Unlike automotive electric-vehicle localization governed under Presidential Regulation No. 79/2023 (analyzed in our Indonesia EV luxury tax exemption dossier), utility power, renewables, and grid equipment are governed jointly by ESDM project-level rules and Kemenperin industrial certification standards.
| Mechanism | Status | Authority | Effective Window | Key Threshold |
|---|---|---|---|---|
| Permen ESDM No. 11/2024 Power Infrastructure Local Content Framework |
Active (Enacted) | Ministry of Energy & Mineral Resources (ESDM) | Effective July 31, 2024; Art. 19 solar import window closed June 30, 2025 | ≥50% multilateral/bilateral funding exemption (Art. 17); pre-end-2024 PPA COD by June 30, 2026 |
| Kepmen ESDM No. 191.K/EK.01/MEM.E/2024 Combined Goods + Services Minimum Schedule |
Active (Enacted) | Ministry of Energy & Mineral Resources (ESDM) / Ditjen EBTKE | Signed Aug 6, 2024 (retroactive to July 31, 2024); active through RUPTL 2025–2034 | PLTS 20%; PLTB 15%; PLTP 24%–29%; PLTA 23%–45%; SUTET 275 kV 65.65% |
| Permenperin No. 33/2024 & No. 34/2024 Legacy Repeal & Solar Module Formula |
Active (Enacted) | Ministry of Industry (Kemenperin) | Enacted July 2024 (revoking Permenperin 54/2012 & 04/2017) | Solar module TKDN weights: 91% materials, 5% direct labor, 4% factory overhead |
| Permenperin No. 35/2025 Horizontal TKDN & BMP Certification Overhaul |
Active (Dec 2025) | Ministry of Industry (Kemenperin) | Issued Sept 11, 2025; effective Dec 11, 2025 (replaces Permenperin 16/2011) | 5-year certificate validity; up to +20% credit for domestic R&D and engineering |
| US–Indonesia ART Selective Waivers Bilateral Reciprocal Trade Carve-Out |
Sector-Specific | Cabinet Secretariat / Kemenko Perekonomian | 2025–2026 bilateral trade cycle | Waives TKDN only for US high-tech/ICT goods lacking Indonesian supply; power floors intact |
For over a decade, Indonesia's power localization rules stalled utility decarbonization. Under Ministry of Industry (Kemenperin) Regulation No. 54/M-IND/PER/3/2012 (amended through Permenperin No. 23/2023) and solar rules under Permenperin No. 04/2017 and No. 05/2017, PT PLN (Persero) utility tenders enforced 40% to 60% module-level domestic content floors despite lacking domestic wafer or cell fabrication.
Local assemblers imported 95% to 100% of solar cells from China while laminating and framing modules domestically. Because Chinese Tier-1 spot imports undercut small-batch local modules by 30% to 50%, and multilateral lenders (World Bank, ADB, KfW, and Just Energy Transition Partnership conduits) bar restrictive local-content mandates in competitive tenders, utility PV auctions repeatedly stalled, delaying disbursements tied to the Indonesia JETP coal phase-out package.
In late July and early August 2024, Jakarta transferred power-sector threshold governance from Kemenperin to the Ministry of Energy and Mineral Resources (ESDM):
Under Permen ESDM 11/2024, compliance is measured across the aggregate contract value of goods plus domestic engineering, construction, and installation services rather than isolated equipment lines. The table below consolidates enacted floors from Kepmen ESDM 191.K/EK.01/MEM.E/2024.
| Infrastructure Segment | Capacity / Voltage Class | Min. Combined TKDN | Supervisory Directorate | EPC & Procurement Implication |
|---|---|---|---|---|
| Solar PV (PLTS) | All utility & centralized classes | 20.00% | Ditjen EBTKE | Achievable via domestic racking, cabling, civil works, and EPC even when cell-level imports dominate, or exceeded with Kendal-assembled modules. |
| Wind Power (PLTB) | All onshore/utility classes | 15.00% | Ditjen EBTKE | Lowest renewable floor; accommodates imported nacelles, blades, and towers while capturing local foundations, cranes, and grid tie-ins. |
| Geothermal (PLTP) | ≤ 60 MW / > 60 MW / Partial | 24.00% / 29.00% / 20.00% | Ditjen EBTKE | Reflects domestic drilling, civil steamfield piping, and balance-of-plant capacity alongside imported turbine-generator packages. |
| Hydropower (PLTA) | ≤10 MW / >10–50 MW / >50 MW | 45.00% / 35.00% / 23.00% | Ditjen EBTKE | Small/mini-hydro carries higher civil and penstock localization; large hydro drops to 23% due to imported large Francis/Pelton turbines. |
| Biomass (PLTBm) & Biogas (PLTBg) | All commercial classes | 21.00% (PLTBm) / 25.19% (PLTBg) | Ditjen EBTKE | Pairs with domestic feedstock logistics; Waste-to-Energy (PLTSa) carries a separate 16.53% combined minimum. |
| Coal Steam (PLTU) | ≤ 600 MW / > 600 MW | 27.18% / 18.83% | Ditjen Gatrik | Ultra-supercritical boilers and steam turbines above 600 MW remain import-intensive; coal fuel supply separately governed by DMO rules. |
| Gas Turbine & Combined Cycle (PLTG / PLTGU / PLTMG) | Open-cycle / Combined-cycle / Gas engine | 10.39% / 21.93% / 23.96% | Ditjen Gatrik | Acknowledges lack of domestic heavy-frame gas turbines while capturing structural steel, HRSG balance, and plant erection. |
| High-Voltage Transmission | SUTT 150 kV / SKTT 150 kV / SUTET 275 kV / SUTET 500 kV | 60.71% / 56.40% / 65.65% / 38.13% | Ditjen Gatrik | Strictest localization in the power sector due to mature Indonesian tower steel, ACSR conductor, and insulator plants. |
| Substations & GIS | GI 150 kV / GITET 275 kV / GITET 500 kV / GIS 150 kV / GIS 500 kV | 39.87% / 24.79% / 13.28% / 12.95% / 17.38% | Ditjen Gatrik | High-voltage SF6 GIS and 500 kV autotransformers remain partially imported; lower-voltage civil works and switchyards localize quickly. |
| Battery Energy Storage (BESS) | Hybrid PLTS-BESS & standalone grid storage | No standalone floor in Kepmen 191.K | Ditjen EBTKE / Gatrik | Evaluated inside project-wide goods + services BoP splits until Indonesia's nickel-LFP battery downstreaming feeds utility grid packs. |
Two special clauses inside Permen ESDM No. 11/2024 reshaped utility project bankability in opposite ways across 2024 and 2026: one durable structural exemption for development-finance capital, and one time-bound solar import bridge that has now closed.
Under Article 17 of Permen ESDM 11/2024, electricity infrastructure funded via foreign development grants or bilateral/multilateral facilities is exempt from Indonesian TKDN thresholds whenever the funding agreement mandates international competitive bidding. Crucially, at least 50% of total project value must originate from multilateral or bilateral development institutions (such as World Bank, ADB, JICA, KfW, or Islamic Development Bank facilities). If DFI participation falls below 50%, full Kepmen 191.K floors bind immediately.
Article 19 offered temporary relief allowing imported non-TKDN solar modules only through June 30, 2025, subject to three cumulative conditions: (1) PPA/PJBL executed by December 31, 2024; (2) RUPTL-scheduled commercial operation by June 30, 2026; and (3) binding supplier commitments to construct Indonesian solar manufacturing lines and meet domestic standards by December 31, 2025. That import waiver expired on schedule on June 30, 2025, shifting all new 2025–2026 PLN tenders onto the 20% combined Kepmen 191.K framework.
Eleven days before the Article 19 import cutoff closed, Indonesia crossed a structural supply threshold. On June 19, 2025, PT Trina Mas Agra Indonesia (TMAI) inaugurated full commercial operations at the Kendal Special Economic Zone in Central Java. Backed by over IDR 1.5 trillion in capital from Trina Solar, Sinar Mas subsidiary PT Daya Sukses Makmur Selaras (PT Dian Swastatika Sentosa Tbk), and PT PLN Indonesia Power Renewables, the plant brings 1 GW per year of n-type TOPCon solar cell and module manufacturing capacity (delivering up to 720 Wp modules) with initial certified TKDN near 41%.
For flagship utility pipelines, including PLN's Hijaunesia tenders, the 92 MWp Saguling floating solar project targeting late-2026 commercial operation, the 100 MWac Karangkates floating solar development in East Java, and Masdar's multi-phase solar expansion following the 145 MWac Cirata plant and Nusantara (IKN) allocations, domestic TOPCon availability eliminates the acute module-certification bottleneck that once forced project sponsors to seek ad hoc ministerial dispensations.
In late 2025 and 2026, two macro policy shifts altered the wider localization landscape without dismantling ESDM's power-sector floors:
Meeting Kepmen ESDM 191.K's minimum percentage avoids administrative disqualification, yet winning competitive PLN IPP or EPC tenders hinges on a second mechanism: Harga Evaluasi Preferensi (HEA), the evaluation-price adjustment applied by state procurement committees.
Verification operates across two distinct tiers. At the factory gate, PT Sucofindo and PT Surveyor Indonesia audit raw material origin invoices, direct Indonesian labor payroll, factory overhead, and (since December 2025) qualifying domestic R&D expenditure to issue an official Tanda Sah TKDN certificate registered with Kemenperin. At the project level, an independent verifier holding an electricity support services license (IUJPTL) audits the combined goods-and-services bill of quantities across EPC execution before final handover, with oversight split between Ditjen EBTKE (renewables) and Ditjen Gatrik (thermal and transmission). Developers can also commission a formal pre-assessment during feasibility design under Permen ESDM 11/2024 to lock down compliance before binding EPC execution.
Because Indonesian-assembled PV modules historically carried a 30% to 50% ex-factory cost premium over Chinese spot imports when local lines relied entirely on imported cells and small volumes, sponsors must model whether the HEA evaluation discount and 20% combined project eligibility outweigh raw module CAPEX inflation in equity IRR models (see our LCOE Calculator and 2026 solar degradation benchmarks).
| Procurement Pathway (100 MWac Utility PLTS) | Module Landed Delta vs. Chinese Spot | Achievable Combined Project TKDN | PLN Tender & Legal Treatment | Equity IRR & Diligence Impact |
|---|---|---|---|---|
| Pathway A: Imported Tier-1 Chinese Modules + Local BoP/EPC | Baseline (Lowest module CAPEX) | ~15%–22% (Civil, piling, AC cabling, local EPC) | Passes 20% Kepmen 191.K floor only if local BoP/services exceed 20% verified under Kepdirjen 150.K; zero goods HEA preference if modules lack TKDN certificate. | Lowest upfront CAPEX, but exposed to verification shortfall risk at IUJPTL closeout and disadvantaged in HEA-weighted PLN BUMN procurement. |
| Pathway B: Kendal-Assembled TOPCon Modules (e.g., TMAI ~41% TKDN) + Local BoP | Narrowing premium (+15%–35% vs. spot, compressing with 1 GW scale) | ~38%–48% combined goods + services | Clears 20% Kepmen 191.K with wide compliance buffer and qualifies for up to 25% goods preference ceiling in PLN HEA bid ranking. | Higher module line-item CAPEX is offset when HEA swings tender award at higher tariff HP, protecting equity returns without waiver dependency. |
| Pathway C: ≥50% Multilateral/Bilateral DFI Structure (Art. 17) | Baseline (International competitive bidding) | Governed by DFI procurement rules | Statutory exemption from Kepmen 191.K floors under Art. 17 Permen ESDM 11/2024; requires verified ≥50% DFI funding share. | Eliminates domestic module premium entirely, preserving lowest LCOE for ADB, World Bank, KfW, or IsDB co-funded projects. |
Under Kepdirjen EBTKE 150.K/2024, developers relying on imported turbines, inverters, or battery packs must ring-fence domestic civil works, site preparation, mounting steel, MV/HV cabling, and local installation inside the same primary EPC contract perimeter. Splitting civil works into a separate landowner SPV strips those local points from the verified combined TKDN denominator.
Grid interconnection assets carry far higher thresholds than generation (60.71% for 150 kV SUTT and 65.65% for 275 kV SUTET). Where an IPP builds a dedicated evacuation line transferred to PLN, failing to source certified Indonesian lattice towers and conductors triggers contract penalties or BPK state-audit objections even when the solar or wind plant itself is compliant.
Sponsors locking EPC contracts in 2026 should verify that supplier Tanda Sah TKDN certificates issued by Sucofindo or Surveyor Indonesia reflect Permenperin 35/2025's five-year cycle and current component prices. A mid-project change in imported solar-cell or LFP-cell origin can invalidate a supplier's certificate between PPA signing and IUJPTL project audit.
All statutory citations, combined percentage thresholds, and effective windows are verified against official Indonesian legislative registers and ministry filings (reviewed November 2026).
Every statutory threshold, exemption cutoff, and tender calculation in this dossier is anchored directly to enacted regulations in the Indonesian Supreme Audit Board (BPK) legislative database, ESDM ministerial decrees, and Kemenperin certification rules cited above. ESI separates legally enacted floors from commercial bid projections.
Connect Indonesian localization rules directly to grid equipment bottlenecks, battery chemistries, and LCOE/LCOS capital models.