campus_architecture,design_ambient_c,peak_pue,gross_power_mw_per_100mw_it,cooling_overhead_mw,chiller_derating_oversize_pct,power_cooling_capex_usd_mw_m,capex_100mw_block_usd_m,equip_lead_time_months_2026,primary_bottleneck "Temperate 35C Baseline (Air-Cooled Chiller, 35 kW Racks)",35,1.32,132.0,32.0,0.0,3.40,340.0,24,Standard MV switchgear & 115-230 kV utility transformer GCC 50C Desert Air-Cooled + Adiabatic (45 kW Racks),50,1.52,152.0,52.0,28.0,4.35,435.0,30,"50C-rated centrifugal chillers, dry coolers & desal water" GCC 50C Direct-to-Chip Liquid CDU (120 kW Blackwell Racks),50,1.26,126.0,26.0,12.0,4.85,485.0,34,"1.5+ MW liquid CDUs, 380 kV SEC/DEWA GIS & 400 kV cables" GCC 50C Hybrid Gas-Turbine + Solar BESS + Liquid AI Campus,50,1.28,128.0,28.0,14.0,6.40,640.0,44,Aeroderivative/H-class gas turbines (40-48 mo) + BESS