insurance_or_loss_layer,governing_standard_or_clause,what_it_covers,key_trigger_or_exclusion,typical_2026_market_friction,required_project_control Marine Cargo All-Risks,Institute Cargo Clauses (ICC A),"Physical loss or damage to equipment in ocean, air, and inland transit","Excludes pure delay, improper packing, and unapproved heavy-lift operations",Tightening scrutiny on unverified shock packing & Red Sea war risk,Owner-controlled policy (avoid supplier CIF) + shock/tilt logs Marine Delay in Start-Up (DSU / ALOP),Project Cargo DSU Endorsement,"Lost gross profit, debt service & fixed costs from COD delay",Strictly requires underlying indemnifiable physical cargo loss (zero payout for pure congestion),30-90 day waiting periods; underwriters resist >18-24 mo caps vs 36 mo LPT waits,Stress-test indemnity period against live OEM transformer/turbine queues Increased Cost of Working (ICOW),DSU Mitigation Extension,"Emergency airfreight, factory overtime, temporary substations",Capped at 'economic limit' (spend must be less than DSU loss saved),Requires rapid underwriter pre-approval before chartering AN-124 / 747-8F,Pre-agree ICOW escalation triggers & emergency broker protocol Marine Warranty Survey (MWS),DNV-ST-N001 (Marine Operations),"Independent engineering review of vessels, lifts, sea-fastening & loadouts",Strict policy warranty: missing Certificate of Approval (CoA) voids cover,Shortage of experienced heavy-lift MWS engineers during wind/LNG peaks,Appoint MWS 90-180 days before sail-away; build CoA into EPC milestones Marine / EAR 50-50 Bridge,50/50 Concealed Damage Clause,Damage found post-arrival when transit vs. site-handling timing is unproven,Requires identical 50/50 wording on BOTH Marine Cargo and Site EAR policies,Split underwriters across Marine and EAR balk without mirrored text,"Place Marine Cargo, DSU, and Site EAR with coordinated lead market"