  "dataset_id": "SC-425",
  "title": "Wildfire Grid Rebuilding & Hardening Equipment Demand Dataset (2018-2026)",
  "publisher": "Energy Solutions Intelligence",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "source_article": "https://energy-solutions.co/supply-chain/climate-risk/wildfire-grid-equipment-rebuilding-demand-surges",
  "dateModified": "2026-11-25",
  "wmp_program_benchmarks": [
    {
      "Utility or Rebuild Event": "PG&E System Hardening & EUP",
      "Jurisdiction & Filing": "Northern/Central CA D.23-11-069 / SB 884",
      "Undergrounding (Completed / Plan)": "1,210 mi (Q1 '26) 6,900 mi (to 2037)",
      "Covered Conductor": "~2,000 mi (207 mi in '25)",
      "Poles Replaced": "28,500+",
      "Verified Unit Cost (UG vs. CC)": "UG: $2.80M/mi CC: $1.21M/mi",
      "Ignition Risk Reduction": "UG: 98.5% CC: 68.0%",
      "Primary Source": "PG&E 2026 EUP"
    },
    {
      "Utility or Rebuild Event": "Southern California Edison (SCE)",
      "Jurisdiction & Filing": "Southern CA D.25-09-030 / WMP",
      "Undergrounding (Completed / Plan)": "269 mi (to '28) +152 mi Burn Scar",
      "Covered Conductor": "7,206 mi ('25) +775 mi ('26–'28)",
      "Poles Replaced": "148,000+",
      "Verified Unit Cost (UG vs. CC)": "UG: $2.23M/mi CC: $0.847M/mi",
      "Ignition Risk Reduction": "UG: 98.8% CC: 72.0%",
      "Primary Source": "SCE 2025 WMP AIR"
    },
    {
      "Utility or Rebuild Event": "San Diego Gas & Electric (SDG&E)",
      "Jurisdiction & Filing": "San Diego County, CA Res. SPD-30 / WiNGS",
      "Undergrounding (Completed / Plan)": "300 mi ('20–'25) 1,500 mi Plan",
      "Covered Conductor": "180 mi ('20–'25) +130 mi ('26–'28)",
      "Poles Replaced": "16,400+",
      "Verified Unit Cost (UG vs. CC)": "UG: $1.48M/mi CC: $1.552M/mi",
      "Ignition Risk Reduction": "UG: 99.02% CC: 58.1%",
      "Primary Source": "SDG&E 2026 WMP"
    },
    {
      "Utility or Rebuild Event": "PacifiCorp (6-State WMP)",
      "Jurisdiction & Filing": "OR, CA, UT, WA, ID, WY OPUC UM 2207 R1",
      "Undergrounding (Completed / Plan)": "38 mi (115 mi Plan)",
      "Covered Conductor": "358 mi (170 mi OR '25)",
      "Poles Replaced": "11,800+ (4,225 OR '25)",
      "Verified Unit Cost (UG vs. CC)": "UG: $2.45M/mi CC: $1.18M/mi",
      "Ignition Risk Reduction": "UG: 98.0% CC: 65.0%",
      "Primary Source": "PacifiCorp UM 2207"
    },
    {
      "Utility or Rebuild Event": "Xcel Energy (PSCo & SPS)",
      "Jurisdiction & Filing": "Colorado & Texas/NM 24A-0296E / PUCT",
      "Undergrounding (Completed / Plan)": "50 mi CO WMP (220 mi Plan)",
      "Covered Conductor": "480 mi (CO & TX/NM)",
      "Poles Replaced": "38,000+ (>10k CO; 28k TX)",
      "Verified Unit Cost (UG vs. CC)": "UG: $2.15M/mi CC: $0.92M/mi",
      "Ignition Risk Reduction": "UG: 98.5% CC: 66.5%",
      "Primary Source": "Xcel WMP Report"
    },
    {
      "Utility or Rebuild Event": "Hawaiian Electric (HECO WSS)",
      "Jurisdiction & Filing": "Oahu, Maui, Hawaii Is. Docket 2025-0156",
      "Undergrounding (Completed / Plan)": "24 mi (85 mi Plan)",
      "Covered Conductor": "110 mi (18 mi in '25)",
      "Poles Replaced": "6,200+ (>2,000 in '25)",
      "Verified Unit Cost (UG vs. CC)": "UG: $3.10M/mi CC: $1.15M/mi",
      "Ignition Risk Reduction": "UG: 99.0% CC: 67.0%",
      "Primary Source": "HECO 2025 WSS"
    },
    {
      "Utility or Rebuild Event": "Victoria PBSP (AusNet & Powercor)",
      "Jurisdiction & Filing": "Victoria, Australia 44 REFCLs + PRF",
      "Undergrounding (Completed / Plan)": "333 mi (536 km) PRF Completed",
      "Covered Conductor": "240 mi +18,000 km REFCL",
      "Poles Replaced": "9,400+",
      "Verified Unit Cost (UG vs. CC)": "UG: $0.42M/mi CC: $0.39M/mi",
      "Ignition Risk Reduction": "UG: 98.5% REFCL: 58.6%",
      "Primary Source": "Vic Auditor-Gen"
    },
    {
      "Utility or Rebuild Event": "2018 Camp Fire Rebuild (PG&E)",
      "Jurisdiction & Filing": "Paradise & Magalia, CA 18,804 Structures",
      "Undergrounding (Completed / Plan)": "200 mi Full Town UG Rebuild",
      "Covered Conductor": "36 mi Feeder Ties",
      "Poles Replaced": "4,600+ (Emergency)",
      "Verified Unit Cost (UG vs. CC)": "UG: $2.30M/mi ($460M Total)",
      "Ignition Risk Reduction": "UG: 99.0%",
      "Primary Source": "PG&E Paradise"
    },
    {
      "Utility or Rebuild Event": "2021 Dixie Fire Rebuild (PG&E)",
      "Jurisdiction & Filing": "Plumas/Butte Co., CA 963,309 Acres",
      "Undergrounding (Completed / Plan)": "28 mi SR-70 & Greenville Canyon",
      "Covered Conductor": "45 mi Hardened OH",
      "Poles Replaced": ">1,050 (Emergency)",
      "Verified Unit Cost (UG vs. CC)": "UG: $3.40M/mi (Hard Rock Canyon)",
      "Ignition Risk Reduction": "UG: 98.5%",
      "Primary Source": "CPUC Res. SED-8"
    },
    {
      "Utility or Rebuild Event": "2023 Maui / Lahaina Rebuild (HECO)",
      "Jurisdiction & Filing": "West Maui, HI 2,200+ Structures",
      "Undergrounding (Completed / Plan)": "15 mi Corridor + Substation Tie",
      "Covered Conductor": "18 mi Steel-Pole OH",
      "Poles Replaced": "400 of 750 (53.3% Lost)",
      "Verified Unit Cost (UG vs. CC)": "UG: $3.25M/mi (300/575 XFMRs)",
      "Ignition Risk Reduction": "UG: 99.0%",
      "Primary Source": "HECO Maui Update"
    },
    {
      "Utility or Rebuild Event": "2024 Smokehouse Creek (Xcel / Co-op)",
      "Jurisdiction & Filing": "Texas Panhandle 1.058M Acres",
      "Undergrounding (Completed / Plan)": "8 mi Critical Crossings",
      "Covered Conductor": "120 mi Feeder Reconductor",
      "Poles Replaced": "8,870 (8k SPS + 870 Co-op)",
      "Verified Unit Cost (UG vs. CC)": "UG: $1.95M/mi CC: $0.78M/mi",
      "Ignition Risk Reduction": "CC/Steel: 64.0%",
      "Primary Source": "NRECA / Xcel TX"
    }
  ],
  "equipment_lead_time_and_ppi_matrix": [
    {
      "Equipment Class & IEEE/ICEA Standard": "Single-Phase Pole-Mounted Transformer (10–100 kVA; IEEE C57.12.20 )",
      "2019 Baseline Lead Time": "4–8 weeks",
      "2022–2024 Peak Lead Time": "52–104 weeks",
      "2026 Current Lead Time": "26–40 weeks",
      "Price / PPI Surge vs. 2019–2020": "+78% to +111% (Spot up to 4x–9x)",
      "Primary Upstream Material & Manufacturing Bottleneck": "GOES / amorphous core slitting capacity; biodegradable natural ester fluid tanks; acute storm/fire restocking."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "Single- & Three-Phase Pad-Mounted Transformer (15–5,000 kVA; IEEE C57.12.34 / C57.12.28)",
      "2019 Baseline Lead Time": "4–8 weeks",
      "2022–2024 Peak Lead Time": "75–120+ weeks (156w custom)",
      "2026 Current Lead Time": "40–60 weeks (52–78w >10 MVA)",
      "Price / PPI Surge vs. 2019–2020": "+86.0% BLS PPI ( PCU335311335311 )",
      "Primary Upstream Material & Manufacturing Bottleneck": "Dead-front tamper-proof enclosures; 80,000+ custom utility SKUs; +497% hyperscale data-center demand surge."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "Subsurface Vault & Submersible Transformer ( IEEE C57.12.23 / C57.12.40 )",
      "2019 Baseline Lead Time": "12–20 weeks",
      "2022–2024 Peak Lead Time": "80–156 weeks",
      "2026 Current Lead Time": "50–104 weeks",
      "Price / PPI Surge vs. 2019–2020": "+95% (+25%–50% over pad-mount)",
      "Primary Upstream Material & Manufacturing Bottleneck": "304L/316L stainless steel corrosion tanks; sealed submersible bushings; compact copper winding footprints."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "Large Power & Substation GSU Transformer (≥100 MVA, >34.5 kV; IEEE C57.12.00)",
      "2019 Baseline Lead Time": "50 weeks",
      "2022–2024 Peak Lead Time": "80–210 weeks (120w avg)",
      "2026 Current Lead Time": "128–160+ weeks",
      "Price / PPI Surge vs. 2019–2020": "+77% LPT / +80% PPI ( WPU117409 )",
      "Primary Upstream Material & Manufacturing Bottleneck": "PDR-grade GOES imports (80%–88% imported); Continuously Transposed Copper (CTC); 130-week HV OIP/RIP bushings."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "MV (15–35 kV) Underground Power Cable (TR-XLPE ICEA S-97-682 & EPR S-94-649 )",
      "2019 Baseline Lead Time": "6–12 weeks",
      "2022–2024 Peak Lead Time": "36–78 weeks",
      "2026 Current Lead Time": "20–52 weeks",
      "Price / PPI Surge vs. 2019–2020": "+99.4% Wire PPI ( WPU10260314 )",
      "Primary Upstream Material & Manufacturing Bottleneck": "Cleanroom TR-XLPE & peroxide semicon compounding; triple-head CCV vulcanization lines; copper concentric neutral wire."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "Triple-Extruded Covered Conductor (\"Tree Wire\") (15–35 kV 3-Layer HDPE/XLPE)",
      "2019 Baseline Lead Time": "8–14 weeks",
      "2022–2024 Peak Lead Time": "32–60+ weeks",
      "2026 Current Lead Time": "20–36 weeks",
      "Price / PPI Surge vs. 2019–2020": "+92.9% Alum PPI ( WPU102501 )",
      "Primary Upstream Material & Manufacturing Bottleneck": "Competes directly with MV underground cable for triple-head co-extrusion lines and UV/track-resistant HDPE compounds."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "SF6-Free / Vacuum Pad Switchgear & Fast-Trip ACRs (15–38 kV Solid-Dielectric / Clean-Air)",
      "2019 Baseline Lead Time": "8–16 weeks",
      "2022–2024 Peak Lead Time": "45–80+ weeks",
      "2026 Current Lead Time": "36–65 weeks",
      "Price / PPI Surge vs. 2019–2020": "+96.0% PPI ( WPU1175 = 433.6 )",
      "Primary Upstream Material & Manufacturing Bottleneck": "Vacuum interrupter bottles; cycloaliphatic epoxy cast resin; CARB/EU SF6 phase-out engineering redesigns."
    },
    {
      "Equipment Class & IEEE/ICEA Standard": "Fire-Resistant Poles (Ductile Iron, Steel & FRP) (Class 1 / H1 Heavy Loading)",
      "2019 Baseline Lead Time": "6–12 weeks",
      "2022–2024 Peak Lead Time": "20–45+ weeks",
      "2026 Current Lead Time": "12–24 weeks",
      "Price / PPI Surge vs. 2019–2020": "+103.5% Steel PPI (2x–4x Wood Cost)",
      "Primary Upstream Material & Manufacturing Bottleneck": "Centrifugal ductile-iron casting & pultruded fiberglass mandrels for >45 ft Class 1/H1 covered-conductor spans."
    }
  ]
}