India Basic Customs Duty (BCD), AIDC & Renewable Tariff Stack

Under Union Budget 2025-26 (CBIC Notifications 04/2025, 06/2025, and 07/2025-Customs), Indian solar modules carry 20% BCD plus 20% AIDC (40% total, Nil SWS) and solar cells carry 20% BCD plus 7.5% AIDC (27.5% total, Nil SWS). Union Budget 2026-27 (via Notification No. 45/2025-Customs and 02/2026-Customs) eliminated BCD on sodium antimonate for solar glass, extended Nil-BCD machinery waivers to BESS cell lines and critical mineral refining, and paired with 5% renewable IGST under Notification 09/2025-IT(R) while Project Imports (9801) and MOOWR solar power warehousing stay closed.
Modules: 20% BCD + 20% AIDC Cells: 20% BCD + 7.5% AIDC Solar IGST: 5% (Sep 2025) BESS & Minerals CapEx: Nil BCD
Solar Modules (8541 43)
40.0% Total
20% BCD + 20% AIDC; SWS Nil.
Solar Cells (8541 42)
27.5% Total
20% BCD + 7.5% AIDC; SWS Nil.
Renewable IGST Rate
5.0% IGST
Cut from 12% on Sep 22, 2025.
Grid BESS (8507 60)
10.0% BCD
Clarified by Circ. 45/2026-Cus.

India Renewable Customs, Cess & Trade-Remedy Matrix (2022โ€“2026)

Five statutory layers govern port clearance and landed equipment CAPEX for utility solar, C&I open-access, BESS, wind, and manufacturing lines. This dossier isolates fiscal customs mechanics, GST cascades, warehousing bans, and DGTR duties; for MNRE domestic list gating, consult our India ALMM List-I, List-II & List-III Mandate analysis.

Mechanism Status Authority Effective Window Key Threshold
Solar BCD + AIDC Split & SWS Waiver
CBIC Notifs. 04/2025, 06/2025 & 07/2025-Cus
Active Statutory Rate Ministry of Finance / CBIC Effective Feb 2, 2025 onward Modules: 20% BCD + 20% AIDC (40%); Cells: 20% BCD + 7.5% AIDC (27.5%); SWS Nil
Budget 2026-27 Manufacturing & BESS Relief
Notifs. 45/2025-Cus, 02/2026-Cus & Circ. 45/2026
Enacted / Consolidated Union Budget 2026-27 / CBIC Feb 1, 2026 through Mar 2028/2029 Nil BCD on sodium antimonate, BESS cell lines & critical mineral CapEx; 10% BCD on grid BESS
GST / IGST Rate Reduction on Renewables
Notification No. 09/2025-Integrated Tax (Rate)
In Force (56th Council) GST Council / CBIC Effective Sep 22, 2025 onward 5% IGST on solar cells/modules & wind sets (down from 12%); 8.9% blended EPC rate
Project Imports (9801) & MOOWR Closures
Notif. 54/2022-Cus & Notif. 86/2024-Cus (N.T.)
Closed for Solar Power CBIC / Finance Act (No. 2) 2024 Oct 20, 2022 (9801) & Dec 17, 2024 (MOOWR) 7.5% Heading 9801 and Sec. 65 MOOWR duty deferral barred for solar power generation
DGTR Anti-Dumping & Origin Enforcement
11/2025-ADD, 16/2024-ADD & CAROTAR 2020
Active / Pending Cells DGTR / Dept. of Revenue 2024-2029 (Glass/Frames); Cells Pending Glass: $593-$664/MT floor; Frames: $577/MT; China Cells: 23%-30% recommended (pending MoF)

Why India Replaced Pure BCD with the BCD + AIDC Split

India's February 2, 2025 customs overhaul appeared to leave headline solar tariffs intact, yet underneath it executed a major constitutional reallocation across Center-State revenue pools, SWS charges, and umbrella exemption schedules.

1. Finance Commission Revenue Retention

Under Article 270 of the Constitution, Basic Customs Duty enters the divisible tax pool where 41% is devolved to states under the 15th Finance Commission formula. The Agriculture Infrastructure and Development Cess (AIDC) is a Union cess retained 100% by New Delhi. Splitting solar modules into 20% BCD plus 20% AIDC (under Notifications 04/2025-Customs and 06/2025-Customs, amending Notification 11/2021-Customs) preserved the 40% tariff barrier while shifting half of module receipts and roughly 27% of cell receipts outside state sharing.

2. The 20% Industrial Ceiling & Entry 8B SWS Waiver

Budget 2025-26 capped peak industrial BCD at 20%. Previously, a 10% Social Welfare Surcharge (SWS) on BCD pushed total customs levies to 44.0% on modules (40% BCD + 4% SWS) and 27.5% on cells (25% BCD + 2.5% SWS). To stop AIDC from stacking with SWS, Notification No. 07/2025-Customs inserted Entry 8B into Notification No. 11/2018-Customs, waiving SWS completely on 8541 42 00, 8541 43 00, and 8541 49 00. Net customs duties fell from 44.0% to 40.0% on modules and held at 27.5% on cells.

3. Budget 2026-27 Consolidation (Notification 45/2025)

On October 24, 2025, CBIC issued Notification No. 45/2025-Customs, consolidating 31 legacy exemption notifications into one master schedule. Budget 2026-27 amended Table I via Notification No. 02/2026-Customs (effective February 2, 2026): cutting BCD on sodium antimonate (2841 90 00) for solar glass from 7.5% to Nil, extending Nil-BCD machinery exemptions to lithium-ion cell lines for grid-scale BESS, and removing BCD on capital goods for domestic critical mineral refining.

Customs Tariffs vs. ALMM Non-Tariff Gating

Paying the 40% module duty no longer confers open market access. Where MNRE ALMM List-I and List-II rules apply, imported modules are excluded regardless of duty payment, and List-I domestic plants must use domestic List-II cells from June 1, 2026 (save grandfathered bids before August 31, 2025 and open-access projects commissioned by December 31, 2026). The 27.5% cell tariff now governs behind-the-meter captive builds, export SEZs, and grandfathered pipelines. See our companion brief on India Solar-Cell Import Duty Progression.

India Clean-Energy Customs, Cess, ADD & IGST Matrix (2025โ€“2026)

Standard MFN tariff parameters across solar, storage, wind, glass, and mineral lines as of November 2026, prior to any verified FTA preference or conditional exemption.

Equipment / Input (HS Code) BCD AIDC SWS (10% of BCD) DGTR ADD / Trade Remedy IGST Rate
Solar PV Modules & Panels
8541 43 00 / 8541 49 00
20.0%
04/2025-Cus
20.0%
06/2025-Cus
Nil
07/2025-Cus (8B)
Cell ADD (23%-30%) recommended Sep 2025; MoF gazette pending 5.0%
09/2025-IT(R)
Unassembled Solar PV Cells
8541 42 00
20.0%
04/2025-Cus
7.5%
06/2025-Cus
Nil
07/2025-Cus (8B)
China PR AD(OI)-24/2024 final finding 23%-30%; MoF gazette pending 5.0%
09/2025-IT(R)
Textured Tempered Solar Glass
7007 19 00 / 7007 29 00
10.0% Nil 1.0%
10% of 10% BCD
Active (11/2025-ADD): China $658-$664/MT; Vietnam $593-$664/MT floor 18.0%
Anodized Aluminum Module Frames
7610 90 / 7616 99
10.0% Nil 1.0%
10% of 10% BCD
Active (16/2024-ADD): $577/MT China PR; NSR 07/2026-ADD provisional 18.0%
Solar Encapsulants (EVA / POE / EPE)
3920 / 3921
7.5%โ€“10% Nil 0.75%โ€“1.0% Under Probe: AD(OI) 33/2025 (KR/TH/VN) & 34/2025 (CN, ext. late 2026) 18.0%
Solar Inverters (Static Converters)
8504 40 90
7.5% Nil 0.75% None currently active 5% (in solar system) / 18% (standalone)
Stationary / Grid-Scale Li-Ion BESS
8507 60 00
10.0%
45/2025 S.325
Nil 1.0% Clarified by Circ. 45/2026-Cus (not excluded as power bank) 18.0%
Wind Generating Sets & Parts
8502 31 00 / 8503 00 90
7.5%
REEIMS req.
Nil 0.75% Mandatory MNRE REEIMS import filing 5.0% (wind generator)
Sodium Antimonate (Solar Glass Input)
2841 90 00
Nil
Cut from 7.5%
Nil Nil Enacted Budget 2026-27 via 45/2025-Cus Table I amendment 18.0%
BESS Cell Lines & Critical Mineral CapEx
Ch. 84 / 85 & Co / Li Scrap
Nil
2025 & 2026
Nil Nil 35+ EV/BESS capital goods + critical mineral processing + Co/Li scrap 18.0% (creditable by OEM)

CIF-to-Landed Cost Cascade & The Blocked IGST Credit Trap

Under Section 3(7) and Section 3(8) of the Customs Tariff Act, 1975, IGST applies to CIF plus BCD, AIDC, SWS, and any ADD. Whether that IGST is recoverable or permanently sunk depends on whether the importer sells taxable goods or GST-exempt electricity.

Cost Layer (Per $100.00 CIF Base) Pathway A: Imported Modules (8541 43) Pathway B: Imported Cells (8541 42) for Domestic Assembly Pathway C: Grid-Scale BESS (8507 60) per Circ. 45/2026 Pathway D: Standalone Inverter (8504 40 90)
1. Assessable CIF Value $100.00 $100.00 $100.00 $100.00
2. Basic Customs Duty (BCD) $20.00 (20.0%) $20.00 (20.0%) $10.00 (10.0%) $7.50 (7.5%)
3. AIDC (Union Cess) $20.00 (20.0%) $7.50 (7.5%) $0.00 (Nil) $0.00 (Nil)
4. Social Welfare Surcharge (SWS) $0.00 (Entry 8B Nil) $0.00 (Entry 8B Nil) $1.00 (10% of BCD) $0.75 (10% of BCD)
5. Customs Duty Subtotal $40.00 (40.00%) $27.50 (27.50%) $11.00 (11.00%) $8.25 (8.25%)
6. IGST Valuation Base (CIF + Duties) $140.00 $127.50 $111.00 $108.25
7. Statutory IGST Levy $7.00 (5.0%) $6.38 (5.0%) $19.98 (18.0%) $19.49 (18.0%)
8. Gross Port Landed Cost (Pre-ITC) $147.00 (+47.00%) $133.88 (+33.88%) $130.98 (+30.98%) $127.74 (+27.74%)
9. Net Economic Cost (Blocked vs. Creditable ITC) $147.00 (Pure IPP: ITC blocked) / $140.00 (Taxable trader) $127.50 (Domestic OEM offsets $6.38 ITC against module GST) $130.98 (Standalone IPP) / $111.00 (Taxable C&I / OEM) $127.74 (Standalone IPP) / $108.25 (Composite / OEM)

Why Electricity Exemption Blocks IPP Input Tax Credit

Electrical energy (HSN 2716 00 00) is GST-exempt in India. Under Section 17(2) of the CGST Act, 2017, capital goods used exclusively to supply exempt power cannot claim Input Tax Credit (ITC), a position reinforced by state Authority for Advance Rulings decisions. Consequently, the 56th GST Council cut from 12% to 5% (Notification No. 09/2025-Integrated Tax (Rate), effective September 22, 2025) delivered permanent CAPEX savings to IPPs, lowering port-cleared module cost from $156.80 per $100 CIF (at 12% IGST) to $147.00 (at 5% IGST).

Turnkey EPC 70:30 Rule & Standalone BoS Exposure

Composite solar EPC contracts apply a deemed 70:30 split (70% goods at 5%, 30% installation services at 18%), producing an 8.9% blended GST rate. Procuring inverters (8504 40 90), mounting steel, cables, or BESS (8507 60 00) separately outside a qualifying solar system package exposes them to 18% IGST/GST. For pure IPPs facing blocked ITC, unbundled procurement turns a 5% or 8.9% tax line into an unrecoverable 18% CAPEX burden. Model these tax waterfalls inside our LCOE Calculator and LCOS Storage Cost Modeler.

Closure of Heading 9801 Project Imports & Section 65 MOOWR Deferral

Between 2021 and 2024, developers used two customs deferral or concessional pathways to bypass India's 40% solar tariff. Both routes are now legislatively closed for power generation.

Heading 9801 Exclusion (October 2022)

Chapter Heading 9801 historically allowed "All Power Plants and Transmission Projects" to clear equipment at a 5% or 7.5% concessional Project Import rate upon MNRE certification. On October 19, 2022, CBIC issued Notification No. 54/2022-Customs (effective October 20, 2022), excluding "solar power plants" and "solar power projects" from the Project Imports Regulations, 1986. Thermal, hydro, and transmission projects retain the 7.5% baseline, while solar arrays remain locked into Chapter 85 duties.

MOOWR Section 65 Statutory Bar (December 2024)

Under MOOWR, 2019 (Section 65 of the Customs Act), several IPPs imported solar modules duty-deferred into bonded sites treating electricity as the resultant good. After CBIC issued Instruction No. 13/2022-Customs (July 9, 2022) and the Delhi High Court quashed retrospective license reviews on May 6, 2024 (Acme Heergarh Powertech), Section 101 of the Finance Act (No. 2), 2024 amended Section 65(1). CBIC then issued Notification No. 86/2024-Customs (N.T.) (effective December 17, 2024), barring solar electricity generation from Section 65 bonded warehouses.

Where MOOWR Remains Viable: Module & Cell Factories

Notification 86/2024-Customs (N.T.) restricts power generation, not physical manufacturing. Domestic cell and module factories operating under MOOWR or SEZs still import capital machinery duty-deferred and clear export output duty-free. However, clearing finished modules into the Domestic Tariff Area (DTA) triggers full deferred BCD and AIDC on embedded imported cells, glass, or encapsulants. Compare these factory economics with India PLI Solar Modules and solar cell capex incentives.

DGTR Anti-Dumping Stack & CAROTAR 2020 ASEAN Origin Audits

Even domestic module assemblers shielded by ALMM face rising bill-of-materials floors from DGTR component remedies and strict FTA origin enforcement.

Solar Glass & Aluminum Frame Anti-Dumping Floors

Under Notification No. 11/2025-Customs (ADD) (May 8, 2025), India enforced 5-year reference-price anti-dumping duties on textured tempered solar glass (retroactive to December 4, 2024 provisional levies). Whenever landed CIF glass value falls below producer floors ($658-$664/MT for major Chinese suppliers and $593-$664/MT for Vietnam), customs collects the shortfall plus 10% BCD and 1% SWS. Separately, anodized Chinese aluminum frames carry a $577/MT ADD under Notification No. 16/2024-Customs (ADD), with New Shipper Review provisional assessment under 07/2026-Customs (ADD).

Pending Chinese Solar Cell ADD & Encapsulant Probes

On September 29, 2025, DGTR issued final findings in Case AD(OI)-24/2024 recommending a 3-year anti-dumping duty of 23% to 30% of CIF on Chinese solar cells (standalone or inside modules). Because DGTR findings are recommendatory, enforcement requires a Ministry of Finance customs notification, which remains pending as of November 2026. Active encapsulant investigations (AD(OI) 33/2025 on South Korea, Thailand, Vietnam and AD(OI) 34/2025 on China PR) add further cost-pass-through risk alongside critical mineral and wafer concentration.

CAROTAR 2020 Scrutiny on ASEAN Pass-Through

Under Notification No. 81/2020-Customs (N.T.) (CAROTAR, 2020) and Section 28DA of the Customs Act, an ASEAN-India FTA Certificate of Origin no longer secures automatic 0% duty. Importers must hold cost statements, Regional Value Content proofs, and wafer-diffusion records prior to filing the Bill of Entry. Where Chinese wafers or cells undergo minimal assembly in Vietnam, Malaysia, or Thailand, customs suspends preferential clearance, requires a revenue bond/bank guarantee during verification, and assesses the full 27.5% or 40.0% MFN duty retrospectively.

Budget 2026-27 BESS Clarifications, Critical Minerals & Wind REEIMS

While solar modules face high tariff walls, Union Budget 2025-26 and 2026-27 lowered capital goods and mineral input duties for storage, glass kilns, and domestic refining.

Grid-Scale BESS: 10% Pack Duty vs. Nil CapEx Duty

Lithium-ion packs under HS 8507 60 00 carry a concessional 10% BCD (+ 1% SWS, plus 18% standalone IGST) under Serial No. 325 of Notification 45/2025-Customs. After port disputes over "power bank" exclusions, CBIC Circular No. 45/2026-Customs instructed ports to grant the 10% rate to stationary and grid-scale BESS. Upstream, Budget 2026-27 extended Nil-BCD machinery exemptions (building on 35 EV battery items from Budget 2025-26) to BESS cell manufacturing lines, supporting India BESS Viability Gap Funding and battery supply-chain buildout.

Critical Minerals & Solar Glass Inputs

Union Budget 2025-26 exempted BCD on cobalt powder and waste, lithium-ion battery scrap, lead, zinc, and 12 critical minerals (adding to 25 exempted in July 2024). Union Budget 2026-27 granted full BCD exemption on capital goods for processing and refining critical minerals inside India and cut BCD on sodium antimonate (2841 90 00) from 7.5% to Nil for domestic solar glass makers.

Wind Turbines & Mandatory REEIMS Port Filings

Wind generating sets (8502 31 00) and wind parts (8503 00 90) carry 7.5% BCD (+ 0.75% SWS) and qualify for 5% IGST on wind-operated electricity generators under Notification 09/2025-IT(R). Importers must pre-register wind and solar shipments on MNRE's Renewable Energy Equipment Import Monitoring System (REEIMS) before customs clearance. Align import timelines with grid equipment lead times and solar sizing models.

Executive Regulatory Q&A

How did Budget 2025-26 restructure BCD, AIDC, and SWS on imported solar cells and modules?
Effective February 2, 2025 under CBIC Notifications 04/2025, 06/2025, and 07/2025-Customs, India split solar tariffs into BCD plus AIDC while waiving SWS via Entry 8B of Notification 11/2018-Customs. Modules (HS 8541 43 00) moved to 20% BCD plus 20% AIDC and Nil SWS (40% total, down from 44%). Cells (HS 8541 42 00) moved to 20% BCD plus 7.5% AIDC and Nil SWS (27.5% total).
What customs exemptions did Union Budget 2026-27 enact for solar glass, BESS, and critical minerals?
Through amendments to Notification No. 45/2025-Customs (via Notification No. 02/2026-Customs from February 2026), India eliminated the 7.5% BCD on sodium antimonate (HS 2841 90 00) for solar glass, extended Nil-BCD capital goods waivers to lithium-ion cell lines for BESS, and exempted machinery for processing critical minerals. CBIC Circular No. 45/2026-Customs also confirmed stationary BESS (HS 8507 60 00) retains the 10% concessional BCD.
What is the current IGST rate on solar modules and EPC contracts, and can IPPs claim ITC?
Notification No. 09/2025-Integrated Tax (Rate) reduced GST and IGST on solar cells, modules, and wind generators from 12% to 5% effective September 22, 2025. Turnkey solar EPC contracts use a 70:30 split (5% goods, 18% services) for an 8.9% blended rate, while standalone inverters (8504 40 90) and BESS face 18%. Because electricity (HSN 2716 00 00) is GST-exempt, pure IPPs face blocked Input Tax Credit under Section 17(2) of the CGST Act.
Are Heading 9801 Project Imports or MOOWR warehouses still open for solar power plants?
No. Notification No. 54/2022-Customs (effective October 20, 2022) excluded solar plants from Heading 9801 Project Imports. Following Section 101 of the Finance Act (No. 2), 2024, Notification No. 86/2024-Customs (N.T.) (effective December 17, 2024) barred solar electricity generation from Section 65 MOOWR bonded warehouses. Physical module assembly under MOOWR remains permitted, subject to duty payment on Domestic Tariff Area sales.
Which DGTR anti-dumping duties apply across India's solar supply chain in late 2026?
Active CBIC-notified levies include 5-year reference-price ADD on solar glass from China PR ($658-$664/MT) and Vietnam ($593-$664/MT) under Notification 11/2025-Customs (ADD), plus $577/MT ADD on Chinese anodized aluminum frames under 16/2024-Customs (ADD) (with NSR review 07/2026-ADD). DGTR's September 29, 2025 recommendation for 23%-30% ADD on Chinese solar cells (AD(OI)-24/2024) awaits Ministry of Finance gazette notification, while encapsulant probes (AD(OI) 33/2025 and 34/2025) continue.
How does CAROTAR 2020 affect ASEAN solar imports from Vietnam, Malaysia, or Thailand?
Under Notification No. 81/2020-Customs (N.T.) and Section 28DA of the Customs Act, importers claiming AIFTA preferential zero duty must hold bill-of-materials, cell-diffusion records, and Regional Value Content proofs prior to filing the Bill of Entry. Customs can suspend preferential clearance and demand revenue bonds whenever Chinese wafers or cells undergo minimal assembly in ASEAN.

Official Statutory & Regulatory Authorities

All tariff rates, cess splits, GST notifications, and DGTR findings are verified against Government of India primary registers as of November 2026.

Regulatory Verification & Primary Basis

Every tariff rate, cess split, IGST rule, and trade-remedy threshold in this dossier is verified directly against enacted CBIC notifications, Finance Act statutes, and DGTR findings, separating enacted law from pending recommendations.

Primary-Source AnchoringCustoms percentages, SWS waivers, and schedule entries are cross-checked against CBIC notifications (04/2025, 06/2025, 07/2025, 45/2025, 02/2026, and 09/2025-IT(R)) rather than secondary summaries.
Procurement & Tax DiligenceProject sponsors should verify live ICEGATE entries, CAROTAR 2020 origin dossiers, REEIMS filings, and site-specific GST Input Tax Credit recoverability before executing binding supply contracts.