {
      "record_id": "OC-FY2024",
      "company_name": "Orascom Construction PLC",
      "ticker": "ORAS.CA / OC",
      "headquarters_region": "MENA & USA (UAE / Egypt Dual-Listed)",
      "primary_segment": "Turnkey Power, Grid, Renewable & Industrial EPC",
      "accounting_standard": "IFRS",
      "reporting_period": "FY2024",
      "period_end_date": "2024-12-31",
      "currency": "USD",
      "unit": "millions",
      "revenue_total": 3254.9,
      "equipment_backlog_rpo": 7590.9,
      "total_backlog_rpo": 7590.9,
      "contract_liabilities_current": 1428.8,
      "contract_liabilities_equipment_only": 1428.8,
      "contract_assets_current_total": 575.7,
      "contract_assets_equipment_only": 575.7,
      "inventories_net": 232.4,
      "supplier_advances_paid_total": 315.3,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": 249.8,
      "retentions_payable_subcontractors": 156.6,
      "annual_contract_liability_inflow_cash": 707.9,
      "benchmark_financing_rate_pct": 9.0,
      "data_status": "Observed (Audited IFRS Consolidated Financial Statements FY2025)",
      "source_citation": "Orascom Construction PLC Consolidated Financial Statements FY2025 (Page 12 & Notes 8, 9, 13, 19)",
      "source_url": "https://orascom.com/wp-content/uploads/Orascom-Construction-PLC-FS-31-Dec-2025English.pdf",
      "net_milestone_float_equipment": 853.1,
      "net_milestone_float_to_rev_pct": 26.2,
      "contract_liabilities_to_rev_pct": 43.9,
      "equipment_advances_to_eq_backlog_pct": 18.8,
      "upstream_pass_through_ratio_pct": 22.1,
      "net_prepayment_surplus_after_wip_inv_adv": 305.4,
      "net_prepayment_surplus_to_rev_pct": 9.4,
      "net_retention_lockup": 93.2,
      "retention_pass_through_coverage_pct": 62.7
    },
    {
      "record_id": "OC-FY2025",
      "company_name": "Orascom Construction PLC",
      "ticker": "ORAS.CA / OC",
      "headquarters_region": "MENA & USA (UAE / Egypt Dual-Listed)",
      "primary_segment": "Turnkey Power, Grid, Renewable & Industrial EPC",
      "accounting_standard": "IFRS",
      "reporting_period": "FY2025",
      "period_end_date": "2025-12-31",
      "currency": "USD",
      "unit": "millions",
      "revenue_total": 5049.8,
      "equipment_backlog_rpo": 9025.4,
      "total_backlog_rpo": 9025.4,
      "contract_liabilities_current": 1694.6,
      "contract_liabilities_equipment_only": 1694.6,
      "contract_assets_current_total": 807.8,
      "contract_assets_equipment_only": 807.8,
      "inventories_net": 275.4,
      "supplier_advances_paid_total": 591.3,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": 289.8,
      "retentions_payable_subcontractors": 175.9,
      "annual_contract_liability_inflow_cash": 187.2,
      "benchmark_financing_rate_pct": 9.0,
      "data_status": "Observed (Audited IFRS Consolidated Financial Statements FY2025)",
      "source_citation": "Orascom Construction PLC Consolidated Financial Statements FY2025 (Page 12 & Notes 8, 9, 13, 19)",
      "source_url": "https://orascom.com/wp-content/uploads/Orascom-Construction-PLC-FS-31-Dec-2025English.pdf",
      "net_milestone_float_equipment": 886.8,
      "net_milestone_float_to_rev_pct": 17.6,
      "contract_liabilities_to_rev_pct": 33.6,
      "equipment_advances_to_eq_backlog_pct": 18.8,
      "upstream_pass_through_ratio_pct": 34.9,
      "net_prepayment_surplus_after_wip_inv_adv": 20.1,
      "net_prepayment_surplus_to_rev_pct": 0.4,
      "net_retention_lockup": 113.9,
      "retention_pass_through_coverage_pct": 60.7
    },
    {
      "record_id": "EE-FY2025",
      "company_name": "Elsewedy Electric S.A.E.",
      "ticker": "SWDY.CA",
      "headquarters_region": "MENA (Egypt / GCC / Africa / Europe)",
      "primary_segment": "EHV/MV Cables, Power Transformers & Turnkey EPC",
      "accounting_standard": "EAS (IFRS-Aligned)",
      "reporting_period": "FY2025",
      "period_end_date": "2025-12-31",
      "currency": "EGP",
      "unit": "millions",
      "revenue_total": 281000.0,
      "equipment_backlog_rpo": null,
      "total_backlog_rpo": null,
      "contract_liabilities_current": 81266.2,
      "contract_liabilities_equipment_only": 81266.2,
      "contract_assets_current_total": 29894.6,
      "contract_assets_equipment_only": 29894.6,
      "inventories_net": 59860.0,
      "supplier_advances_paid_total": 23031.1,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": 8831.7,
      "retentions_payable_subcontractors": 3069.0,
      "annual_contract_liability_inflow_cash": null,
      "benchmark_financing_rate_pct": 20.32,
      "data_status": "Observed (Audited EAS/IFRS Comparative Notes 21, 25, 26, 31, 32, 33)",
      "source_citation": "Elsewedy Electric Q1 2026 & FY2025 Consolidated Financial Statements (Notes 21, 25, 26, 31-33)",
      "source_url": "https://irfiles.technologyverse.com/swdy2/EE-Consolidation-FS-31-3-26-EN.pdf",
      "net_milestone_float_equipment": 51371.6,
      "net_milestone_float_to_rev_pct": 18.3,
      "contract_liabilities_to_rev_pct": 28.9,
      "equipment_advances_to_eq_backlog_pct": null,
      "upstream_pass_through_ratio_pct": 28.3,
      "net_prepayment_surplus_after_wip_inv_adv": -31519.5,
      "net_prepayment_surplus_to_rev_pct": -11.2,
      "net_retention_lockup": 5762.7,
      "retention_pass_through_coverage_pct": 34.7
    },
    {
      "record_id": "EE-Q12026",
      "company_name": "Elsewedy Electric S.A.E.",
      "ticker": "SWDY.CA",
      "headquarters_region": "MENA (Egypt / GCC / Africa / Europe)",
      "primary_segment": "EHV/MV Cables, Power Transformers & Turnkey EPC",
      "accounting_standard": "EAS (IFRS-Aligned)",
      "reporting_period": "Q1 2026 (Ann. Rev / Mar 31, 2026 B/S)",
      "period_end_date": "2026-03-31",
      "currency": "EGP",
      "unit": "millions",
      "revenue_total": 301193.8,
      "equipment_backlog_rpo": null,
      "total_backlog_rpo": null,
      "contract_liabilities_current": 105095.7,
      "contract_liabilities_equipment_only": 105095.7,
      "contract_assets_current_total": 35427.0,
      "contract_assets_equipment_only": 35427.0,
      "inventories_net": 70771.8,
      "supplier_advances_paid_total": 34174.4,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": 9576.3,
      "retentions_payable_subcontractors": 3702.3,
      "annual_contract_liability_inflow_cash": 95318.0,
      "benchmark_financing_rate_pct": 20.32,
      "data_status": "Observed (Reviewed Interim EAS/IFRS Notes 21, 25, 26, 31, 32, 33)",
      "source_citation": "Elsewedy Electric Condensed Interim Consolidated Financial Statements for 3M Ended 31 March 2026",
      "source_url": "https://irfiles.technologyverse.com/swdy2/EE-Consolidation-FS-31-3-26-EN.pdf",
      "net_milestone_float_equipment": 69668.7,
      "net_milestone_float_to_rev_pct": 23.1,
      "contract_liabilities_to_rev_pct": 34.9,
      "equipment_advances_to_eq_backlog_pct": null,
      "upstream_pass_through_ratio_pct": 32.5,
      "net_prepayment_surplus_after_wip_inv_adv": -35277.5,
      "net_prepayment_surplus_to_rev_pct": -11.7,
      "net_retention_lockup": 5874.0,
      "retention_pass_through_coverage_pct": 38.7
    },
    {
      "record_id": "MB-FY2023",
      "company_name": "Meyer Burger Technology AG",
      "ticker": "MBTN.SW",
      "headquarters_region": "Europe & USA (Switzerland / Germany / Arizona)",
      "primary_segment": "Heterojunction Solar Cells & PV Modules (Distress Control Case)",
      "accounting_standard": "Swiss GAAP FER",
      "reporting_period": "FY2023",
      "period_end_date": "2023-12-31",
      "currency": "CHF",
      "unit": "millions",
      "revenue_total": 135.0,
      "equipment_backlog_rpo": null,
      "total_backlog_rpo": null,
      "contract_liabilities_current": 79.1,
      "contract_liabilities_equipment_only": 79.1,
      "contract_assets_current_total": 0.0,
      "contract_assets_equipment_only": 0.0,
      "inventories_net": 130.8,
      "supplier_advances_paid_total": 24.3,
      "supply_chain_finance_outstanding": null,
      "equipment_project_payables": null,
      "retentions_receivable_total": null,
      "retentions_payable_subcontractors": null,
      "annual_contract_liability_inflow_cash": 78.2,
      "benchmark_financing_rate_pct": 8.5,
      "data_status": "Observed (Audited Swiss GAAP FER Annual Report 2023)",
      "source_citation": "Meyer Burger Annual Report 2023 Financial Statements (pp. 104-116)",
      "source_url": "https://gb.meyerburger.com/fileadmin/user_upload/redakteure/gb2023/pdf/MB_AR2023_Financial-Statements.pdf",
      "net_milestone_float_equipment": 79.1,
      "net_milestone_float_to_rev_pct": 58.6,
      "contract_liabilities_to_rev_pct": 58.6,
      "equipment_advances_to_eq_backlog_pct": null,
      "upstream_pass_through_ratio_pct": 30.7,
      "net_prepayment_surplus_after_wip_inv_adv": -76.0,
      "net_prepayment_surplus_to_rev_pct": -56.3,
      "net_retention_lockup": null,
      "retention_pass_through_coverage_pct": null
    }
  ]
}