🇻🇳
Corporate Power Procurement · Vietnam · Verified Nov 2026

Vietnam DPPA: Decree 57/2025 & 243/2026 Offtake Rules

Decree No. 57/2025/ND-CP (effective March 3, 2025, replacing Decree 80/2024/ND-CP) and amending Decree No. 243/2026/ND-CP (June 26, 2026) govern Vietnam's Direct Power Purchase Agreements. Corporate buyers procure renewable energy via uncapped physical private-wire lines (20,000 kWh/month floor, 50% rooftop surplus cap) or national-grid Contract-for-Differences across the Vietnam Wholesale Electricity Market (200,000 kWh/month floor, ≥10 MW solar, wind, or biomass).
Decree 57/2025 & 243/2026 Private Wire + VWEM CfD Live Execution (2026)
Operative Framework
57/2025 & 243/2026
Replaced Decree 80/2024; amended Jun 2026
Buyer Consumption Floor
20k / 200k kWh
Monthly avg: private wire vs. grid CfD
Track 2 Plant Floor
≥10 MW
Wind, solar & biomass on VWEM
RTS Surplus Grid Cap
Up to 50%
Raised from 20% under Decree 243/2026

Institutional Regulatory Summary

Mechanism Status Authority Effective Window Key Threshold
Vietnam Direct Power Purchase Agreement (DPPA)
Track 1 Private Wire & Track 2 VWEM Synthetic CfD
Active & Amended Government / MOIT / NSMO Mar 3, 2025 (Decree 57); Jun 26, 2026 (Decree 243) Track 1: ≥20,000 kWh/mo (uncapped tariff, 50% RTS surplus); Track 2: ≥200,000 kWh/mo (≥22 kV) & ≥10 MW plant
Self-Consumption Rooftop Solar & BESS Pairing
Decree 58/2025/ND-CP & Adjusted PDP8 (Decision 768)
Active & Expanded Prime Minister / MOIT / EVN Mar 3, 2025 (Decree 58); Apr 15, 2025 (PDP8); Jun 26, 2026 50% surplus export to Power Corps (exceedable to 2030 if grid allows); 10,000 to 16,300 MW BESS target

Statutory Evolution: From Decree 80/2024 to Decrees 57/2025 and 243/2026

Vietnam replaced an eight-month interim pilot with a statutory corporate procurement regime grounded in Electricity Law 61/2024/QH15, Adjusted PDP8, and Resolution 253/2025/QH15.

Vietnam's corporate renewable procurement regime moved through four legal milestones between mid-2024 and mid-2026. On July 3, 2024, Decree No. 80/2024/ND-CP launched the initial DPPA framework, settling on a 200,000 kWh/month buyer threshold at 22 kV or higher (down from 500,000 kWh/month in earlier drafts) across physical private-wire and national-grid tracks.

Decree 80 operated for only eight months. On November 30, 2024, the National Assembly enacted Electricity Law No. 61/2024/QH15 (effective February 1, 2025), codifying direct power trading, competitive market separation, and battery storage into primary law. On March 3, 2025, the Government issued two companion decrees: Decree No. 57/2025/ND-CP, repealing and replacing Decree 80, and Decree No. 58/2025/ND-CP, governing renewable energy development and self-consumption rooftop solar (RTS).

Six weeks later, Prime Minister Decision No. 768/QD-TTg (April 15, 2025) approved Adjusted PDP8, backed by MOIT Decision 1509/QD-BCT (May 30, 2025). Calibrated for ~10% annual GDP growth in 2026 to 2030, Adjusted PDP8 lifted onshore and nearshore wind targets to 26,000 to 38,029 MW by 2030, expanded offshore wind horizons above 17,000 MW toward 2035, and raised national Battery Energy Storage System (BESS) capacity from 300 MW to 10,000 to 16,300 MW by 2030.

2026 Liberalization: Resolution 253/2025/QH15 & Decree 243/2026/ND-CP

During MOIT's August 2025 implementation review, developers flagged two persistent frictions: statutory generation tariff caps and a 20% RTS surplus ceiling compressed private-wire equity margins, while Track 2 synthetic onboarding required a seven-step clearance across Vietnam Electricity (EVN), the National Power System and Market Operator (NSMO), and MOIT.

National Assembly Resolution No. 253/2025/QH15 (passed December 11, 2025; effective March 1, 2026) removed price caps on physical private-wire DPPAs and integrated licensed industrial-park, economic-zone, export-processing, and high-tech zone electricity retailers. On June 26, 2026, Decree No. 243/2026/ND-CP amended Decrees 57/2025 and 58/2025 immediately, paired with MOIT Circular No. 29/2026/TT-BCT (effective July 20, 2026) governing Vietnam Wholesale Electricity Market (VWEM) dispatch and BESS settlement.

Regulatory Parameter Decree 80/2024 (Repealed) Decree 57/2025 (Mar 2025) Decree 243/2026 & Res. 253 (Jun 2026)
Statutory Anchor 2004 Electricity Law Electricity Law 61/2024/QH15 Law 61/2024 + Res. 253/2025/QH15
Track 2 Technologies Wind and solar (≥10 MW) Added biomass (≥10 MW), small hydro, geothermal, waste-to-energy Expanded solar, wind, biomass, hydro, plus standalone BESS VWEM rules
Buyer Consumption Floor Hardcoded ≥200,000 kWh/mo 200,000 kWh/mo baseline; MOIT flexible authority Track 1 cut to 20,000 kWh/mo; Track 2 kept at 200,000 kWh/mo (data centers & EV hubs added)
Zone Retailers Limited zone intermediary role Initial zone-buyer provisions Full participation as buyers, sellers, or authorized buyer agents
Private-Wire Price Cap Bounded by MOIT ceilings Bounded by MOIT generation brackets Price caps removed; free bilateral negotiation
RTS Surplus Cap to EVN 20% of actual output 20% of actual output Raised to 50% (exceedable to 2030 if local grid absorbs)
Track 2 Onboarding Multi-agency sequential review 7-step approval sequence Compressed to 3 steps via one-time submission

Track 1 Private-Wire vs. Track 2 Grid-Connected Virtual DPPA

Track 1 and Track 2 operate under wholly distinct legal structures, settlement waterfalls, and grid-fee pass-through exposures.

Track 1: Physical Private-Wire Delivery & 50% Surplus Relief

Track 1 connects a renewable generator via a dedicated private line or behind-the-meter array directly to an eligible consumer or industrial-zone retailer without transmitting primary power across EVN's national grid. Because no 10 MW plant floor applies, Track 1 suits factory rooftop solar portfolios, co-located biomass cogeneration, and industrial-park solar-plus-BESS microgrids.

Decree 243/2026/ND-CP materially improved Track 1 bankability. Cutting the buyer floor tenfold to 20,000 kWh/month brings mid-sized Tier-2 textile, food-processing, and electronics suppliers into eligibility. Eliminating MOIT tariff ceilings lets sponsors negotiate tariffs directly against industrial retail benchmarks, while raising EVN's surplus buyback ceiling from 20% to 50% cushions weekend and holiday curtailment. Surplus power sold to EVN clears at the preceding period's average market price capped by MOIT solar brackets, whereas excess sales to licensed industrial-park retailers are uncapped.

Track 2: Three-Contract Synthetic CfD via VWEM & NSMO

Track 2 is not a physical wheeling arrangement outside EVN. Under Circular 16/2025/TT-BCT, successor Circular No. 29/2026/TT-BCT (effective July 20, 2026), and NSMO Official Dispatch No. 1543/NSMO-TTD, Track 2 operates as a three-contract financial Contract-for-Differences (CfD) linking a ≥10 MW VWEM generator with a ≥200,000 kWh/month (≥22 kV) corporate buyer or zone retailer:

  • VWEM Spot PPA: The ≥10 MW generator sells 100% of metered output into the VWEM pool at Full Market Price (FMP = SMP + CAN, System Marginal Price plus capacity add-on).
  • EVN Retail DPPA: The buyer purchases 100% of physical factory consumption from its EVN Power Corporation at pass-through spot plus regulated grid fees.
  • Bilateral CfD Hedge: Generator and buyer settle the financial spread between their contracted strike price and the VWEM spot clearing price.
MOIT / VWEM Buyer Cost Formula: CKH = CĐN + CDPPA + CCL + CBL
CĐN = VWEM spot electricity cost | CDPPA = EVN grid & dispatch service fee (published CDPPAdv) | CCL = CfD difference clearing (subject to PCLmax) | CBL = balancing charge

Under 2026 disclosure rules, EVN must publish historical per-unit grid fees (CDPPAdv) covering transmission, distribution, losses, and system operation alongside escalation bounds (PCLmax). Those non-bypassable fees typically decide whether a 15-year Track 2 CfD delivers net retail savings or carries a modest decarbonization premium.

Cashflow & Risk Item Track 1: Private-Wire Physical DPPA Track 2: National-Grid Virtual / CfD DPPA
Capacity & Load Floor No 10 MW plant floor; buyer ≥20,000 kWh/month Generator ≥10 MW on VWEM; buyer ≥200,000 kWh/month (≥22 kV)
Physical Delivery Dedicated private line / behind-the-meter; bypasses EVN grid 100% physical delivery over EVN transmission/distribution grid
Contract Stack Bilateral physical PPA (+ optional EVN/IP surplus export PPA) VWEM spot PPA + EVN retail supply contract + bilateral CfD
Tariff Regulation Uncapped (Res. 253 & Decree 243 free negotiation) CfD strike price negotiated; spot leg clears at VWEM FMP
EVN Grid Charges Zero on private-wire kWh consumed onsite Buyer pays CDPPA, CCL, and CBL pass-throughs
Surplus & Basis Risk Up to 50% RTS surplus sold to EVN; uncapped to IP retailer Exposed to NSMO dispatch curtailment & hourly SMP depression
Registration Steps Local construction, fire safety, & grid-connection notice 3-step NSMO/EVN one-time application (cut from 7 steps)

2025–2026 MOIT Price Brackets, BESS Adders & Equity Underwriting

MOIT's regional generation ceiling brackets (excl. VAT) anchor EVN surplus buybacks, utility transition PPAs, and competitive CfD strike benchmarks across Vietnam's three load zones.

Issued under Circular No. 09/2025/TT-BCT, MOIT's 2025 and 2026 generation frameworks are denominated in VND/kWh rather than legacy USD Feed-in Tariffs. On November 5, 2026, Decision No. 2946/QD-BCT (solar) and Decision No. 2945/QD-BCT (wind) replaced the 2025 ceilings under Decisions 988/QD-BCT and 1508/QD-BCT. Crucially, Decision 2946 introduced a 14% to 16% storage adder for solar facilities paired with BESS rated at least 10% of plant capacity for 2 hours, aligning tariffs with Adjusted PDP8's evening-ramp targets. Biomass remains capped at 2,091.74 VND/kWh under Decision No. 1008/QD-BCT (April 14, 2025).

Technology & MOIT Decision North (VND/kWh) Central (VND/kWh) South (VND/kWh) Statutory Condition
Ground Solar (No BESS)
Decision 2946/QD-BCT (Nov 5, 2026)
1,591.02 1,293.17 1,104.32 Up from 2025 Dec. 988 (1,012.0–1,382.7); excl. VAT
Ground Solar + BESS
Decision 2946/QD-BCT (Nov 5, 2026)
1,813.48 1,469.90 1,254.97 Requires BESS ≥10% plant MW & ≥2-hour discharge
Floating Solar (No BESS / + BESS)
Decision 2946/QD-BCT (Nov 5, 2026)
1,939.74 / 2,120.31 1,560.63 / 1,703.21 1,340.21 / 1,461.39 Reflects civil anchoring CAPEX & water leasing
Onshore Wind
Decision 2945/QD-BCT (Nov 5, 2026)
2,187.83 1,893.61 2,035.37 Replaces 2025 Decision 1508/QD-BCT; excl. VAT
Nearshore Wind
Decision 2945/QD-BCT (Nov 5, 2026)
2,126.92 2,126.92 2,126.92 Uniform national ceiling across coastal zones
Biomass Power
Decision 1008/QD-BCT (Apr 14, 2025)
2,091.74 2,091.74 2,091.74 0 to 2,091.74 VND/kWh ceiling under Circ. 09/2025

Equity Underwriting & Operational Controls

Asset-backed equity sponsors underwriting Vietnam DPPA cashflows must price four structural constraints into CAPEX and OPEX sensitivity models:

  • VND Settlement vs. USD Equipment CAPEX: Vietnamese FX rules mandate domestic power settlement in VND even when CfD term sheets reference USD exchange bands. Equity IRR models should benchmark imported turbine, module, and inverter costs via LCOE and LCOS calculators against trailing VND depreciation.
  • Hourly VWEM Shape Risk: Midday solar surpluses compress VWEM SMP between 10:00 and 15:00 while industrial plants pull evening baseload. Pairing 2-hour to 4-hour LFP battery storage shifts solar generation into high-SMP evening windows.
  • Grid Interconnection Lead Times: 110 kV and 220 kV substation upgrades govern Track 2 COD dates; developers must track power transformer lead times before committing liquidated damages.
  • Private-Wire Surplus Pricing: Track 1 pro-formas should underwrite EVN surplus sales (up to 50%) at trailing wholesale averages capped by Decision 2946 rather than retail tariff parity.

Committee Check: Modeling Total Track 2 Invoice Spreads

Treasury teams must evaluate the full CKH invoice stack using NSMO's CDPPAdv disclosures. In Central and Southern Vietnam, high irradiation keeps generation LCOE below peak industrial tariffs even after wheeling charges; in Northern Vietnam, tighter spreads favor 110 kV buyers or BESS-paired evening shifting.

First Commercial DPPAs, RE100 Factories & Data Center Load

Multinational electronics, footwear, and hyperscale operators pushed Vietnam's DPPA rollout to replace unbundled I-RECs with traceable, coal-displacing Scope 2 supply.

Global manufacturers including Samsung, Apple, Nike, Lego, and Amkor face binding RE100 and EU CBAM-adjacent supply-chain decarbonization rules across Vietnam. Unbundled I-RECs from legacy FIT assets failed additionality audits, leaving export plants tied to coal-heavy grid factors.

On June 1, 2026, Samsung Electronics Vietnam Thai Nguyen (SEVT) and the TTC Duc Hue 2 Solar Power Plant (49 MWp / 41.4 MWac plus BESS in Tay Ninh, COD May 2026, developed by GEC/TTC Group and advised by Schneider Electric) executed Vietnam's first live Track 2 national-grid DPPA settlement, supplying roughly 70 GWh/year and cutting ~46,000 tonnes of CO2 annually.

On Track 1, Lego's USD 1 billion-plus Binh Duong plant paired onsite solar and BESS with Vietnam-Singapore Industrial Park (VSIP) grid infrastructure. With Decree 243/2026/ND-CP extending Track 2 to data centers and EV charging/battery-swapping hubs while cutting approval to three steps, developers should align yield assumptions with 2026 solar degradation benchmarks, onshore wind economics, and site solar sizing tools, alongside regional peers in ESI's Malaysia CGES and Thailand FIT dossiers.

Executive Regulatory Q&A

Which decree currently governs Vietnam's DPPA mechanism in late 2026?
Decree No. 57/2025/ND-CP (March 3, 2025), amended by Decree No. 243/2026/ND-CP (June 26, 2026), governs Vietnam's DPPA regime. Decree 57/2025 replaced Decree 80/2024/ND-CP to align direct power trading with Electricity Law No. 61/2024/QH15 and Resolution No. 253/2025/QH15.
What is the minimum monthly consumption threshold for DPPA buyers?
Under Decree 243/2026/ND-CP and implementing MOIT rules, Track 1 private-wire DPPA buyers require at least 20,000 kWh per month on average. Track 2 national-grid synthetic DPPA buyers, including data centers and EV charging operators, retain the 200,000 kWh per month floor at ≥22 kV.
Which renewable technologies qualify under Track 2 grid-connected DPPAs?
Whereas Decree 80/2024 limited Track 2 mainly to wind and solar plants ≥10 MW, Decree 57/2025 added biomass power plants (≥10 MW) alongside qualifying small hydro, geothermal, waste-to-energy, and ocean energy facilities participating directly in the Vietnam Wholesale Electricity Market (VWEM).
Are physical private-wire DPPA prices still capped by MOIT brackets?
No. National Assembly Resolution No. 253/2025/QH15 (effective March 1, 2026) and Decree No. 243/2026/ND-CP abolished statutory MOIT tariff ceilings for physical private-wire DPPAs and excess rooftop solar sales to licensed industrial-park retailers, allowing free commercial price negotiation.
How much surplus rooftop solar power can a private-wire project sell to EVN?
Decree 57/2025/ND-CP capped surplus rooftop solar sales to EVN at 20% of actual generation. Decree 243/2026/ND-CP raised the ceiling to 50% of actual output, with higher exports allowed through 2030 where local grid absorption permits, priced against market averages under MOIT caps.
How does settlement work under a Track 2 national-grid synthetic DPPA?
Under Track 2, the ≥10 MW generator sells 100% of metered output into the VWEM spot pool at Full Market Price (SMP plus capacity add-on), the buyer purchases retail power from EVN, and both parties settle a bilateral Contract-for-Differences plus EVN grid service fees (C_DPPA) under Circular 29/2026/TT-BCT.

Official Statutes, Circulars & Market Notices

Citations verified against Vietnamese legislation, Government portals, MOIT decisions, and EVN/NSMO market notices (November 2026).

Regulatory Verification & Primary Basis

All thresholds, surplus export ceilings, and MOIT generation brackets in this briefing trace directly to enacted Vietnamese statutes, ministerial decisions, and NSMO/EVN settlement schedules.

Primary-Source AnchoringParameters track Electricity Law 61/2024/QH15, Decree 57/2025/ND-CP, Resolution 253/2025/QH15, Decree 243/2026/ND-CP, Circular 29/2026/TT-BCT, and Decisions 2945/2946/QD-BCT.
Underwriting ProtocolSponsors and corporate buyers should verify active NSMO registration slots, EVN CDPPAdv grid charges, and local Power Corporation grid absorption capacity before execution.
Reviewed & Verified by Khaled Shawky · Chief Energy Systems & Policy Editor, Energy Solutions Intelligence Verification Cycle: November 2026