  "dataset_id": "SC-445-SUPPLIER-ORDERBOOK-REVENUE-RATIO",
  "title": "Orderbook vs. Revenue in Energy Equipment: Empirical RPO Decomposition & Factory Queue Dataset (2025-2026)",
  "publisher": "Energy Solutions Intelligence",
  "canonical_article_url": "https://energy-solutions.co/supply-chain/procurement-finance/supplier-orderbook-revenue-ratio",
  "section_hub_url": "https://energy-solutions.co/supply-chain/procurement-finance/",
  "date_published": "2026-11-01",
  "date_modified": "2026-11-01",
  "data_cutoff_date": "2026-10-30",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "methodology_formulas": {
    "raw_orderbook_to_revenue_ratio": "OBR_raw = B_total / R_annual",
    "normalized_equipment_backlog_coverage_ratio": "EBCR = [B_total * (1 - omega_service) * (1 - phi_unfirm) - B_JV_unconsolidated] / R_equip_annual",
    "twelve_month_conversion_coverage": "CBC_12m = (B_equip * v_12m_equip + B_service * v_12m_service) / R_annual",
    "physical_factory_queue_months": "T_queue_months = 12 * (B_equip_firm / ASP_backlog) / (Capacity_GW_yr * u_eff)",
    "deposit_backed_backlog_quality_ratio": "DBQR = Contract_Liabilities_Equipment / B_equip_firm"
  },
  "empirical_benchmarks": [
    {
      "record_type": "OEM_SEGMENT_RPO",
      "company": "GE Vernova Inc. (Consolidated)",
      "ticker": "GEV",
      "segment": "Total Group (Power, Electrification & Wind)",
      "accounting_standard": "US GAAP (ASC 606 RPO)",
      "reporting_period": "Q3 2026 (as of Sept 30, 2026)",
      "currency": "USD",
      "headline_backlog_m": 196721.0,
      "equipment_backlog_m": 104054.0,
      "service_backlog_m": 92667.0,
      "service_share_of_backlog_pct": 47.11,
      "annualized_total_revenue_m": 44112.0,
      "annualized_equipment_revenue_m": 26737.0,
      "annualized_service_revenue_m": 17375.0,
      "headline_backlog_to_rev_ratio_x": 4.46,
      "true_equipment_backlog_to_equip_rev_x": 3.89,
      "pct_equip_rpo_recognized_12m": 33.0,
      "pct_service_rpo_recognized_12m": 16.0,
      "contract_liabilities_m": 45669.0,
      "deposit_coverage_of_equip_rpo_pct": 42.05,
      "book_to_bill_ratio_x": 1.45,
      "primary_distortion_type": "Multi-Decade Service CSA Blending (47.1% Services with 15-Year Tail)",
      "key_audit_finding": "Total RPO of $196,721m splits into $104,054m Equipment RPO (33% recognized in 1 yr, 60% in 2 yrs, 97% in 5 yrs) and $92,667m Services RPO (only 16% recognized in 1 yr, 54% in 5 yrs, 78% in 10 yrs, 91% in 15 yrs). Backed by $45,669m current contract liabilities ($43,680m equipment/other + $1,990m CSA).",
      "primary_source_citation": "GE Vernova Q3 2026 Form 10-Q (Note 9 p. 14-15 & Note 24 p. 22-24, filed Oct 28, 2026)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000163/gev-20260930.htm"
    },
    {
      "record_type": "OEM_SEGMENT_RPO",
      "company": "GE Vernova — Power Segment",
      "ticker": "GEV-PWR",
      "segment": "Gas Power, Nuclear Power & Hydro Power",
      "accounting_standard": "US GAAP (ASC 606 RPO)",
      "reporting_period": "Q3 2026 (as of Sept 30, 2026)",
      "currency": "USD",
      "headline_backlog_m": 130854.0,
      "equipment_backlog_m": 54422.0,
      "service_backlog_m": 76431.0,
      "service_share_of_backlog_pct": 58.41,
      "annualized_total_revenue_m": 22021.0,
      "annualized_equipment_revenue_m": 8961.0,
      "annualized_service_revenue_m": 13061.0,
      "headline_backlog_to_rev_ratio_x": 5.94,
      "true_equipment_backlog_to_equip_rev_x": 6.07,
      "pct_equip_rpo_recognized_12m": 30.0,
      "pct_service_rpo_recognized_12m": 15.0,
      "contract_liabilities_m": 33163.0,
      "deposit_coverage_of_equip_rpo_pct": 57.28,
      "book_to_bill_ratio_x": 1.62,
      "primary_distortion_type": "CSA Service Dominance (58.4% Services) + Non-RPO Slot Reservation Agreements (SRAs)",
      "key_audit_finding": "Power RPO is 58.4% multi-year service agreements ($76,431m). However, Equipment RPO surged 186.8% YoY from $18,977m (Q3 2025) to $54,422m (Q3 2026) — equal to 6.07x annualized equipment revenue ($8,961m), backed by $31,173m in equipment contract liabilities. 9M 2026 gas turbine orders hit 36.7 GW (262 units) vs 12.8 GW shipped (86 units).",
      "primary_source_citation": "GE Vernova Q3 2026 Form 10-Q (Note 9 p. 14-15 & Item 2 MD&A Power Segment, filed Oct 28, 2026)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000163/gev-20260930.htm"
    },
    {
      "record_type": "OEM_SEGMENT_RPO",
      "company": "GE Vernova — Electrification Segment",
      "ticker": "GEV-ELEC",
      "segment": "Transformers (Prolec GE), HVDC, Switchgear & Grid Automation",
      "accounting_standard": "US GAAP (ASC 606 RPO)",
      "reporting_period": "Q3 2026 (as of Sept 30, 2026)",
      "currency": "USD",
      "headline_backlog_m": 46148.0,
      "equipment_backlog_m": 42204.0,
      "service_backlog_m": 3943.0,
      "service_share_of_backlog_pct": 8.54,
      "annualized_total_revenue_m": 13945.0,
      "annualized_equipment_revenue_m": 12011.0,
      "annualized_service_revenue_m": 1935.0,
      "headline_backlog_to_rev_ratio_x": 3.31,
      "true_equipment_backlog_to_equip_rev_x": 3.51,
      "pct_equip_rpo_recognized_12m": 35.0,
      "pct_service_rpo_recognized_12m": 25.0,
      "contract_liabilities_m": 9976.0,
      "deposit_coverage_of_equip_rpo_pct": 23.64,
      "book_to_bill_ratio_x": 1.54,
      "primary_distortion_type": "Pure Hardware Bottleneck (91.5% Equipment RPO = 3.51 Years Physical Queue)",
      "key_audit_finding": "Unlike Power or Wind, Electrification RPO ($46,148m) is 91.5% pure hardware equipment ($42,204m Equipment vs $3,943m Services). Thus its 3.31x headline ratio understates the true 3.51x hardware factory queue (42+ months for large power transformers and HVDC systems), with 19.1% Q3 2026 segment EBITDA margin.",
      "primary_source_citation": "GE Vernova Q3 2026 Form 10-Q (Note 9 & Segment Information, filed Oct 28, 2026)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000163/gev-20260930.htm"
    },
    {
      "record_type": "OEM_SEGMENT_RPO",
      "company": "GE Vernova — Wind Segment",
      "ticker": "GEV-WIND",
      "segment": "Onshore Wind & Offshore Wind Turbines",
      "accounting_standard": "US GAAP (ASC 606 RPO)",
      "reporting_period": "Q3 2026 (as of Sept 30, 2026)",
      "currency": "USD",
      "headline_backlog_m": 19952.0,
      "equipment_backlog_m": 7584.0,
      "service_backlog_m": 12368.0,
      "service_share_of_backlog_pct": 61.99,
      "annualized_total_revenue_m": 8267.0,
      "annualized_equipment_revenue_m": 5873.0,
      "annualized_service_revenue_m": 2393.0,
      "headline_backlog_to_rev_ratio_x": 2.41,
      "true_equipment_backlog_to_equip_rev_x": 1.29,
      "pct_equip_rpo_recognized_12m": 55.0,
      "pct_service_rpo_recognized_12m": 16.0,
      "contract_liabilities_m": 2529.0,
      "deposit_coverage_of_equip_rpo_pct": 33.35,
      "book_to_bill_ratio_x": 0.77,
      "primary_distortion_type": "Service Dilution + Onerous Offshore Margin Drag (-$585M 9M 2026 EBITDA Loss)",
      "key_audit_finding": "Headline Wind RPO of $19,952m (2.41x total segment revenue) hides that 62.0% ($12,368m) is long-term O&M service. True equipment RPO fell from $9,112m (Dec 2025) to $7,584m (Sept 2026) — only 1.29x annualized equipment revenue — while 9M 2026 Wind EBITDA was a loss of -$585m (-9.4% margin).",
      "primary_source_citation": "GE Vernova Q3 2026 Form 10-Q (Note 9 & Item 2 Wind Segment, filed Oct 28, 2026)",
      "source_url": "https://www.sec.gov/Archives/edgar/data/1996810/000199681026000163/gev-20260930.htm"
    },
    {
      "record_type": "OEM_EMPIRICAL",
      "company": "Vestas Wind Systems A/S",
      "ticker": "VWS.CO",
      "segment": "Power Solutions (Wind Turbines) & Service (11-Yr Avg Duration)",
      "accounting_standard": "IFRS (IFRS 15)",
      "reporting_period": "Q2 2026 (ended June 30, 2026) & FY2025 (ended Dec 31, 2025)",
      "currency": "EUR",
      "headline_backlog_m": 76900.0,
      "equipment_backlog_m": 36000.0,
      "service_backlog_m": 40900.0,
      "service_share_of_backlog_pct": 53.19,
      "annualized_total_revenue_m": 21000.0,
      "annualized_equipment_revenue_m": 17000.0,
      "annualized_service_revenue_m": 4000.0,
      "headline_backlog_to_rev_ratio_x": 3.66,
      "true_equipment_backlog_to_equip_rev_x": 2.12,
      "pct_equip_rpo_recognized_12m": 47.0,
      "pct_service_rpo_recognized_12m": 9.1,
      "contract_liabilities_m": null,
      "deposit_coverage_of_equip_rpo_pct": null,
      "book_to_bill_ratio_x": 1.15,
      "primary_distortion_type": "11-Year Average Service Backlog Duration Inflating Headline Ratio by +72.6%",
      "key_audit_finding": "At June 30, 2026, Vestas reported EUR 76.9bn combined backlog (3.66x 2026E revenue midpoint of EUR 21.0bn; up from EUR 71.9bn in FY25). However, EUR 40.9bn (53.2%) is Service agreements with an average duration of 11 years (up to 30+ years). Turbine equipment backlog is EUR 36.0bn (2.12x equipment revenue).",
      "primary_source_citation": "Vestas Q2 2026 Interim Report (Aug 12, 2026), Q1 2026 Interim Report (May 6, 2026) & FY2025 Annual Report",
      "source_url": "https://www.vestas.com/en/media/company-news/2026/vestas---interim-report--first-quarter-2026-c4344988"
    },
    {
      "record_type": "OEM_EMPIRICAL",
      "company": "Siemens Energy AG",
      "ticker": "ENR.DE",
      "segment": "Gas Services, Grid Technologies, Transformation of Industry & Siemens Gamesa",
      "accounting_standard": "IFRS (IFRS 15)",
      "reporting_period": "Q3 FY2026 (ended June 30, 2026)",
      "currency": "EUR",
      "headline_backlog_m": 162000.0,
      "equipment_backlog_m": 87480.0,
      "service_backlog_m": 74520.0,
      "service_share_of_backlog_pct": 46.0,
      "annualized_total_revenue_m": 45600.0,
      "annualized_equipment_revenue_m": 29640.0,
      "annualized_service_revenue_m": 15960.0,
      "headline_backlog_to_rev_ratio_x": 3.55,
      "true_equipment_backlog_to_equip_rev_x": 2.95,
      "pct_equip_rpo_recognized_12m": 34.0,
      "pct_service_rpo_recognized_12m": 15.0,
      "contract_liabilities_m": null,
      "deposit_coverage_of_equip_rpo_pct": null,
      "book_to_bill_ratio_x": 1.57,
      "primary_distortion_type": "Segment Book-to-Bill Divergence (Gas Services 2.65x vs. Multi-Year HVDC Grid Queue)",
      "key_audit_finding": "Order backlog hit a record EUR 162bn (~$186bn) in Q3 FY2026 on quarterly orders of EUR 17.9bn vs revenue of EUR 11.4bn (1.57x group book-to-bill; 2.65x book-to-bill in Gas Services). Free cash flow before tax surged to EUR 2.3bn in Q3 FY26 on customer advance payments tied to new orders.",
      "primary_source_citation": "Siemens Energy Q3 FY2026 Earnings Release (Aug 5, 2026) & FY2025 Annual Report",
      "source_url": "https://www.siemens-energy.com/global/en/home/press-releases/earnings-release-q3-fy-2026.html"
    },
    {
      "record_type": "OEM_EMPIRICAL",
      "company": "First Solar, Inc.",
      "ticker": "FSLR",
      "segment": "Thin-Film CdTe Utility-Scale Solar Modules (Series 6 & Series 7 CuRe)",
      "accounting_standard": "US GAAP (ASC 606)",
      "reporting_period": "Q3 2026 (as of Sept 30, 2026, reported Oct 29, 2026)",
      "currency": "USD",
      "headline_backlog_m": 13500.0,
      "equipment_backlog_m": 13500.0,
      "service_backlog_m": 0.0,
      "service_share_of_backlog_pct": 0.0,
      "annualized_total_revenue_m": 4750.0,
      "annualized_equipment_revenue_m": 4750.0,
      "annualized_service_revenue_m": 0.0,
      "headline_backlog_to_rev_ratio_x": 2.84,
      "true_equipment_backlog_to_equip_rev_x": 2.67,
      "pct_equip_rpo_recognized_12m": 37.5,
      "pct_service_rpo_recognized_12m": 0.0,
      "contract_liabilities_m": null,
      "deposit_coverage_of_equip_rpo_pct": null,
      "book_to_bill_ratio_x": 0.62,
      "primary_distortion_type": "Geographic ASP Dispersion ($0.36/W U.S. vs $0.20/W India) & De-Booking Attrition (50.1 GW -> 44.0 GW)",
      "key_audit_finding": "Contracted backlog of 44.0 GW ($13.5bn, ~$0.307/W blended ASP) at Sept 30, 2026 is 100% equipment, down from 50.1 GW at Dec 31, 2025 due to shipments (11.7 GW in 9M 26) and contract terminations. U.S. bookings average ~$0.36/W while India bookings average ~$0.20/W (+80% more physical GW per dollar in India); 2026 revenue guidance cut to $4.6-$4.9bn (16-17 GW vs 22.1 GW nameplate capacity).",
      "primary_source_citation": "First Solar Q3 2026 Financial Results (Oct 29, 2026) & Q2 2026 Form 8-K / 10-Q (July 30, 2026)",
      "source_url": "https://www.pv-tech.org/first-solar-sales-down-23-year-on-year-cuts-full-year-revenue-guidance/"
    },
    {
      "record_type": "OEM_EMPIRICAL",
      "company": "Fluence Energy, Inc.",
      "ticker": "FLNC",
      "segment": "Utility-Scale Battery Energy Storage Systems (BESS) & Services/Digital",
      "accounting_standard": "US GAAP (ASC 606 RPO)",
      "reporting_period": "Q3 FY2026 (9M ended June 30, 2026, filed Aug 5, 2026)",
      "currency": "USD",
      "headline_backlog_m": 6400.0,
      "equipment_backlog_m": 5632.0,
      "service_backlog_m": 768.0,
      "service_share_of_backlog_pct": 12.0,
      "annualized_total_revenue_m": 2120.0,
      "annualized_equipment_revenue_m": 1990.0,
      "annualized_service_revenue_m": 130.0,
      "headline_backlog_to_rev_ratio_x": 3.02,
      "true_equipment_backlog_to_equip_rev_x": 2.83,
      "pct_equip_rpo_recognized_12m": 50.5,
      "pct_service_rpo_recognized_12m": 20.0,
      "contract_liabilities_m": 956.5,
      "deposit_coverage_of_equip_rpo_pct": 16.98,
      "book_to_bill_ratio_x": 1.48,
      "primary_distortion_type": "High Backlog Ratio Masking Margin Compression (6.47% 9M Gross Margin & -$98.8M Net Loss)",
      "key_audit_finding": "Remaining performance obligations reached $6.4bn at June 30, 2026 (48%-53% recognized within 12 months) with $956.5m in deferred revenue. Yet 9M FY2026 revenue of $1.59bn generated only $102.9m gross profit (6.47% gross margin), a -$98.8m net loss, and -$366.5m operating cash flow — proving record RPO ratios do not guarantee embedded profitability.",
      "primary_source_citation": "Fluence Energy Q3 FY2026 Form 10-Q (ended June 30, 2026, filed Aug 5, 2026)",
      "source_url": "https://www.stocktitan.net/sec-filings/FLNC/10-q-fluence-energy-inc-quarterly-earnings-report-7170b2a96086.html"
    },
    {
      "record_type": "OEM_EMPIRICAL",
      "company": "Nextpower Inc. (formerly Nextracker Inc.)",
      "ticker": "NXT",
      "segment": "Solar Trackers, Foundations, eBOS & TrueCapture Software",
      "accounting_standard": "US GAAP (ASC 606)",
      "reporting_period": "FY2026 (ended March 31, 2026) & Q2 FY2027 (reported Oct 29, 2026)",
      "currency": "USD",
      "headline_backlog_m": 5250.0,
      "equipment_backlog_m": 5092.5,
      "service_backlog_m": 157.5,
      "service_share_of_backlog_pct": 3.0,
      "annualized_total_revenue_m": 3559.4,
      "annualized_equipment_revenue_m": 3452.6,
      "annualized_service_revenue_m": 106.8,
      "headline_backlog_to_rev_ratio_x": 1.47,
      "true_equipment_backlog_to_equip_rev_x": 1.47,
      "pct_equip_rpo_recognized_12m": 72.0,
      "pct_service_rpo_recognized_12m": 35.0,
      "contract_liabilities_m": 312.4,
      "deposit_coverage_of_equip_rpo_pct": 6.13,
      "book_to_bill_ratio_x": 1.12,
      "primary_distortion_type": "Clean Pure-Equipment Benchmark (Low 1.47x Ratio Reflects High 80 GW/Yr Partner Throughput, Not Weak Demand)",
      "key_audit_finding": "Backlog exceeded $5.25bn at FY26 year-end (and >$6.0bn by Q2 FY27 on $1.11bn quarterly revenue) with 32.6% GAAP gross margin. Because Nextpower scales across 100+ partner factories (~1,500 MW/week capacity), its 1.47x backlog-to-revenue ratio reflects fast factory throughput rather than weak orders.",
      "primary_source_citation": "Nextpower FY2026 Form 10-K & Q4 FY26 Release (May 12, 2026) & Q2 FY27 Release (Oct 29, 2026)",
      "source_url": "https://nextpower.com/post/press-release/nextpower-reports-q4-and-fiscal-year-2026-financial-results"
    },
    {
      "record_type": "EPC_MENA_EMPIRICAL",
      "company": "Orascom Construction PLC",
      "ticker": "ORAS",
      "segment": "MENA, Europe & U.S. Power, Water, Data Center & Industrial Turnkey EPC",
      "accounting_standard": "IFRS (IFRS 15 / IAS 28 Equity Method)",
      "reporting_period": "H1 2026 (as of June 30, 2026, published Aug 14, 2026) & FY2025",
      "currency": "USD",
      "headline_backlog_m": 14500.0,
      "equipment_backlog_m": 10879.0,
      "service_backlog_m": 3621.0,
      "service_share_of_backlog_pct": 24.97,
      "annualized_total_revenue_m": 4987.2,
      "annualized_equipment_revenue_m": 4987.2,
      "annualized_service_revenue_m": 0.0,
      "headline_backlog_to_rev_ratio_x": 2.91,
      "true_equipment_backlog_to_equip_rev_x": 2.18,
      "pct_equip_rpo_recognized_12m": 45.0,
      "pct_service_rpo_recognized_12m": 0.0,
      "contract_liabilities_m": null,
      "deposit_coverage_of_equip_rpo_pct": null,
      "book_to_bill_ratio_x": 1.38,
      "primary_distortion_type": "Pro-Forma Equity-Method JV Backlog Mismatch (+33.5% Overstatement if Divided by Consolidated Revenue)",
      "key_audit_finding": "At June 30, 2026, Orascom reported Consolidated Backlog of $10,879.0m ($10.9bn) and Pro Forma Backlog of $14.5bn including its 50% share in BESIX ($3.6bn). Because BESIX is accounted for under the equity method (carrying value $451.2m), consolidated IFRS revenue ($4,987.2m in FY25) excludes BESIX sales — making 2.18x (not 2.91x) the true consolidated ratio.",
      "primary_source_citation": "Orascom Construction H1 2026 Earnings Release (Aug 14, 2026) & FY2025 Financial Statements",
      "source_url": "https://orascom.com/updates/orascom-construction-reports-backlog-of-usd-10-9-billion-and-ebitda-of-usd-92-6-million-in-q2-2026-bringing-ebitda-to-usd-200-9-million-in-h1-2026/"
    },
    {
      "record_type": "EPC_MENA_EMPIRICAL",
      "company": "Elsewedy Electric S.A.E.",
      "ticker": "SWDY.CA",
      "segment": "Wires & Cables (52% Rev), Turnkey E&C Projects (33% Rev), Transformers & Meters",
      "accounting_standard": "EAS / IFRS",
      "reporting_period": "FY2025 & Q1/H1 2026 (published March–August 2026)",
      "currency": "EGP",
      "headline_backlog_m": 312000.0,
      "equipment_backlog_m": 50600.0,
      "service_backlog_m": 261400.0,
      "service_share_of_backlog_pct": 83.78,
      "annualized_total_revenue_m": 261648.0,
      "annualized_equipment_revenue_m": 146520.0,
      "annualized_service_revenue_m": 115128.0,
      "headline_backlog_to_rev_ratio_x": 1.19,
      "true_equipment_backlog_to_equip_rev_x": 0.35,
      "pct_equip_rpo_recognized_12m": 95.0,
      "pct_service_rpo_recognized_12m": 38.0,
      "contract_liabilities_m": null,
      "deposit_coverage_of_equip_rpo_pct": null,
      "book_to_bill_ratio_x": 1.24,
      "primary_distortion_type": "Blended Fast-Turn Commodity Cables (0.29x–0.35x) vs. Multi-Year Turnkey EPC Backlog (2.3x–2.8x)",
      "key_audit_finding": "Group backlog of ~$6.5bn (~EGP 312bn) blends fast-turn Wires & Cables backlog (EGP 42.4bn vs EGP 42.6bn Q4 2025 single-quarter segment revenue = ~3 months coverage, heavily indexed to LME copper and EGP/USD FX) with multi-year Turnkey E&C backlog (~EGP 238bn+ across 24-48 month projects) and Smart Meters backlog (EGP 8.2bn).",
      "primary_source_citation": "Elsewedy Electric Q4 2025 Earnings Release (March 15, 2026) & Q1 2026 Consolidated FS",
      "source_url": "https://irfiles.technologyverse.com/swdy2/Elsewedy-Electric-ER-4Q2025-E-.pdf"
    }
  ]
}