discipline,discipline_code,campus_it_mw,craft_or_specialist_hours,peak_onsite_headcount,base_burdened_rate_usd_hr,overtime_traveler_rate_usd_hr,base_testing_equipment_usd_m,extended_testing_equipment_usd_m,base_total_cost_usd_m,compressed_surge_cost_usd_m,inflation_delta_usd_m,inflation_delta_pct,primary_bottleneck_note "Electrical Craft (MV/LV Switchgear, Busway, Generators, Power)",electrical_mep,100,720000,420,115.00,155.00,0.00,0.00,82.80,111.60,28.80,34.8,4-5 yr apprenticeship; traveler per-diem & 6x10 OT Mechanical / Pipefitting / Orbital-Weld Liquid Cooling,mechanical_dlc,100,540000,310,110.00,148.00,0.00,0.00,59.40,79.92,20.52,34.5,"Stainless manifolds, CDU piping, 25-micron flushing" Controls / BMS / EPMS / Low-Voltage Integration,controls_bms_epms,100,180000,110,125.00,165.00,0.00,0.00,22.50,29.70,7.20,32.0,"CDU-to-BMS interlocks, switchgear relay telemetry" "Commissioning (L1-L5 CxA, NETA, Liquid/Electrical Load Banks)",commissioning_l1_l5,100,90000,55,185.00,230.00,3.50,5.50,20.15,26.20,6.05,30.0,Includes $3.5M-$5.5M mobile electrical & liquid load banks