  "publisher": "Energy Solutions Intelligence",
  "sourceArticle": "https://energy-solutions.co/supply-chain/mena-africa/saudi-grid-manufacturing-localisation",
  "generatedFrom": "Published article tables",
  "dateModified": "2026-11-15",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "tables": [
    {
      "tableNumber": 1,
      "title": "Table 1: Master Plant-by-Plant Audit — Comparing Operational vs. Announced Grid Equipment Factories in Saudi Arabia (As of Nov 2026)",
      "columns": [
        "Company / Industrial Entity",
        "City / Cluster",
        "Core Grid Product Scope",
        "2025–2026 Operational Capacity & Revenue",
        "Announced / Under-Construction Expansion (2026–2030f)",
        "Voltage Ceiling (Now → 2028)",
        "Est. Net Local VA",
        "Execution Status"
      ],
      "rows": [
        {
          "Company / Industrial Entity": "Electrical Industries Co. (EIC — STC & WESCOSA)",
          "City / Cluster": "Dammam (1st & 2nd Ind. Cities)",
          "Core Grid Product Scope": "Distribution & Medium Power Transformers, MV/LV Switchgear, Cable Trays",
          "2025–2026 Operational Capacity & Revenue": "Expanded +70% in H2 2024; ~50% KSA dist. transformer share; FY25 Rev: SAR 2,296M ($612.3M) (Transformers: SAR 1,811M; Switchgear: SAR 280M).",
          "Announced / Under-Construction Expansion (2026–2030f)": "Scaling sales to 25,532 transformers/yr & 30,639 switchgears/yr by 2030f (projected revenue SAR 3,528M).",
          "Voltage Ceiling (Now → 2028)": "132 kV / 100 MVA → 132 kV",
          "Est. Net Local VA": "52%–64%",
          "Execution Status": "Operational (+70% Live)"
        },
        {
          "Company / Industrial Entity": "Saudi Power Transformers Co. (SPTC — EIC 100% Unit)",
          "City / Cluster": "Dammam (2nd Ind. City)",
          "Core Grid Product Scope": "HV & Extra-High-Voltage (EHV) Power Transformers & Shunt Reactors",
          "2025–2026 Operational Capacity & Revenue": "5,000+ MVA/yr (~150 HV units/yr up to 150 MVA / 245 kV); SEC framework supplier.",
          "Announced / Under-Construction Expansion (2026–2030f)": "SAR 192M ($51.2M) expansion for 380 kV EHV transformers & reactors (COD 2027f); backed by SAR 1,411M ($376.3M) 84-month SEC contract.",
          "Voltage Ceiling (Now → 2028)": "245 kV / 150 MVA → 380 kV EHV",
          "Est. Net Local VA": "42%–55%",
          "Execution Status": "380 kV Line COD 2027f"
        },
        {
          "Company / Industrial Entity": "Riyadh Cables Group Co. (RCGC)",
          "City / Cluster": "Riyadh (1.5M+ m² Complex)",
          "Core Grid Product Scope": "LV, MV, HV & EHV XLPE Power Cables, OHL Conductors, Fiber Optic",
          "2025–2026 Operational Capacity & Revenue": "220,000 tons/yr KSA capacity (+55 kt UAE/Iraq); 271 kt sold in FY25 (97% utilization) ; FY25 Rev: SAR 10,674M ($2.85B) ; 38% KSA share.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Adding 6%–7% capacity/yr through 2027f (SAR 255M annual capex) to reach 333,000 tons/yr sales by 2030f; SAR 5.1B (163 kt) backlog.",
          "Voltage Ceiling (Now → 2028)": "380 kV (420 kV AC) → 420 kV AC",
          "Est. Net Local VA": "32%–42%",
          "Execution Status": "Operational + 6–7%/yr Ramp"
        },
        {
          "Company / Industrial Entity": "Al-Babtain Power & Telecommunication Co.",
          "City / Cluster": "Riyadh & Dammam",
          "Core Grid Product Scope": "EHV/HV Lattice Transmission Towers, Monopoles, Poles & Solar PV Structures",
          "2025–2026 Operational Capacity & Revenue": "220,000 tons/yr tower capacity (expanded +50,000 t in Apr 2025) + 1.2 GW/yr PV steel; 60%–70% KSA tower share; FY25 Rev: SAR 2,857M ($761.9M) .",
          "Announced / Under-Construction Expansion (2026–2030f)": "Executing SAR 3.5B tower backlog + SAR 1.8B new contracts (Hyundai E&C, L&T, SSEM) for 380 kV AC and ±500 kV HVDC corridors.",
          "Voltage Ceiling (Now → 2028)": "380 kV / ±500 kV Towers → 800 kV",
          "Est. Net Local VA": "68%–78%",
          "Execution Status": "Operational (Apr 25 Exp. Live)"
        },
        {
          "Company / Industrial Entity": "Alfanar Electric",
          "City / Cluster": "Riyadh (Alfanar Ind. City)",
          "Core Grid Product Scope": "LV/MV/HV Switchgear, RMUs, Distribution Transformers & HVDC Control Systems",
          "2025–2026 Operational Capacity & Revenue": "Major domestic LV/MV switchgear, RMU (up to 36 kV), distribution transformer, and protection relay panel manufacturer.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Inaugurated SAR 375M ($100M) Riyadh HVDC & High-Voltage Electrical Systems Factory in January 2026 for digital substations & HVDC.",
          "Voltage Ceiling (Now → 2028)": "36–132 kV → 380 kV / HVDC Panels",
          "Est. Net Local VA": "45%–60%",
          "Execution Status": "HVDC Plant Opened Jan 2026"
        },
        {
          "Company / Industrial Entity": "Hitachi Energy Saudi Arabia",
          "City / Cluster": "Dammam & Riyadh",
          "Core Grid Product Scope": "High-Voltage Gas-Insulated Switchgear (GIS up to 380 kV), Protection & Power Quality",
          "2025–2026 Operational Capacity & Revenue": "Assembles 132 kV–380 kV GIS bays , capacitor banks, and SAS/protection panels at Dammam factory; EHV transformers imported from Vaasa.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Signed Feb 2025 MoU with SEC to localize EconiQ SF 6 -free HV switchgear and expand Dammam engineering/service center.",
          "Voltage Ceiling (Now → 2028)": "380 kV GIS → 420 kV SF 6 -Free GIS",
          "Est. Net Local VA": "35%–48%",
          "Execution Status": "Operational + SF 6 -Free Ramp"
        },
        {
          "Company / Industrial Entity": "Siemens Energy Dammam Energy Hub",
          "City / Cluster": "Dammam (2nd Ind. City)",
          "Core Grid Product Scope": "HV/MV Switchgear, SF 6 -Free Blue GIS, Grid Automation & Gas Turbines",
          "2025–2026 Operational Capacity & Revenue": "Assembles HV/MV switchgear, protection panels & turbines; deployed KSA’s 1st SF 6 -free Blue GIS in Jeddah (July 2025) with Elsewedy PSP.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Expanding Dammam Hub under $1.6B Rumah 2 & Nairyah 2 contract (Mar 2025) and NEOM/Red Sea Blue GIS & digital twin orders.",
          "Voltage Ceiling (Now → 2028)": "132–380 kV GIS → 420 kV Blue GIS",
          "Est. Net Local VA": "35%–45%",
          "Execution Status": "Operational + Hub Expansion"
        },
        {
          "Company / Industrial Entity": "Schneider Electric Saudi Arabia",
          "City / Cluster": "Riyadh & Dammam (3 Plants)",
          "Core Grid Product Scope": "MV Vacuum Circuit Breakers (HVX/EVO Pact), RMUs, LV Switchgear & Automation",
          "2025–2026 Operational Capacity & Revenue": "35,000+ m² across 3 plants (~11–12 lines) producing Made in KSA MV vacuum breakers, LV/MV panels, and data-center distribution skids.",
          "Announced / Under-Construction Expansion (2026–2030f)": "May 2026 commitment to nearly triple Saudi manufacturing capacity to 32 production lines by 2030 .",
          "Voltage Ceiling (Now → 2028)": "Up to 36 kV → 36–40.5 kV AirSeT",
          "Est. Net Local VA": "50%–62%",
          "Execution Status": "Tripling to 32 Lines by 2030"
        },
        {
          "Company / Industrial Entity": "GE Vernova — GESAT Facility",
          "City / Cluster": "Dammam",
          "Core Grid Product Scope": "High-Voltage Gas-Insulated Switchgear (GIS) & H-Class Gas Turbines",
          "2025–2026 Operational Capacity & Revenue": "~850 KSA staff; turbine manufacturing, grid automation, and service center; supplied GIS for NEOM Green Hydrogen (from global/regional plants).",
          "Announced / Under-Construction Expansion (2026–2030f)": "February 2025 investment commitment to expand GESAT Dammam facility for local manufacturing of high-voltage GIS .",
          "Voltage Ceiling (Now → 2028)": "132 kV Skids → 132–380 kV HV GIS",
          "Est. Net Local VA": "32%–45%",
          "Execution Status": "HV GIS Expansion (2026–27f)"
        },
        {
          "Company / Industrial Entity": "Bawan Co. — UTEC & USSG",
          "City / Cluster": "Riyadh",
          "Core Grid Product Scope": "Distribution & HV Power Transformers, Package Substations & MV/LV Switchgear",
          "2025–2026 Operational Capacity & Revenue": "90%-owned by Bawan; SAR 533.8M (9M) revenue in distribution transformers, unit substations, and MV/LV switchgear.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Constructing new High-Voltage Transformer Plant (COD 2027f) + Aug 2026 USSG MoU to manufacture Data Center substations.",
          "Voltage Ceiling (Now → 2028)": "36 kV / 25 MVA → 132 kV+ HV Trafos",
          "Est. Net Local VA": "48%–58%",
          "Execution Status": "HV Plant Under Construction (2027f)"
        },
        {
          "Company / Industrial Entity": "Bahra Electric (Bahra Cables)",
          "City / Cluster": "Bahra / Rabigh (Jeddah)",
          "Core Grid Product Scope": "LV, MV & HV Power Cables, Copper/Aluminum Rod, Conduits & Busbars",
          "2025–2026 Operational Capacity & Revenue": "~120,000+ tons/yr estimated conductor capacity supplying SEC, Aramco, and Western Region giga-projects (Red Sea, Amaala, Jeddah).",
          "Announced / Under-Construction Expansion (2026–2030f)": "Expanding HV/EHV XLPE extrusion and fire-resistant LSHF cable lines for urban metro and data-center projects.",
          "Voltage Ceiling (Now → 2028)": "132–220 kV → 380 kV AC",
          "Est. Net Local VA": "35%–44%",
          "Execution Status": "Operational"
        },
        {
          "Company / Industrial Entity": "Jeddah Cables (Energya KSA) & El Sewedy Cables KSA",
          "City / Cluster": "Jeddah & Yanbu / Riyadh",
          "Core Grid Product Scope": "LV, MV, HV & EHV Power Cables and Overhead Transmission Conductors",
          "2025–2026 Operational Capacity & Revenue": "Combined ~110,000+ tons/yr of LV/MV/HV cables and ACSR/AAAC overhead transmission conductors.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Debottlenecking EHV testing and stranding capacity for SEC’s 160,000 c.km transmission target.",
          "Voltage Ceiling (Now → 2028)": "Up to 380 kV AC → 380 kV AC",
          "Est. Net Local VA": "34%–42%",
          "Execution Status": "Operational"
        },
        {
          "Company / Industrial Entity": "ABB Arabia & Lucy Electric Saudi Arabia",
          "City / Cluster": "Dammam & Al Khobar",
          "Core Grid Product Scope": "MV AIS/GIS Switchgear, Ring Main Units (Sabre / Aegis Plus 12–36 kV)",
          "2025–2026 Operational Capacity & Revenue": "Dedicated Dammam MV switchgear lines (ABB) and Al Khobar RMU plant (Lucy Electric) supplying SEC distribution automation.",
          "Announced / Under-Construction Expansion (2026–2030f)": "Integrating Nuventura 24–36 kV dry-air SF 6 -free primary/secondary switchgear technology (acquired by Lucy Group April 2026).",
          "Voltage Ceiling (Now → 2028)": "Up to 36 kV → 36 kV SF 6 -Free",
          "Est. Net Local VA": "46%–56%",
          "Execution Status": "Operational"
        },
        {
          "Company / Industrial Entity": "Saudi Voltamp JV (Al-Sharif Holding & Voltamp Oman)",
          "City / Cluster": "Western / Central KSA",
          "Core Grid Product Scope": "High-Voltage Power & Distribution Transformers",
          "2025–2026 Operational Capacity & Revenue": "Pre-commercial ($10M initial JV capital launched February 2024; previously supplied from Oman parent up to 132 kV).",
          "Announced / Under-Construction Expansion (2026–2030f)": "Developing local Saudi manufacturing facility for power and distribution transformers.",
          "Voltage Ceiling (Now → 2028)": "Import → 132 kV Power Trafos",
          "Est. Net Local VA": "40%–50%",
          "Execution Status": "Under Development (2026–27f)"
        },
        {
          "Company / Industrial Entity": "Arabian Transformers Co. (ATC) & TIEPCO",
          "City / Cluster": "Dammam & Riyadh",
          "Core Grid Product Scope": "Distribution Transformers (25 kVA–10 MVA), Compact Substations & Panels",
          "2025–2026 Operational Capacity & Revenue": "SEC-qualified oil-immersed distribution transformers (ATC) and MV/LV switchgear/control panels (TIEPCO; ERP digital upgrade May 2025).",
          "Announced / Under-Construction Expansion (2026–2030f)": "Scaling shift utilization for Roshn housing (115k homes/yr) and SEC rural/urban distribution reinforcement.",
          "Voltage Ceiling (Now → 2028)": "Up to 36 kV / 10 MVA → 36 kV",
          "Est. Net Local VA": "50%–60%",
          "Execution Status": "Operational"
        },
        {
          "Company / Industrial Entity": "TBEA / Chint / HD Hyundai Electric (KSA Pipeline)",
          "City / Cluster": "Riyadh / Dammam / SPARK",
          "Core Grid Product Scope": "EHV/UHV Power Transformers (380–800 kV), GIS & Reactors",
          "2025–2026 Operational Capacity & Revenue": "0 MVA manufactured in-Kingdom (TBEA executing RMB 16.4B SEC order from China; HD Hyundai executing NEOM/Diriyah orders from Ulsan).",
          "Announced / Under-Construction Expansion (2026–2030f)": "Evaluating local KSA transformer/GIS assembly facilities under MoE 75% localization mandate & SAR 104B Energy Localization Forum.",
          "Voltage Ceiling (Now → 2028)": "Import → 380–500 kV Proposed",
          "Est. Net Local VA": "30%–45%",
          "Execution Status": "Feasibility / Pre-FID (2028–30f)"
        }
      ]
    },
    {
      "tableNumber": 2,
      "title": "Table 2: Financial & Operational Performance Comparison of Saudi Arabia’s Listed Grid Equipment Champions (Audited 2024a–2025a vs. 2026e–2030f Consensus)",
      "columns": [
        "Metric / Financial Indicator",
        "Riyadh Cables Group (RCGC — 4142)",
        "Electrical Industries Co. (EIC — 1303)",
        "Al-Babtain Power & Telecom (2320)",
        "Bawan Electrical Division (UTEC & USSG)"
      ],
      "rows": [
        {
          "Metric / Financial Indicator": "FY 2024a Audited Revenue",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 9,007M ($2,401.9M)",
          "Electrical Industries Co. (EIC — 1303)": "SAR 1,987M ($529.9M)",
          "Al-Babtain Power & Telecom (2320)": "SAR 2,720M ($725.3M)",
          "Bawan Electrical Division (UTEC & USSG)": "SAR 533.8M (9M Electrical Segment)"
        },
        {
          "Metric / Financial Indicator": "FY 2025a Audited Revenue",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 10,674M ($2,846.4M)",
          "Electrical Industries Co. (EIC — 1303)": "SAR 2,296M ($612.3M)",
          "Al-Babtain Power & Telecom (2320)": "SAR 2,857M ($761.9M)",
          "Bawan Electrical Division (UTEC & USSG)": "Consolidating 90% stake in UTEC/USSG"
        },
        {
          "Metric / Financial Indicator": "FY 2030f Projected Revenue (CAGR)",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 13,942M (+5.5% CAGR)",
          "Electrical Industries Co. (EIC — 1303)": "SAR 3,528M (+9.0% CAGR)",
          "Al-Babtain Power & Telecom (2320)": "SAR 4,440M (+9.2% CAGR)",
          "Bawan Electrical Division (UTEC & USSG)": "Expanding via 2027 HV Transformer Plant"
        },
        {
          "Metric / Financial Indicator": "FY 2025a Gross Profit & Margin (%)",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 1,733M ( 16.2% )",
          "Electrical Industries Co. (EIC — 1303)": "SAR 860M ( 37.5% )",
          "Al-Babtain Power & Telecom (2320)": "SAR 693M ( 24.3% )",
          "Bawan Electrical Division (UTEC & USSG)": "High-margin specialized substations"
        },
        {
          "Metric / Financial Indicator": "FY 2025a Net Profit & Margin (%)",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 1,085M ( 10.2% )",
          "Electrical Industries Co. (EIC — 1303)": "SAR 630M ( 27.4% )",
          "Al-Babtain Power & Telecom (2320)": "SAR 458M ( 16.0% )",
          "Bawan Electrical Division (UTEC & USSG)": "SAR 48.5M net profit (9M baseline)"
        },
        {
          "Metric / Financial Indicator": "FY 2025a Return on Equity (ROE)",
          "Riyadh Cables Group (RCGC — 4142)": "36.6% (38.7% in 2026e)",
          "Electrical Industries Co. (EIC — 1303)": "56.1% (59.4% in 2027f)",
          "Al-Babtain Power & Telecom (2320)": "38.1% (33.0% in 2026e)",
          "Bawan Electrical Division (UTEC & USSG)": "Supported by low group leverage"
        },
        {
          "Metric / Financial Indicator": "Order Backlog (End-2025)",
          "Riyadh Cables Group (RCGC — 4142)": "SAR 5.10B (163 kt; 70% Trans.)",
          "Electrical Industries Co. (EIC — 1303)": "SAR 3.30B (+SAR 1.41B EHV)",
          "Al-Babtain Power & Telecom (2320)": "SAR 3.50B (+SAR 1.8B awards)",
          "Bawan Electrical Division (UTEC & USSG)": "SEC & Data Center MoU backlog"
        },
        {
          "Metric / Financial Indicator": "Domestic Revenue Share vs. Exports (2025)",
          "Riyadh Cables Group (RCGC — 4142)": "69% KSA / 31% Export (UAE 20%, Iraq 7%)",
          "Electrical Industries Co. (EIC — 1303)": "89% KSA / 11% Export (Europe 8%, GCC 3%)",
          "Al-Babtain Power & Telecom (2320)": "87% KSA / 13% Export (GCC & Egypt Link)",
          "Bawan Electrical Division (UTEC & USSG)": "Predominantly KSA utility & industrial"
        }
      ]
    },
    {
      "tableNumber": 3,
      "title": "Table 3: EPC & Utility Procurement Action Matrix — Matching Saudi Grid Tender Packages to Operational & Announced Factory Capabilities",
      "columns": [
        "Grid Equipment Package",
        "2025 KSA Market ($M)",
        "2025 Local Coverage",
        "2030f Local Coverage",
        "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)"
      ],
      "rows": [
        {
          "Grid Equipment Package": "LV, MV & 132–380 kV AC Land Power Cables ( HS 8544 )",
          "2025 KSA Market ($M)": "$4,800M",
          "2025 Local Coverage": "88.0%",
          "2030f Local Coverage": "93.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Procure 100% in-Kingdom via frame agreements with RCGC, Bahra Electric, Jeddah Cables, and El Sewedy KSA. Because RCGC operates at 97% utilization, lock in rolling mill slots 6–9 months ahead and index contracts to LME copper/aluminum formulas."
        },
        {
          "Grid Equipment Package": "Transmission Lattice Towers & Solar Steel ( HS 7308 )",
          "2025 KSA Market ($M)": "$1,150M",
          "2025 Local Coverage": "91.0%",
          "2030f Local Coverage": "95.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Source 100% locally from Al-Babtain (220 kt capacity), Zamil Steel, and Hidada to maximize Benaa/IKTVA score and capture 72% domestic value-added."
        },
        {
          "Grid Equipment Package": "Distribution & Medium Power Transformers (≤100 MVA) ( HS 850421–22 )",
          "2025 KSA Market ($M)": "$620M",
          "2025 Local Coverage": "82.0%",
          "2030f Local Coverage": "90.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Source oil-filled and cast-resin dry-type units (≤33–132 kV) from EIC (STC/WESCOSA), UTEC (Bawan), and ATC. Verify SASO SALEEM CoC and SEC AVL status prior to RFQ issuance."
        },
        {
          "Grid Equipment Package": "LV & MV Switchgear, RMUs & Automation Panels (≤36 kV) ( HS 8536/37 )",
          "2025 KSA Market ($M)": "$1,650M",
          "2025 Local Coverage": "76.0%",
          "2030f Local Coverage": "88.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Utilize local assembly lines of Alfanar, WESCOSA, Schneider Electric (expanding to 32 lines), ABB Dammam, Lucy Electric Al Khobar, and USSG. Specify silicone-rubber sand/salt-fog seals and SF 6 -free dry-air/vacuum designs for giga-projects."
        },
        {
          "Grid Equipment Package": "High-Voltage GIS Substation Bays (132–380 kV) ( HS 8535/37 )",
          "2025 KSA Market ($M)": "$870M",
          "2025 Local Coverage": "46.0%",
          "2030f Local Coverage": "72.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Pair local bay assembly at Hitachi Energy Dammam, Siemens Energy Dammam Hub, GE Vernova GESAT, and Alfanar Riyadh with early offshore slot reservation for HV vacuum/fluoronitrile interrupter poles."
        },
        {
          "Grid Equipment Package": "EHV/UHV Power Transformers (380–800 kV) & HVDC Systems ( HS 850423/40 )",
          "2025 KSA Market ($M)": "$1,450M",
          "2025 Local Coverage": "12.0%",
          "2030f Local Coverage": "48.0%",
          "Optimal Sourcing & Qualification Strategy for EPCs (2026–2030)": "Transition 380 kV AC transformer orders toward SPTC Dammam (SAR 192M expansion online 2027f) and Bawan’s new HV plant (2027f) to boost ICV score, while reserving offshore manufacturing slots (18–48 months ahead) with Hitachi Energy, Siemens Energy, GE Vernova, TBEA, and HD Hyundai for 800 kV UHV and ±500 kV HVDC converter stations."
        }
      ]
    }
  ]
}