cable_class,max_voltage_kv,conductor_metal,delivered_usd_per_km,circuit_cost_50km_3ph_usd_m,gcc_local_share_pct,import_dep_component,lead_time_weeks_2026,key_regional_oems 33 kV Medium-Voltage XLPE Feeder (Al 3x300 mm2),36,Local GCC Aluminium (EGA/Maaden),46500,2.33,92.0,Standard XLPE & semicon resin,14,"Oman Cables (Prysmian), Riyadh Cables, Ducab, Bahra, Elsewedy" "132 kV High-Voltage Underground XLPE (Cu 1,200 mm2)",132,Imported Grade A Cu Rod,315000,47.25,84.0,Super-clean HV XLPE & HV joints,26,"Riyadh Cables, Ducab HV, Bahra Electric, Elsewedy" "380-400 kV EHV Underground Milliken XLPE (Cu 2,500 mm2)",400,OFHC / ETP Segmented Cu,1180000,177.00,62.0,Borealis/Dow EHV XLPE + Brugg/Pfisterer 400 kV joints,46,"Ducab HV (105C EPQ), Riyadh Cables (up to 500 kV), Bahra, Elsewedy" 380-400 kV High-Temp Overhead Conductor (ACCC / ACSR),400,GCC Smelter EC Al + Steel/Carbon Core,34000,5.10,88.0,Composite carbon-core rods (for ACCC reconductoring),18,"Riyadh Cables, Ducab Metals, Elsewedy, Oman Cables"