  "publisher": "Energy Solutions Intelligence",
  "sourceArticle": "https://energy-solutions.co/supply-chain/mena-africa/egypt-energy-equipment-import-map",
  "generatedFrom": "Published article tables",
  "dateModified": "2026-11-15",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "tables": [
    {
      "tableNumber": 1,
      "title": "Table 1: Egypt Core Energy Equipment Trade & Localization Matrix across HS-4 & HS-6 Headings (Values in USD Millions)",
      "columns": [
        "HS Code",
        "Equipment / Sub-Assembly Description",
        "2023 World Imports",
        "2023 World Exports",
        "2023 Net Balance",
        "2025 China Imports",
        "Localization Status",
        "Primary Domestic / Foreign OEMs & Choke Point"
      ],
      "rows": [
        {
          "HS Code": "8544 (All)",
          "Equipment / Sub-Assembly Description": "Insulated Wire, Power Cable & Optical Fibre",
          "2023 World Imports": "$343.00M",
          "2023 World Exports": "$1,150.00M",
          "2023 Net Balance": "+$807.00M",
          "2025 China Imports": "$170.80M",
          "Localization Status": "Net Exporter",
          "Primary Domestic / Foreign OEMs & Choke Point": "Elsewedy Electric, Energya Cables, Giza Cable Industries; imports limited to submarine/EHV & fiber ( 854470 : $52M imp)."
        },
        {
          "HS Code": "7408 (All)",
          "Equipment / Sub-Assembly Description": "Refined Copper Wire (Upstream Conductor Input)",
          "2023 World Imports": "$272.00M",
          "2023 World Exports": "$660.00M",
          "2023 Net Balance": "+$388.00M",
          "2025 China Imports": "N/A (UAE 88%)",
          "Localization Status": "Net Exporter",
          "Primary Domestic / Foreign OEMs & Choke Point": "UAE supplies $242M (2023) / $477M Ch. 74 (2025) cathode/rod; Egypt draws rod/wire and exports 50% ($334M) to Saudi Arabia."
        },
        {
          "HS Code": "850423",
          "Equipment / Sub-Assembly Description": "Liquid-Dielectric Power Transformers (>10,000 kVA)",
          "2023 World Imports": "$12.40M",
          "2023 World Exports": "$26.00M",
          "2023 Net Balance": "+$13.60M",
          "2025 China Imports": "Sub-part of 8504",
          "Localization Status": "Net Exporter",
          "Primary Domestic / Foreign OEMs & Choke Point": "Elsewedy Transformers (up to 500 kV / 500 MVA), Hitachi Energy/ABB Egypt; exports to MENA, UK, and Sub-Saharan Africa."
        },
        {
          "HS Code": "850421",
          "Equipment / Sub-Assembly Description": "Liquid-Dielectric Distribution Transformers (≤650 kVA)",
          "2023 World Imports": "$6.49M",
          "2023 World Exports": "$10.40M",
          "2023 Net Balance": "+$3.91M",
          "2025 China Imports": "Sub-part of 8504",
          "Localization Status": "Net Exporter",
          "Primary Domestic / Foreign OEMs & Choke Point": "El-Maco, Elsewedy, ABB, EGMAC supply EEHC’s 229,524 distribution transformer fleet (105,067 MVA)."
        },
        {
          "HS Code": "850422",
          "Equipment / Sub-Assembly Description": "Liquid-Dielectric Medium Power Transformers (650–10,000 kVA)",
          "2023 World Imports": "$16.80M",
          "2023 World Exports": "$16.00M",
          "2023 Net Balance": "-$0.80M",
          "2025 China Imports": "Sub-part of 8504",
          "Localization Status": "Balanced / Local",
          "Primary Domestic / Foreign OEMs & Choke Point": "High domestic coverage for solar/wind MV step-up skids; specialized multi-winding units imported for petrochemical/industrial plants."
        },
        {
          "HS Code": "850440",
          "Equipment / Sub-Assembly Description": "Static Converters (Solar PV Inverters, BESS PCS, Rectifiers)",
          "2023 World Imports": "$222.00M",
          "2023 World Exports": "$1.26M",
          "2023 Net Balance": "-$220.74M",
          "2025 China Imports": "Dominant in $284.9M",
          "Localization Status": "Critical Gap",
          "Primary Domestic / Foreign OEMs & Choke Point": "100% import reliance on Sungrow, Huawei, Sineng, SMA, Ingeteam; 63.75% of all HS 8504 imports."
        },
        {
          "HS Code": "850490",
          "Equipment / Sub-Assembly Description": "Parts of Transformers & Static Converters",
          "2023 World Imports": "$40.00M",
          "2023 World Exports": "$2.28M",
          "2023 Net Balance": "-$37.72M",
          "2025 China Imports": "Sub-part of 8504",
          "Localization Status": "Upstream Gap",
          "Primary Domestic / Foreign OEMs & Choke Point": "CRGO silicon electrical steel cores, ≥66 kV condenser bushings, and motorized on-load tap changers (OLTCs) must be imported."
        },
        {
          "HS Code": "850431–34",
          "Equipment / Sub-Assembly Description": "Dry-Type & Instrument Transformers (All Ratings)",
          "2023 World Imports": "$42.95M",
          "2023 World Exports": "$4.39M",
          "2023 Net Balance": "-$38.56M",
          "2025 China Imports": "Sub-part of 8504",
          "Localization Status": "Import Reliant",
          "Primary Domestic / Foreign OEMs & Choke Point": "Elsewedy manufactures cast-resin up to 15 MVA, but wind-turbine nacelle dry transformers and instrument CTs/VTs are largely imported."
        },
        {
          "HS Code": "8541",
          "Equipment / Sub-Assembly Description": "Solar PV Cells, Modules, Diodes & Semiconductors",
          "2023 World Imports": "$218.00M (est.)",
          "2023 World Exports": "$4.20M",
          "2023 Net Balance": "-$213.80M",
          "2025 China Imports": "$245.39M",
          "Localization Status": "SCZONE Scaling",
          "Primary Domestic / Foreign OEMs & Choke Point": "2.3 GW Chinese module imports in 2025 + 2.4 GW cell/wafer imports in H1 2026; EliTe Solar (2 GW cells / 3 GW modules) opened Jan 2026."
        },
        {
          "HS Code": "8502",
          "Equipment / Sub-Assembly Description": "Electric Generating Sets (Wind Turbines & Diesel Gensets)",
          "2023 World Imports": "$245.00M (est.)",
          "2023 World Exports": "$11.50M",
          "2023 Net Balance": "-$233.50M",
          "2025 China Imports": "$233.09M",
          "Localization Status": "Nacelle Gap",
          "Primary Domestic / Foreign OEMs & Choke Point": "Envision & Goldwind dominate Gulf of Suez wind imports; NSF fabricates steel towers locally (HS 7308); SANY 2 GW MoU signed June 2026."
        },
        {
          "HS Code": "8507",
          "Equipment / Sub-Assembly Description": "Electric Accumulators (Li-Ion BESS & Lead-Acid Batteries)",
          "2023 World Imports": "$138.00M (est.)",
          "2023 World Exports": "$34.00M",
          "2023 Net Balance": "-$104.00M",
          "2025 China Imports": "$141.87M",
          "Localization Status": "Pack Assembly",
          "Primary Domestic / Foreign OEMs & Choke Point": "Sungrow 10 GWh BESS plant broke ground Aug 2026; ATUM Solar 1 GWh BESS due H1 2027; lithium iron phosphate (LFP) cells remain imported."
        },
        {
          "HS Code": "8537",
          "Equipment / Sub-Assembly Description": "Boards, Panels, Consoles & Switchgear Assemblies",
          "2023 World Imports": "$165.00M (est.)",
          "2023 World Exports": "$92.00M",
          "2023 Net Balance": "-$73.00M",
          "2025 China Imports": "$119.68M",
          "Localization Status": "Strong Local LV/MV",
          "Primary Domestic / Foreign OEMs & Choke Point": "Schneider Electric (Badr City), ABB (10th of Ramadan), Elsewedy, Lectrobar, and EGIC localize LV/MV panels up to 24 kV; EHV GIS imported."
        },
        {
          "HS Code": "8535 + 8536",
          "Equipment / Sub-Assembly Description": "HV (>1,000 V) & LV (≤1,000 V) Circuit Breakers & Relays",
          "2023 World Imports": "$210.00M (est.)",
          "2023 World Exports": "$68.00M",
          "2023 Net Balance": "-$142.00M",
          "2025 China Imports": "$115.24M",
          "Localization Status": "Core Breaker Gap",
          "Primary Domestic / Foreign OEMs & Choke Point": "China supplied $90.58M (8536) + $24.66M (8535) and India supplied $16.21M in 2025; vacuum interrupters, SF6 poles & IED relays imported."
        },
        {
          "HS Code": "8501",
          "Equipment / Sub-Assembly Description": "Electric Motors & Generators (Excl. Generating Sets)",
          "2023 World Imports": "$142.00M (est.)",
          "2023 World Exports": "$8.40M",
          "2023 Net Balance": "-$133.60M",
          "2025 China Imports": "$117.23M",
          "Localization Status": "Critical Gap",
          "Primary Domestic / Foreign OEMs & Choke Point": "China imports rose +41.2% from $83M (2023) to $117.23M (2025); industrial induction motors for desalination, pumping & HVAC imported."
        },
        {
          "HS Code": "8503 + 8538",
          "Equipment / Sub-Assembly Description": "Dedicated Parts for Generators (8503) & Switchgear (8538)",
          "2023 World Imports": "$134.00M (est.)",
          "2023 World Exports": "$14.20M",
          "2023 Net Balance": "-$119.80M",
          "2025 China Imports": "$101.78M",
          "Localization Status": "Sub-Tier Input",
          "Primary Domestic / Foreign OEMs & Choke Point": "China supplied $72.41M in 8503 and $29.37M in 8538 in 2025; feeds local switchgear panel builders and wind/thermal O&M."
        },
        {
          "HS Code": "8532",
          "Equipment / Sub-Assembly Description": "Electrical Power Capacitors (Fixed, Variable, Reactive Banks)",
          "2023 World Imports": "$48.00M (est.)",
          "2023 World Exports": "$2.10M",
          "2023 Net Balance": "-$45.90M",
          "2025 China Imports": "$34.69M",
          "Localization Status": "Import Reliant",
          "Primary Domestic / Foreign OEMs & Choke Point": "China ($34.69M), Saudi Arabia ($6.30M), and India ($1.36M) supply shunt capacitor banks required for EETC reactive power compensation."
        }
      ]
    },
    {
      "tableNumber": 2,
      "title": "Table 2: Flagship Egyptian Renewable & Storage Projects — OEM Equipment Provenance & Local Balance-of-Plant (BoP) Audit",
      "columns": [
        "Project Name & Location",
        "Capacity & Tech",
        "Sponsors & Capex",
        "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)",
        "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)",
        "Est. Local Capex Share"
      ],
      "rows": [
        {
          "Project Name & Location": "Abydos I Solar + BESS (Kom Ombo, Aswan)",
          "Capacity & Tech": "500 MW PV + 300 MWh BESS (COD Dec 2024)",
          "Sponsors & Capex": "AMEA Power ($500M; IFC/JICA/DFC financed)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "JA Solar / Trina bifacial PV modules (China); Sungrow inverters & LFP BESS containers (China); Nextracker / Arctech trackers.",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "MV/LV XLPE collector cables (Elsewedy/Energya), grid substation step-up transformers, civil piling, steel structures & EETC bay integration.",
          "Est. Local Capex Share": "22%–26%"
        },
        {
          "Project Name & Location": "Amunet Wind Farm (Ras Ghareb, Gulf of Suez)",
          "Capacity & Tech": "500 MW Onshore Wind (COD Q2 2025)",
          "Sponsors & Capex": "AMEA Power (60%) & Sumitomo Corp (40%) ($680M)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "77 × 6.5 MW Envision Energy wind turbines (nacelles, permanent-magnet generators, blades, internal converters).",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "33 kV underground collector cables, 220/33 kV main substation transformers, reinforced concrete foundations, crane pads & haul roads.",
          "Est. Local Capex Share": "24%–28%"
        },
        {
          "Project Name & Location": "Red Sea Wind Energy (Ras Ghareb, Gulf of Suez)",
          "Capacity & Tech": "650 MW Onshore Wind (Full COD June 2025)",
          "Sponsors & Capex": "ENGIE (35%), Orascom (25%), Toyota Tsusho (20%), Eurus (20%) ($680M)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "104 Goldwind turbines (84×6.0 MW + 20×7.5 MW nacelles, hubs, blades) + 69 imported tubular steel towers.",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "Orascom EPC : 35 tubular steel towers fabricated locally by NSF in Ain Sokhna (33.7% of fleet), MV/HV cables, 220 kV substation & civil works.",
          "Est. Local Capex Share": "31%–35%"
        },
        {
          "Project Name & Location": "Suez Wind Energy (Gulf of Suez)",
          "Capacity & Tech": "1,100 MW Onshore Wind (Under Construction)",
          "Sponsors & Capex": "ACWA Power & Hassan Allam Utilities ($1.5B; EBRD financed)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "138 × 8.0 MW Envision Energy turbines (nacelles, blades, pitch/yaw systems, nacelle dry-type transformers).",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "Hassan Allam Construction civil/structural BoP, local steel tower co-fabrication, domestic MV/HV copper/aluminum cables & 500/220 kV grid tie.",
          "Est. Local Capex Share": "28%–33%"
        },
        {
          "Project Name & Location": "Obelisk Hybrid PV + BESS (Nagaa Hammadi)",
          "Capacity & Tech": "1,000 MW PV + 200 MWh BESS (Ph. 1 500 MW 2026)",
          "Sponsors & Capex": "Scatec ASA (~$600M; EBRD/EIB/AFDB financed)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "Chinese N-type TOPCon modules (or SCZONE EliTe/Sunrev supply for Ph. 2), 1,500 V central/string inverters, LFP battery racks & PCS.",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "Substation power transformers (>10 MVA), MV/LV trench cables, galvanized steel mounting purlins (CSF), and civil switchyard works.",
          "Est. Local Capex Share": "25%–38%*"
        },
        {
          "Project Name & Location": "Abydos II Solar + BESS & Standalone BESS",
          "Capacity & Tech": "1,000 MW PV + 600 MWh BESS (+ 1,500 MWh Standalone)",
          "Sponsors & Capex": "AMEA Power (~$800M+; IFC financed)",
          "Primary Imported Core OEMs (HS 8541 / 8502 / 8507 / 850440)": "Imported LFP cells/racks & PCS (transitioning toward Sungrow SCZONE BESS assembly from 2027), 1,500 V PV inverters.",
          "Localized Domestic Scope (HS 8544 / 850423 / 7308 / Civil)": "Local substation transformers, HV/MV switchgear bays, domestic power cables, and local solar module/BESS pack integration post-2026.",
          "Est. Local Capex Share": "30%–45%*"
        }
      ]
    },
    {
      "tableNumber": 3,
      "title": "Table 3: Egypt Clean-Tech & Grid Equipment Manufacturing Tracker (Operational, Under Construction & Contracted as of Nov 2026)",
      "columns": [
        "Facility / Joint Venture",
        "Location",
        "Product & Annual Nameplate Capacity",
        "Capex ($M)",
        "Milestone Status (Cutoff: Aug 2026)",
        "Imported Upstream Inputs Required",
        "Est. Local Value-Added"
      ],
      "rows": [
        {
          "Facility / Joint Venture": "EliTe Solar (China)",
          "Location": "SCZONE (TEDA Ain Sokhna, 78,000 m²)",
          "Product & Annual Nameplate Capacity": "2 GW N-type Solar Cells + 3 GW PV Modules",
          "Capex ($M)": "$115M–$150M",
          "Milestone Status (Cutoff: Aug 2026)": "Operational (Jan 11, 2026)",
          "Imported Upstream Inputs Required": "Monocrystalline silicon wafers (China), silver paste, EVA/POE film, solar glass (until local glass online).",
          "Est. Local Value-Added": "28%–35%"
        },
        {
          "Facility / Joint Venture": "Sunrev Solar (China)",
          "Location": "SCZONE (TEDA Ain Sokhna, 200,000 m²)",
          "Product & Annual Nameplate Capacity": "Ph. 1: 2 GW PV Modules; Ph. 2: 2 GW Silicon/Cells",
          "Capex ($M)": "$200M",
          "Milestone Status (Cutoff: Aug 2026)": "Construction (2026 Ramp)",
          "Imported Upstream Inputs Required": "Ph. 1 imports cells & glass; Ph. 2 shifts upstream to silicon wafers and chemical precursors.",
          "Est. Local Value-Added": "18% (Ph.1) → 34% (Ph.2)"
        },
        {
          "Facility / Joint Venture": "ATUM Solar (JA Solar, AH Industrial, Infinity, Global South Utilities)",
          "Location": "SCZONE (TEDA Ain Sokhna, 200,000 m²)",
          "Product & Annual Nameplate Capacity": "2 GW Solar Cells (Export) + 2 GW Modules + 1 GWh BESS",
          "Capex ($M)": "$210M (EGP 10.5B)",
          "Milestone Status (Cutoff: Aug 2026)": "Contracted (Target H1 2027)",
          "Imported Upstream Inputs Required": "JA Solar silicon wafers, LFP battery cells, BMS microcontrollers, POE film.",
          "Est. Local Value-Added": "30%–38%"
        },
        {
          "Facility / Joint Venture": "Sungrow Middle East & Africa BESS Factory",
          "Location": "SCZONE (TEDA Ain Sokhna, 50,000 m²)",
          "Product & Annual Nameplate Capacity": "10 GWh/year Utility & C&I BESS Containers",
          "Capex ($M)": "~$120M (est.)",
          "Milestone Status (Cutoff: Aug 2026)": "Broke Ground Aug 27, 2026 (COD Apr 2027)",
          "Imported Upstream Inputs Required": "Prismatic LFP battery cells ( 850760 ), IGBT/SiC power modules, BMS chips; localizes enclosures, HVAC/liquid cooling, wiring & testing.",
          "Est. Local Value-Added": "22%–30%"
        },
        {
          "Facility / Joint Venture": "SANY Renewable Energy & Arab Organization for Industrialization (AOI)",
          "Location": "Egypt Industrial Zone (MoU Signed June 24, 2026)",
          "Product & Annual Nameplate Capacity": "2 GW/year Wind Turbine Blades, Nacelles & Towers (up to 70% local target)",
          "Capex ($M)": "$300M+",
          "Milestone Status (Cutoff: Aug 2026)": "MoU / Feasibility (June 2026)",
          "Imported Upstream Inputs Required": "Main shaft bearings, yaw/pitch slewing rings, carbon/E-glass roving, epoxy resin, permanent magnets & IGBT converters.",
          "Est. Local Value-Added": "35%–55% (Target)"
        },
        {
          "Facility / Joint Venture": "Kibing Group Solar Photovoltaic Glass Complex",
          "Location": "SCZONE (Ain Sokhna)",
          "Product & Annual Nameplate Capacity": "Ultra-Clear Rolled Solar PV Glass (1.2M+ tons/yr planned)",
          "Capex ($M)": "$685M–$700M",
          "Milestone Status (Cutoff: Aug 2026)": "Framework / Permitting",
          "Imported Upstream Inputs Required": "Uses high-purity North Sinai/Eastern Desert silica sand & domestic natural gas; imports soda ash & furnace refractories.",
          "Est. Local Value-Added": "65%–75%"
        },
        {
          "Facility / Joint Venture": "Elsewedy Electric & EETC Grid Consortium (with Siemens / Hitachi / Schneider)",
          "Location": "10th of Ramadan, Ain Sokhna & Badr City",
          "Product & Annual Nameplate Capacity": "15,000+ MVA Transformers, LV/MV/HV Cables, 24 kV Switchgear & Smart Meters",
          "Capex ($M)": "Established Base",
          "Milestone Status (Cutoff: Aug 2026)": "Fully Operational",
          "Imported Upstream Inputs Required": "CRGO silicon electrical steel ( 722511 ), copper cathode ( 7403 ), HV bushings, OLTCs, and vacuum interrupters.",
          "Est. Local Value-Added": "38%–62%"
        }
      ]
    },
    {
      "tableNumber": 4,
      "title": "Table 4: Decision & Procurement Action Matrix — Capex FX Sensitivity to a Hypothetical 15% EGP/USD Movement & Optimal Sourcing Rules",
      "columns": [
        "Capital Package",
        "2025 Total FX Exposure (Direct + Feedstock)",
        "2028 Total FX Exposure (Post-SCZONE)",
        "EGP Capex Shift per +15% FX Move (2025 → 2028)",
        "Recommended Procurement & Contracting Strategy for EPCs / IPPs"
      ],
      "rows": [
        {
          "Capital Package": "100 MW Solar PV + 50 MWh BESS ($88.0M)",
          "2025 Total FX Exposure (Direct + Feedstock)": "78.0% ($68.64M FX / $19.36M EGP)",
          "2028 Total FX Exposure (Post-SCZONE)": "55.0% ($48.40M FX / $40.04M EGP)",
          "EGP Capex Shift per +15% FX Move (2025 → 2028)": "+11.70% → +8.25%",
          "Recommended Procurement & Contracting Strategy for EPCs / IPPs": "Split EPC into offshore equipment supply (inverters 850440 , LFP cells) and onshore EGP supply (local transformers 850422/23 , MV/LV cables 8544 , CSF tracker purlins, and EliTe/Sunrev SCZONE modules). Index local cable contracts strictly to LME copper formulas."
        },
        {
          "Capital Package": "220/66/22 kV Grid Substation ($42.0M)",
          "2025 Total FX Exposure (Direct + Feedstock)": "58.0% ($24.36M FX / $17.64M EGP)",
          "2028 Total FX Exposure (Post-SCZONE)": "50.0% ($21.00M FX / $21.00M EGP)",
          "EGP Capex Shift per +15% FX Move (2025 → 2028)": "+8.70% → +7.50%",
          "Recommended Procurement & Contracting Strategy for EPCs / IPPs": "Procure 100% of oil-immersed power transformers (>10 MVA, 850423 ), 22 kV switchgear ( 8537 ), and HV/MV cables domestically. Reserve direct FX allocation for 220 kV GIS breaker bays ( 8535 ), IED protection relays, and OLTC/bushing spares ( 850490 )."
        },
        {
          "Capital Package": "250 MW Onshore Wind Farm ($265.0M)",
          "2025 Total FX Exposure (Direct + Feedstock)": "75.0% ($198.75M FX / $66.25M EGP)",
          "2028 Total FX Exposure (Post-SCZONE)": "56.0% ($148.40M FX / $116.60M EGP)",
          "EGP Capex Shift per +15% FX Move (2025 → 2028)": "+11.25% → +8.40%",
          "Recommended Procurement & Contracting Strategy for EPCs / IPPs": "Mandate minimum 50%–100% domestic tubular steel tower fabrication (NSF / Elsewedy / SIAC) in turbine supply agreements, shifting HS 730820 out of foreign EPC scope and saving $1,800–$2,400 per tower section in oversize maritime freight."
        }
      ]
    }
  ]
}